Geomega Resources Inc. (“
Geomega” or the
“
Corporation”) (TSX.V: GMA) (OTC: GOMRF), a
developer of clean technologies for the mining, refining, and
recycling of rare earths and other critical materials, is pleased
to provide an update to shareholders on its rare earths recycling
demonstration plant, including certain required project design
modifications, and an update on site preparation activities that
have started at the Saint-Hubert facility.
Project engineering updateThe
past 6 months have been dedicated to bringing engineering to a
sufficient level of completion that it could be tendered to the
construction contractors for execution and completion of the rare
earths recycling demonstration project. Procurement also progressed
and various items were ordered while others were received at the
Saint-Hubert facility during this period. In parallel, permitting
activities have been ongoing at both the municipal and provincial
levels. The objective was to be able to start the construction
activities in February 2024. As a result of providing all the
requested data to the governmental authorities, Geomega was
notified by the municipality of Saint-Hubert, a borough within the
city of Longueuil, that the sewer system capacity is not currently
able to accommodate the water discharges from the cooling tower
that was to be installed for the demonstration plant (please
see September 20, 2023 press release for the 3D model of the
originally intended layout of the plant and cooling tower). Various
solutions have been evaluated by Geomega, including in
collaboration with city engineers, however none were appropriate
for the project due to resulting increased costs, additional
unforeseeable delays, and the overall feasibility of the proposed
solution. As a result, Geomega had to undertake a design change for
the rare earths recycling demonstration plant.
Project design change from batch to
continuous Geomega’s engineering team has begun a design
change for the rare earths recycling demonstration plant from a
batch process to a continuous 24hrs operation with smaller
equipment and lower demand for utilities, most importantly in
regard to the cooling requirements (chillers with a closed loop
operation instead of a cooling tower with regular water discharges
into the municipal sewer system). Despite the design change, the
demonstration plant throughput capacity is planned to remain
unchanged at 1.5 tonnes of feed material per day.
Geomega’s engineering team believes that there
are advantages to the change to continuous design:
- Continuous design is usually
preferred over batch design in industrial operations and was the
ultimate goal for the project in the long-term. Switching to this
design now is much more applicable to the long-term market targeted
by the Corporation, namely swarf recycling from NdFeB magnet
factories that are being planned for Europe and North America. The
first priority of the demonstration plant remains to process end of
life and scrap magnets.
- Continuous design simplifies the
control system, improves the quality of the product and, therefore,
has advantages on both the operating and capital costs of the
demonstration plant.
- The smaller equipment should have
better availability with shorter lead times which should help the
project to remain within the Corporation’s timeline for the rare
earths recycling demonstration plant.
Geomega is aware that such a major design change
may result in significant risks. The following are some of the
primary risks that were considered and are being addressed by the
management and engineering teams at Geomega:
- Engineering – Batch to continuous
design change is an important modification and requires a major
rework of engineering documentation. The current detailed
engineering package can no longer be used for construction as is,
except for some sections. The new engineering package will be using
components from the previous design and will help reduce some
delays.
- Procurement – The design change has
a major impact on size of equipment and on equipment selection. An
ongoing procurement review has already identified equipment that
has been purchased and received but is no longer needed for the
continuous design and has been already put for sale. Other
equipment that has been ordered but not yet received was cancelled.
Replacement equipment is being selected as part of the ongoing
engineering rework and will be ordered as soon as possible.
- Piloting – The batch process was
piloted in 2019 and 2020 with the main objective of scaling it up
and then converting to continuous process. Implementing the scale
up of the process and switching from batch to continuous in one
step is not optimal. On the other hand, the Corporation’s R&D
team has been working over the last year on continuous piloting in
other similar processes. That experience gained provides the
management and engineering teams with the confidence that the
continuous process now proposed for the rare earths recycling
demonstration plant should achieve the set product targets.
- Feed material – Dealing with
end-of-life material always had a risk of feed variability which is
better to adjust to with a batch design. Switching to continuous
design requires a more uniform feed which may have an impact on
sourcing of material and might require blending and preparation of
feed in a way that will not impose significant changes on the
operation conditions.
For ease of reference, a comparison between
batch and continuous design is presented in the table below:
|
Batch Design |
Continuous Design |
Operation schedule |
8-10 hrs per day |
24 hrs per day |
Process cooling technology |
Cooling tower with regular water discharges |
Chillers with closed loop operation |
Magnet throughput capacity |
1.5 tpd |
1.5 tpd |
Heating duty |
1,962 kW |
466 kW |
Cooling duty |
1,940 kW |
449 kW |
Start of Site Preparation Activities at
the Saint-Hubert FacilityFollowing a thorough review of
the required construction activities and the ongoing design change,
the engineering team was able to select several items that are not
being impacted by the design change to continuous operation. In
particular, Geomega has secured the services of a local
construction company that will manage and execute the required
work. The site preparation activities that have begun at the
Saint-Hubert facility include some of the civil work that is not
being affected by the design change, electrical work, installation
of the required fire protection system and the HVAC system for the
rare earths recycling demonstration plant. The majority of that
work is expected to be completed by end of June 2024. Engineering
and procurement work will continue in parallel to these site
preparation activities to avoid any further delays once equipment
installation and assembly is ready to commence.
