TORONTO, May 4, 2020 /PRNewswire/ -- Americas Gold
and Silver Corporation (TSX: USA)
(NYSE American: USAS) ("Americas" or the "Company"), a growing
North American precious metals producer, today provided an
operations update.
Summary
- Relief Canyon poured first gold in mid-February 2020 and the Company remains
confident that commercial production can be achieved towards the
end of Q2-2020 or beginning of Q3-2020 despite the challenges
presented by COVID-19.
- While Relief Canyon has been operating through the COVID-19
pandemic, ramp-up has been slower than anticipated due to an
inability to get key management and consultants to site to
troubleshoot common start up challenges.
- All operating aspects of Relief Canyon have now started to meet
budget parameters. Waste movement is ahead of budget and there is
an ore stockpile of over 0.2 million tonnes. As of April 30, 2020, approximately 3.3 million tonnes
of material have been mined, including 2.5 million tonnes of waste
and 0.8 million tonnes of ore.
- Ore gold grade mined and early grade reconciliation are in-line
with the mine plan.
- Ore leaching has been slower than planned, a common issue when
commissioning heap leach operations. Pregnant solution grade and
solution application rate are now nearing design levels following
improvements to agglomeration, solution application and stacking
practices.
- The Galena recapitalization plan ("Recapitalization Plan") is
proceeding better than expectations with the Company seeing
benefits in both production and exploration. The Company plans to
update the market on this asset on a more regular basis moving
forward.
- The Mexican government issued a national decree to suspend
non-essential businesses in relation to the COVID-19 pandemic until
the end of May. This order affects all mining operations.
- Due to the rapidly changing and on-going uncertainty caused by
the COVID-19 pandemic, which has resulted in the reduced ability to
adequately meet the normal commissioning challenges at Relief
Canyon with the COVID-19 limitations in place and impact to the
Cosalá Operations, the Company has decided to withdraw its
full-year 2020 guidance.
- Outlook for 2021 continues to be 90,000 to 110,000 gold
equivalent ounces which assumes Relief Canyon is fully ramped up to
commercial production and the Cosalá Operations has resumed normal
operations and expected production.
- As of March 31, 2020, the Company
had cash and cash equivalents of $16.3
million which includes funds under the Galena
Recapitalization Plan.
"All aspects of the Relief Canyon mine are starting to perform
near design capacity following some initial teething pains common
to commissioning a new operation. These start-up challenges
took slightly longer to remediate due to travel and operational
restrictions caused by the COVID-19 pandemic. However, Relief
Canyon is now well on its way to a successful ramp-up.
Americas Gold and Silver is closely monitoring developments
regarding the outbreak of COVID-19 and our priority is to protect
the health and safety of our employees by providing a safe work
environment," said Americas President & CEO Darren Blasutti.
Relief Canyon
Relief Canyon successfully poured its first gold in mid-February 2020 with initial construction
completed nine months after construction formally commenced in
mid-May 2019. The initial capital spend to first production
was within the guidance range the Company provided of US$28 to US$30
million.
The Company is targeting commercial production by the end of
Q2-2020 or beginning of Q3-2020, which represents a potential delay
of approximately one month from the previous expectations.
While operations continue during the COVID-19 pandemic, the Company
has been limited in its ability to promptly troubleshoot ramp-up
issues often present when commissioning a new mine.
Mining rates have steadily increased and total tonnes mined are
close to budget. As of April 30,
2020, approximately 3.3 million tonnes of material have been
mined, including 2.5 million tonnes of waste and 0.8 million tonnes
of ore. Waste movement is ahead of budget and the operation
currently has an ore stockpile of approximately 0.2 million tonnes
ahead of the crusher waiting to be placed on the leach pad.
To-date, approximately 0.6 million tonnes of ore have been stacked
on the leach pad.
Mined ore grade is reconciling well to the block model.
Ore grade from these early phases of the mine plan are lower than
the life of mine average grade and the Company expects mined ore
grade to increase towards the end of the year and into 2021.
