TIDMBSE
AIM and Media Release
25 July 2023
Base Resources Limited
Quarterly Activities Report - June 2023
African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (Base
Resources or the Company) is pleased to provide an operational, development and
corporate update for the quarter ended 30 June 2023.
KEY POINTS
· FY23 production guidance achieved and FY24 production guidance released.
· Prices were steady for ilmenite and slightly lower for rutile, while zircon
prices moderately increased.
· Mining volumes increased to 4.1Mt following a stoppage in the prior quarter
for the transition of half the mining operations to the North Dune.
· Exploration drill results from Kwale East confirmed the presence of heavy
mineral, with a peak drill hole grade of 6.3% heavy mineral, as well as a high
value mineral assemblage. Three areas were identified for further targeted
exploration as part of a second phase air core drilling program.
· Results from the first phase of drilling at the Umba South exploration
project in Tanzania confirmed rutile mineralisation was present but a number of
factors were identified limiting the project's economic potential, with further
exploration activity paused pending receipt of assay results from a second phase
infill drilling program.
· Engagement with the Government of Madagascar on Toliara Project fiscal
terms, and lifting of the project's on-ground suspension, has been limited
during the quarter due to the Government focus on an overhaul of the Malagasy
Mining Code and preparations for the upcoming Presidential elections. While the
Company remains committed to developing the world class project and is ready to
progress, until the Mining Code reform is finalised, and the elections scheduled
for late 2023 have concluded, the Company does not expect to achieve material
progress in securing fiscal terms or lifting of the project's on-ground
suspension.
KWALE OPERATIONS
Operational performance
The Kwale South and North Dunes continued to be mined concurrently during the
quarter, with mining operations split equally between the two deposits. Mined
tonnage was higher at 4.1 million tonnes (Mt) (last quarter: 3.3Mt) following
the stoppage for the mine move to North Dune last quarter. Mining rates in the
high slime lower ore zones of the North Dune also improved during the quarter,
but remain below the mining rates for the upper ore zone. Further enhancements
aimed at improving North Dune mining rates will be trialled in the coming
quarter.
The heavy mineral (HM) grade of ore mined in the quarter was lower at 3.0% (last
quarter: 3.9%) due to the lower grades associated with the North Dune. Ilmenite
recoveries were lower than the previous quarter due to a zone of high chrome ore
in the South Dune that required a higher quantity of low magnetic rejects than
normal to achieve requisite product quality. As a result of the lower ore grade
mined and limited availability of heavy mineral concentrate stocks, production
of finished products was lower than the prior quarter.
Sand tails continued to be deposited into the mined-out Central Dune area and
capped with a 6m co-disposed slimes/sand layer to aid water retention and
subsequent rehabilitation. Rehabilitation activities on the Central Dune and
the South Dune proceeded to plan.
Preparations are underway to commence sand deposition in the mined-out areas of
the North Dune pit with pumping infrastructure established during the quarter.
SUMMARY BY QUARTER FY22 FY23
JUN SEP DEC MAR JUN
Mining (million tonnes)
Ore mined 3.9 4.4 4.5 3.3 4.1
HM % 4.1 3.8 4.0 3.9 3.0
VHM % 3.1 2.9 3.1 3.1 2.3
Production (thousand tonnes)
Ilmenite 83.8 86.0 84.5 71.6 55.5
Rutile 19.2 18.9 19.5 16.6 13.8
Zircon 6.8 6.6 7.4 6.4 5.5
Low grade products1 4.9 5.7 5.2 4.1 3.4
SUMMARY BY QUARTER FY22 FY23
JUN SEP DEC MAR JUN
US$ per tonne
Sales revenue $691 $714 $651 $637 $695
Operating costs $152 $154 $165 $190 $240
Cost of goods sold $196 $200 $191 $195 $263
Revenue: Cost ratio 3.5 3.6 3.4 3.3 2.6
Sales (thousand tonnes)
Ilmenite 95.7 62.6 74.1 86.2 74.6
Rutile 24.7 14.2 14.7 15.2 19.6
Zircon 7.1 6.2 5.0 7.4 6.6
Low grade products1 4.7 4.5 4.7 5.3 3.2
[Note (1): Low grade products are a combination of low-grade zircon and low
-grade rutile which are sold separately at a discount to standard grade
products.]