“We have been working diligently with all the
stakeholders to build a sustainable solution for rare earths
recycling. Although we have some challenging engineering work to do
during the coming months, we are excited to finally start the site
preparation activities at our Saint-Hubert facility. We believe
that the proposed design modifications not only resolve the
obstacle we faced with the municipality’s sewer infrastructure but
overall makes our process a more environmentally sustainable
technological solution to REE recycling, a more robust industrial
application and a better demonstration plant for our future clients
to see. As design modifications and procurement progress during the
coming months, we will be better positioned to provide regular
updates. In addition, I would like to highlight that none of the
recent developments and changes to the REE demonstration plant are
expected to affect our bauxite residues valorization initiatives.
Furthermore, we continue to believe that the centralized facility
in Saint-Hubert is the best available option for both the
demonstration plant and our other R&D activities,” commented
Kiril Mugerman, President & CEO of Geomega.
Addendum to the Last Press
ReleaseGeomega would like to make an addendum to its
January 26, 2024 Press Release relative to the vesting of the
Restricted Share Units (“RSUs”) in order to align with the policies
of the TSX Venture Exchange. The change is as follows:
Vesting and
settlement terms as indicated in the January 26, 2024 press
release: “The RSUs vest over a 2-year period in increments of 25%
every 6 months and may be settled after 3 years.”
The corrected vesting
and settlement terms: “The RSUs vest over a 2-year period in
increments of 50% every year and may be settled after 3 years.”
The rest of the information presented in the
January 26, 2024 press release remains unchanged.
About Geomega
(www.geomega.ca)Geomega
develops innovative technologies for extraction and separation of
rare earth elements and other critical metals essential for a
sustainable future. With a focus on renewable energies, vehicle
electrification, automation and reduction in energy usage, rare
earth magnets or neo-magnets (NdFeB) are at the center of all these
technologies. Geomega’s strategy revolves around gradually
de-risking its innovative technology and delivering cashflow and
return value to shareholders while working directly with the main
players in these industries to recycle the magnets that power all
those technologies.
As its technologies are demonstrated on larger
scales, Geomega is committed to work with major partners to help
extract value from mining feeds, tailings and other industrial
residues which contain rare earths and other critical metals.
Irrespective of the metal or the source, Geomega adopts a
consistent approach to reduce the environmental impact and to
contribute to lowering greenhouse gases emissions through recycling
the major reagents in the process.
Geomega’s process is based around its
proprietary, low-cost, environmentally friendly way to tap into a
C$1.5 billion global market to recycle magnet production waste and
end of life magnets profitably and safely.
Geomega also owns the Montviel rare earth
carbonatite deposit, the largest 43-101 bastnaesite resource
estimate in North America and holds over 16.8M shares, representing
approximately 14% of the issued and outstanding shares, of Kintavar
Exploration Inc. (KTR.V), a mineral exploration company that is
exploring for copper projects in Quebec, Canada.
For further information, please
contact:
Kiril Mugerman |
President and CEO |
Geomega |
450-641-5119 ext.5653 |
kmugerman@geomega.ca |
|
Nancy Thompson |
Vorticom Public Relations |
212-532-2208 |
nancyt@vorticom.com |
X: @Geomega_REE |
Cautions Regarding Forward-Looking
Statements Neither TSX Venture Exchange nor its Regulation
Services Provider (as that term is defined in the policies of TSX
Venture Exchange) accepts responsibility for the adequacy or
accuracy of this release.
This news release contains statements that may
constitute “forward-looking information” or “forward-looking
statements” within the meaning of applicable Canadian securities
legislation. Forward-looking information and statements may
include, among others, statements regarding future plans, costs,
objectives or performance of the Corporation, or the assumptions
underlying any of the foregoing. In this news release, words such
as “may”, “would”, “could”, “will”, “likely”, “believe”, “expect”,
“anticipate”, “intend”, “plan”, “estimate” “target” and similar
words and the negative form thereof are used to identify
forward-looking statements. Forward-looking statements should not
be read as guarantees of future performance or results, and will
not necessarily be accurate indications of whether, or the times at
or by which, such future performance will be achieved. No assurance
can be given that any events anticipated by the forward-looking
information will transpire or occur, including as regards the
commercialization of any of the technology referred to above, or if
any of them do so, what benefits the Corporation will derive.
Forward-looking statements and information are based on information
available at the time and/or management's good-faith belief with
respect to future events and are subject to known or unknown risks,
uncertainties, assumptions and other unpredictable factors, many of
which are beyond the Corporation’s control. These risks,
uncertainties and assumptions include, but are not limited to,
those described under “Risk Factors” in the Corporation’s annual
management’s discussion and analysis for the fiscal year ended May
31, 2023, which is available on SEDAR at www.sedar.com; they could
cause actual events or results to differ materially from those
projected in any forward-looking statements. The Corporation does
not intend, nor does the Corporation undertake any obligation, to
update or revise any forward-looking information or statements
contained in this news release to reflect subsequent information,
events or circumstances or otherwise, except if required by
applicable laws.
Geomega Resources (TSXV:GMA)
過去 株価チャート
から 11 2024 まで 12 2024
Geomega Resources (TSXV:GMA)
過去 株価チャート
から 12 2023 まで 12 2024