Ore crushing and stacking rates are steadily increasing.
Following the first gold pour in February, solution flow rates
to the leach pad increased at a slower rate than anticipated.
The Company is confident that measures taken in the past five
weeks, including improved agglomeration and stacking practices,
will allow the operation to continue its ramp-up to feasibility
study targets. Solution and grade are now on-track to meet
expectations and any placed ounces will be recovered through the
leach cycle.
Galena Complex
The Galena Complex is benefiting from the previously announced
Recapitalization Plan that commenced in October 2019. The
Recapitalization Plan improves productivity in the short term with
the purchase and refurbishment of underground mining
equipment. Underground development improvements, additional
equipment procurements, and an exploration drilling program will
benefit the operation longer term by further improving mining
efficiency and lowering cash costs. Exploration is aimed at
adding mineral resources with exploration success already realized
in Q1-2020.
Production
The Recapitalization Plan is still in the early stages of
implementation but the Company is already starting to see the
benefits in terms of production and a reduction in cash operating
costs. The Galena Complex increased production and lowered
cash costs in Q1-2020 compared to Q4-2019; silver and lead
production increased by 44% and 67% respectively. During the
Recapitalization Plan, the Company has chosen to exclude production
and cost figures from the outlook but feel that it is important to
provide an update to the significant improvements already
demonstrated by the operation.
Development
Redevelopment of existing infrastructure is progressing on the
4300 and 5500 Levels which includes drift rehabilitation and rail
replacement. On the 4300 Level, drift rehabilitation is over
70% complete, with new rail placement over 60% complete. The
4300 Level rehabilitation is expected to be finished by the end of
May 2020. A recently developed drill station on the 4300
Level will facilitate testing of up-dip extensions of
silver/lead-rich zones starting in mid-May 2020. The 5500
Level drift rehabilitation is complete and rail installation is
well underway. Additionally, ramp development between the
5200 and 5500 Levels is proceeding according to plan. This
ramp development provides access to two mining fronts, which when
complete, will allow more efficient movement of equipment and
workers between levels. Repair of the lowest loading pocket
is also proceeding, which when finished, will allow material to be
hoisted from the 5500 Level.
Equipment
With the Recapitalization Plan, the operation has acquired
several new pieces of equipment to help improve productivity.
A 4-yard scoop and a single boom jumbo are now in service.
Two 3.5-yard scoops are on-site, being disassembled for
shipment and reassembly underground.
Exploration
The Recapitalization Plan has budgeted approximately 39,000
meters of exploration drilling with over 9,000 meters (or over 20%)
complete. Based on the current drill plan, the Company
expects drilling to finish in approximately 15 months with two
drills in operation. Targets include up-dip and down-dip
extensions of known veins, with emphasis on untested zones below
the 5500 Level, which is the deepest working level of the
mine. Additionally, a new geologic model is partially
complete. The geologic model will be used for target
improvements in the near term and exploration for new orebodies
longer term.
Drilling on the 3200 Level extended the strike and dip length of
several veins with widths and grades the Company expects to be
economic in the future. Five veins in the Upper Country Lead
Zone (UCLZ) were extended between 37 and 61 meters to the
east. These veins are adjacent to current production areas on
the level. The 133 vein was extended 107 meters along strike
and 70 meters up-dip and down-dip. A 9.1-meter siderite vein
zone was crossed 500 meters north of the 3200 Level in an area
previously untested on the South Argentine fault. This zone
has the potential to be a new orebody and will be explored from the
4300 and 5500 Levels as drilling continues. The current 3200
Level drill program will be completed in early May, followed by
drilling on the 4300 Level targeting upper extensions of the 360
vein system.