Bulk shipping operations at the Company's Likoni export facility continued to
run smoothly, with a combined 89.5kt of bulk ilmenite and rutile dispatched
(last quarter: 96kt). Containerised shipments of rutile and zircon through the
Mombasa Port also proceeded to plan.
Unit operating costs have increased to US$240 per tonne produced (rutile,
ilmenite, zircon and low-grade products) (last quarter: US$190 per tonne) due to
lower ore grades resulting in lower production. Despite this, total cash
operating costs of US$18.8 million are in line with the prior quarter (last
quarter: US$18.8 million) due to lower maintenance, product transport and
shipping costs offsetting the higher mining costs.
Cost of goods sold increased to US$263 per tonne sold (operating costs, adjusted
for stockpile movements, and royalties) due to sales volume and mix (last
quarter: US$195 per tonne), which also drove an increase in the average unit
revenue US$695 per tonne (prior quarter: US$637 per tonne). Consequently, the
revenue to cost of goods sold ratio for the quarter was 2.6 (last quarter: 3.3).
FY23 production and FY24 production guidance
Total Kwale Operations production for the 2023 financial year (FY23) was within
the Company's previously disclosed guidance range. Total production for FY23,
together with the Company's production guidance for FY23 and the 2024 financial
year (FY24), is set out in the table below. The FY24 production guidance is
unchanged from that previously announced2.
Production Guidance (tonnes) FY23 FY23 FY24
Guidance Range
Actual Guidance Range
Rutile 62,000 to 73,000 68,784 35,000 to 41,000
Ilmenite 260,000 to 310,000 297,861 130,000 to 160,000
Zircon 22,000 to 27,000 25,954 13,000 to 16,000
[Note (2): Refer to Base Resources' announcement on 26 June 2023, "FY24
Production Guidance - Kwale Operations", for the assumptions upon which the
guidance is based and an explanation of why the guidance is lower than the FY23
guidance.]
MARKETING
Market conditions were relatively stable in North America and Europe but became
challenging in China due to a stalling economic recovery. Despite this, firm
demand continued for Base Resources' products through the quarter. Prices were
steady for ilmenite and slightly lower for rutile, while zircon prices
moderately increased on the expectation of improved domestic conditions after
Chinese New Year.
Ilmenite demand and prices in China improved at the end of the March quarter and
into the start of the June quarter as Chinese pigment plants ramped up
production in anticipation of a rebound in the domestic pigment market.
However, sentiment became increasingly negative through the quarter as the
expected improvement in conditions was not realised. Increasing competition for
pigment sales in both the domestic and export markets led to reduced production
from some operations in China, which led to a corresponding decline in overall
demand for ilmenite over the quarter. Chloride pigment producers in China,
which are reliant on better quality imported ilmenite than the domestically
produced ilmenite, continue to ramp up new production lines which is supporting
demand for Base Resources' ilmenite.
The planned ramp up in pigment production from major western producers in the
first half of 2023 has been slower than expected, with demand not returning to
normal levels by the end of the quarter due to ongoing economic uncertainties in
the major markets. Pigment producers are therefore maintaining a cautious
approach to production to manage inventory levels. Rutile remains a preferred
feedstock for western pigment producers as it enables plants to minimise the use
of other costly raw materials such as chlorine. This supported rutile demand
through the quarter with prices only declining moderately despite the
challenging environment. This situation is expected to continue in the coming
quarter.
Rutile demand from the smaller welding and titanium metal sectors remained firm
in the quarter and is expected to increase for the coming quarter. Rutile
prices into these sectors command a significant price premium over bulk rutile
for the TiO2 pigment market. Base Resources continues to increase its
proportion of rutile sales to the welding sector.
As zircon sale contracts are typically agreed on a quarterly basis in advance of
the relevant quarter, better than expected market sentiment across Europe and
China in the March quarter resulted in an increase in the contracted price of
zircon deliveries for the June quarter. However, stagnant conditions in Europe
through the June quarter, combined with negative sentiment in China, has dented
the outlook for zircon in coming quarters and zircon prices have decreased
moderately for the September quarter contracts.