Drilling from the 5200 Level has focused on deep extensions of
mineralization centred around the 291 and 360 vein systems with
encouraging results. The two deepest holes project-to-date
include the highest-grade values. Hole 52-493 crossed the 291
vein more than 60 meters below the current mineral resource with an
interval grading 3,020 grams per tonne silver over a true width of
1.4 meters. In drill hole 52-501, a new vein was crossed in
the footwall of the 360 vein approximately 85 meters below the 5200
Level. The unnamed vein assayed 2,123 grams per tonne silver
over 0.8 meters and has the potential to become a new mining front
with additional drilling.
The 16-hole drill program on 5200 Level is nearing
completion. Drilling will commence from the 5500 Level in
mid-May, targeting what the Company's geologists believe to be some
of the most prospective targets in the mine. This includes
the down-dip projection of the 72 vein, which was the main source
of ore during the peak silver production years of 2000-2004.
Drilling will focus on areas to the east and below historical
workings, which produced average grades of over 680 grams per tonne
silver. In addition to targeting the 72 vein, exploration
will focus on what has been described as the "triple point", where
the high-grade 175, 185 and Silver veins are projected to
converge. This area has never been explored and is projected
to be 100 meters below historical workings. Follow-up
drilling in the 291 and 360 vein systems is also planned from 5500
Level and is designed to extend these zones down-dip.
The following table summarizes the most significant intercepts
of the program to date:
Hole
|
Vein
|
Zone
|
From
(m)
|
To
(m)
|
True
Width
(m)
|
Ag
(g/t)
|
Pb
(%)
|
Cu
(%)
|
AgEq1
(g/t)
|
32-091
|
4
|
UCLZ
|
29.8
|
30.9
|
0.9
|
467
|
5.9
|
-
|
704
|
|
3
|
UCLZ
|
52.3
|
54.4
|
1.8
|
283
|
9.8
|
-
|
675
|
32-092
|
4
|
UCLZ
|
26.6
|
27.5
|
0.9
|
250
|
9.7
|
-
|
638
|
32-093
|
5
|
UCLZ
|
32.6
|
34.4
|
0.8
|
447
|
16.9
|
-
|
1,122
|
|
133
|
UCLZ
|
153.0
|
153.9
|
0.7
|
306
|
9.9
|
-
|
704
|
32-096
|
Fuller
|
UCLZ
|
49.1
|
50.1
|
1.0
|
251
|
15.9
|
-
|
887
|
|
133
|
UCLZ
|
86.9
|
87.2
|
0.3
|
343
|
15.2
|
-
|
951
|
32-097
|
4B
|
UCLZ
|
30.0
|
31.4
|
1.1
|
301
|
12.3
|
-
|
793
|
|
133
|
UCLZ
|
140.5
|
141.3
|
0.7
|
593
|
19.9
|
-
|
1,390
|
32-099
|
5
|
UCLZ
|
59.4
|
61.1
|
1.0
|
159
|
11.8
|
-
|
632
|
|
3
|
UCLZ
|
84.4
|
85.2
|
0.6
|
331
|
11.4
|
-
|
787
|
52-487
|
242
|
291 System
|
124.5
|
125.9
|
1.0
|
312
|
12.4
|
-
|
809
|
including
|
242
|
|
124.5
|
125.0
|
0.3
|
837
|
32.6
|
-
|
2,141
|
52-488
|
348
|
360 System
|
75.9
|
78.7
|
2.6
|
271
|
12.6
|
-
|
777
|
52-490
|
|
|
89.4
|
90.1
|
0.4
|
1,295
|
5.5
|
0.5
|
1,572
|
52-491
|
291
|
291 System
|
99.5
|
100.7
|
1.2
|
1,430
|
-
|
0.9
|
1,531
|
including
|
|
|
100.5
|
100.7
|
0.2
|
7,544
|
-
|
4.7
|
8,083
|
52-493
|
291
|
291 System
|
154.9
|
156.7
|
1.4
|
3,020
|
-
|
2.3
|
3,284
|
including
|
|
|
155.4
|
156.7
|
1.0
|
4,252
|
-
|
3.2
|
4,623
|
52-494
|
291
|
291 System
|
122.3
|
124.8
|
2.1
|
430
|
-
|
0.5
|
489
|
52-495
|
291
|
291 System
|
132.7
|
133.7
|
0.8
|
473
|
-
|
0.4
|
518
|
52-496
|
291
|
291 System
|
206.3
|
207.6
|
0.9
|
892
|
-
|
2.9
|
1,221
|
52-499
|
370
|
360 System
|
252.7
|
254.1
|
0.7
|
378
|
9.2
|
-
|
750
|
|
360
|
360 System
|
257.5
|
258.4
|
0.4
|
1,737
|
25.9
|
0.3
|
2,803
|
52-501
|
239
|
291 System
|
147.0
|
148.3
|
0.7
|
373
|
12.3
|
-
|
867
|
including
|
|
|
147.3
|
147.4
|
0.1
|
1,156
|
38.5
|
-
|
2,696
|
including
|
|
|
147.8
|
148.0
|
0.1
|
1,101
|
34.2
|
-
|
2,469
|
52-501
|
368
|
360 System
|
229.4
|
230.6
|
0.6
|
800
|
26.6
|
-
|
1,863
|
52-501
|
370
|
360 System
|
232.9
|
234.1
|
0.7
|
422
|
16.1
|
-
|
1,066
|
52-501
|
360
|
360 System
|
256.4
|
258.9
|
1.3
|
364
|
5.8
|
-
|
596
|
including
|
|
|
257.2
|
257.4
|
0.1
|
2,428
|
39.1
|
-
|
3,992
|
52-501
|
|
360 System
|
321.2
|
323.2
|
0.8
|
2,123
|
-
|
0.9
|
2,232
|
including
|
|
|
321.2
|
321.9
|
0.3
|
4,595
|
-
|
1.9
|
4,817
|
A full table of all drill results is available on our website
at:
https://www.americas-gold.com/site/assets/files/5450/dr20200504.pdf
Cosalá Operations
On March 31, 2020, the Government
of Mexico issued a national
COVID-19 related decree for the temporary suspension of all
non-essential businesses in the country, including all mining
operations, until at least the end of May. At this time, the
Company's Cosalá Operations continue to be illegally occupied (see
Company news release dated February
3, 2020). While the Company cannot negotiate with the
self-interested representatives of this illegal action, it is
optimistic that a legal and legitimate labour representative for
its workers will be identified, and the mine will be in a position
to re-open after any COVID-19 restrictions are lifted. The
Company's priority continues to be the safety of its workers and
the community of Cosalá that have been negatively impacted – first
by the illegal blockade and now by the COVID-19 pandemic.
2020 Guidance Withdrawal and Q1 2020 Quarterly Results
Update
The Company continues to assess the potential impacts of the
COVID-19 pandemic on operations during this unprecedented
period. Due to the rapidly changing and on-going uncertainty
caused by the COVID-19 pandemic, which has resulted in a reduced
ability to efficiently meet normal commissioning challenges at
Relief Canyon with the COVID-19 limitations in place and impact to
the Cosalá Operations, the Company has decided to withdraw the
full-year 2020 guidance. The Company believes it is prudent
to take this step as the global COVID-19 pandemic continues to
develop, particularly given the significant risk related to the
potential for additional government laws, regulations or other
measures that might be required that could impact its ability to
operate, such as business disruptions in supply chains, disruptions
in the markets for our products, commodity prices generally as well
as global health and economic impacts. The Company will
continue to target safe and effective execution of its operation
and production plans. The Company does not expect that these
factors will materially impact its growth plans and the previously
provided outlook for 2021 and beyond, as applicable, to the extent
that commercial production is achieved at Relief Canyon on the
currently expected timing in 2020 and resumption at the Cosalá
Operations of normal operations and production occurs by the end of
2020.
The Company expects to provide updated financial and quarterly
production results with its Q1-2020 release. The Company will
provide updated timing and details of our quarterly conference call
in advance.
Technical Information
The diamond drilling program used NQ-size drilling.
Americas Gold and Silver's standard QA/QC practices were utilized
to ensure the integrity of the core and sample preparation at the
Galena Complex through delivery of the samples to the assay
lab. The drill core was stored in a secure facility,
photographed, logged and sampled based on lithologic and
mineralogical interpretations. Standards of certified
reference materials, field duplicates and blanks were inserted as
samples shipped with the core samples to the lab.
Analytical work was carried out by American Analytical Services
Inc. ("AAS") located in Osburn, Idaho. AAS is an independent,
ISO-17025 accredited laboratory. Sample preparation includes
a 30-gram pulp sample analyzed by atomic absorption spectrometry
("AA") techniques to determine silver, copper, and lead, using aqua
regia for pulp digestion. Samples returning values over
514g/t Ag are re-assayed using fire-assay techniques for silver.
Additionally, samples returning values over 23% Pb are
re-assayed using titration techniques.
Duplicate pulp samples were sent out quarterly to ALS Global, an
independent, ISO-17025 accredited laboratory based in Reno, Nevada to perform an independent check
analysis. A conventional AA technique was used for the
analysis of silver, copper and lead at ALS Global with the same
industry standard procedures as those used by AAS. The assay
results listed in this report did not show any significant
contamination during sample preparation or sample bias of
analysis.
About Americas Gold and Silver Corporation
Americas Gold and Silver Corporation is a high-growth precious
metals mining company with multiple assets in North America. The Company's newest
asset, Relief Canyon in Nevada,
USA, has poured first gold and is expected to ramp up to
full production over the course of 2020. The Company also
owns and operates the Cosalá Operations in Sinaloa, Mexico and manages the 60%-owned
Galena Complex in Idaho, USA.
The Company also holds an option on the San Felipe development project in Sonora, Mexico. For further information,
please see SEDAR or www.americas-gold.com.
For more information:
Stefan
Axell
|
Darren
Blasutti
|
VP, Corporate
Development & Communications
|
President and
CEO
|
Americas Gold and
Silver
Corporation
|
Americas Gold and
Silver Corporation
|
416-874-1708
|
416‐848‐9503
|
Qualified Persons
Niel de Bruin, Director of
Geology and a Qualified Person under Canadian Securities
Administrators guidelines, has approved the applicable contents of
this news release.
Cautionary Statement on Forward-Looking Information:
This news release contains "forward-looking information" within
the meaning of applicable securities laws. Forward-looking
information includes, but is not limited to, Americas Gold and
Silver's expectations, intentions, plans, assumptions and beliefs
with respect to, among other things, estimated production rates and
results for gold, silver and other precious metals, as well as the
related costs, expenses and capital expenditures, the Company's
construction, production, development plans and performance
expectations at the Relief Canyon Mine, including the anticipated
timing of commercial production at Relief Canyon, the resolution
and removal of the illegal blockade at the Company's Cosalá
Operations and the resumption of mining and processing
operations. Often, but not always, forward-looking
information can be identified by forward-looking words such as
"anticipate", "believe", "expect", "goal", "plan", "intend",
"potential', "estimate", "may", "assume" and "will" or similar
words suggesting future outcomes, or other expectations, beliefs,
plans, objectives, assumptions, intentions, or statements about
future events or performance. Forward-looking information is
based on the opinions and estimates of Americas Gold and Silver as
of the date such information is provided and is subject to known
and unknown risks, uncertainties, and other factors that may cause
the actual results, level of activity, performance, or achievements
of Americas Gold and Silver to be materially different from those
expressed or implied by such forward-looking information.
With respect to the business of Americas Gold and Silver, these
risks and uncertainties include risks relating to widespread
epidemics or pandemic outbreak including the COVID-19 pandemic; the
impact of COVID-19 on our workforce, suppliers and other essential
resources and what effect those impacts, if they occur, would have
on our business, including our ability to access goods and
supplies, the ability to transport our products and impacts on
employee productivity, the risks in connection with the operations,
cash flow and results of the Company relating to the unknown
duration and impact of the COVID-19 pandemic; interpretations
or reinterpretations of geologic information; unfavorable
exploration results; inability to obtain permits required for
future exploration, development or production; general economic
conditions and conditions affecting the industries in which the
Company operates; the uncertainty of regulatory requirements and
approvals; fluctuating mineral and commodity prices; the ability to
obtain necessary future financing on acceptable terms or at all;
the ability to develop, complete construction, bring to production
and operate the Relief Canyon Project; and risks associated with
the mining industry such as economic factors (including future
commodity prices, currency fluctuations and energy prices), ground
conditions and other factors limiting mine access, failure of
plant, equipment, processes and transportation services to operate
as anticipated, environmental risks, government regulation, actual
results of current exploration and production activities, possible
variations in ore grade or recovery rates, permitting timelines,
capital and construction expenditures, reclamation activities,
labor relations or disruptions, social and political developments
and other risks of the mining industry. The potential effects
of the COVID-19 pandemic on our business and operations are unknown
at this time, including the Company's ability to manage challenges
and restrictions arising from COVID-19 in the communities in which
the Company operates and our ability to continue to safely operate
and to safely return our business to normal operations. The
impact of COVID-19 on the Company is dependent on a number of
factors outside of its control and knowledge, including the
effectiveness of the measures taken by public health and
governmental authorities to combat the spread of the disease,
global economic uncertainties and outlook due to the disease, and
the evolving restrictions relating to mining activities and to
travel in certain jurisdictions in which it operate. Although
the Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
forward-looking information, there may be other factors that cause
results not to be as anticipated, estimated, or intended.
Readers are cautioned not to place undue reliance on such
information. Additional information regarding the factors
that may cause actual results to differ materially from this
forward‐looking information is available in Americas filings with
the Canadian Securities Administrators on SEDAR and with the SEC.
Americas does not undertake any obligation to update publicly
or otherwise revise any forward-looking information whether as a
result of new information, future events or other such factors
which affect this information, except as required by law.
Americas does not give any assurance (1) that Americas will
achieve its expectations, or (2) concerning the result or timing
thereof. All subsequent written and oral forward‐looking
information concerning Americas are expressly qualified in their
entirety by the cautionary statements above.
Cautionary Note to U.S. Investors:
The terms "proven and probable reserve", "resource", "measured
resource", "indicated resource", and "inferred resource" used in
the press release are mining terms used in accordance with Canadian
National Instrument 43-101 - Standards of Disclosure for Mineral
Projects under the guidelines set out in the Canadian Institute of
Mining, Metallurgy and Petroleum Standards. Mineral resources
which are not mineral reserves do not have demonstrated economic
viability.
While the terms "mineral resource", "measured mineral resource",
"indicated mineral resource", and "inferred mineral resource" are
recognized and required by Canadian regulations, they are not
defined terms under standards in the
United States and normally are not permitted to be used in
reports and registration statements filed with the Securities &
Exchange Commission ("SEC"). Moreover, the definitions of
proven and probable reserves used in NI 43-101 differ from the
definitions in the United States
Securities and Exchange Commission's Industry Guide 7. As
such, information contained in the Company's disclosure concerning
descriptions of mineralization, reserves and resources under
Canadian standards may not be comparable to similar information
made public by U.S companies in SEC filings. With respect to
"inferred mineral resource" there is a great amount of uncertainty
as to their existence and a great uncertainty as to their economic
and legal feasibility. It cannot be assumed that all or any
part of an "inferred mineral resource" will ever be upgraded to a
higher category. Investors are cautioned not to assume that
any part or all of the mineral deposits in these categories will
ever be converted into reserves.
1 AgEq was calculated using metal prices of
$18.00/oz silver, $3.00/lb copper and $1.05/lb lead
View original content to download
multimedia:http://www.prnewswire.com/news-releases/americas-gold-and-silver-corporation-provides-operations-update-301051647.html
SOURCE Americas Gold and Silver Corporation