SUSTAINABILITY
Health and safety
There were no lost time injuries during the quarter and, with no lost time
injuries in the past 12 months, Base Resources has a lost time injury frequency
rate (LTIFR) of 0.0 per million hours worked. Compared to the Western
Australian All Mines 2020/2021 LTIFR of 2.0, this is an exceptional performance
and reflects the ongoing focus and importance placed on safety. With one
medical treatment injury recorded in the last 12 months, Base Resources' total
recordable injury frequency rate is 0.20per million hours worked.
Community and environment - Kwale Operations
Farmers participating in the Company's agricultural livelihood programs in Kwale
County, implemented through the PAVI farmers' cooperative, planted 95 acres of
cotton and 190 acres of maize in preparation for the new season, with recent
rainfall providing an encouraging sign for farmers. Poultry feed production
continued to supplement farmer incomes, and the Company's poultry and beekeeping
programs continued to grow in popularity.
Over 52,000 trees have been planted during the current rainy season.
Established environmental controls have ensured that the onset of the wet season
were well managed with no significant erosion events or runoff into surrounding
communities. Further, no instances of environmental non-compliance, major
environmental incidents or environment-related community complaints were
identified or recorded during the quarter.
Community and environment - Toliara Project
All community training programs and social infrastructure projects remain on
hold while the Toliara Project's on-ground activities are suspended.
BUSINESS DEVELOPMENT
Toliara Project development - Madagascar
Engagement with the Government of Madagascar on Toliara Project fiscal terms,
and lifting of the project's on-ground suspension, has been limited during the
quarter due to the Government focus on an overhaul of the Malagasy Mining Code
and preparations for the upcoming Presidential elections.
A replacement Mining Code has been approved by Parliament and is now under
review by the High Constitutional Court for consistency with Madagascar's
constitution. Following this review and assuming no changes are required, the
replacement Mining Code will be sent to the President for promulgation and will
pass into law when published in the Official Gazette.
Key financial elements of the replacement Mining Code relevant to the Toliara
Project are:
· Increase in royalty rate from 2% to 5%. A reduction of 30% is applied to
the 5% royalty in the event the products are locally "transformed", the
definition and application of which are unclear. The Toliara Project Updated
Definitive Feasibility Study (DFS2) completed on 27 September 2021 assumed a 4%
royalty rate.
· A contribution to the "Mining Fund for Community and Social Investment"
equal to 3% of the direct investment amount. The term "direct investment" is
not defined and the applicability of this contribution requirement to the
Toliara Project is unclear. If this requirement were to apply to the Toliara
Project, based on the DFS2 Stage1 CAPEX of US$520million, this would require a
contribution of US$15.6million.3 DFS2 assumed upfront community development
spend of US$10million.
The application of the above elements, and several other key provisions of the
replacement Mining Code, lack sufficient detail to properly assess their
potential impact on the project. Greater clarity is expected once the
Government has finalised and published the supporting regulations, orders and
decrees.
The first round of the Presidential elections are scheduled for 9 November 2023,
with the second round (if needed) scheduled for 20December 2023. If the
President intends to contest the election as expected, he will have to declare
his candidacy by 23 August 2023 and resign by 9 September 2023.
Until the Mining Code reform is completed and the elections finalised, the
Company does not expect to achieve material progress in securing fiscal terms or
lifting of the project's on-ground suspension. The Company remains ready and
committed to progressing the world class Toliara Project to a final investment
decision once fiscal terms are secured and the on-ground suspension is lifted.
Contact with major EPCM consultants, construction contractors and equipment
suppliers continued to be maintained in readiness once the suspension is
lifted. Assessment of potential funding options for the Toliara Project also
progressed during the quarter.
The Toliara Rare Earths Pre-Feasibility Study of the economic potential of the
monazite contained in the Toliara Project's Ranobe Mineral Resources estimate
continued in the quarter and remains on track for completion in the March
quarter of 2024.
Total expenditure on the Toliara Project and Toliara Rare Earths Pre-Feasibility
Study for the quarter was US$2.0 million (last quarter: US$1.7 million).
[Note (3): For further information about DFS2, refer to Base Resources'
announcement on 27 September 2021 "DFS2 enhances scale and economics of the
Toliara Project" available at
https://baseresources.com.au/investors/announcements/. Base Resources confirms
that all the material assumptions underpinning the production information and
forecast financial information disclosed in that announcement continue to apply
and have not materially changed.]
Extensional exploration - Kenya
The Company released results from the first phase auger drilling program (Phase
1) at the Kwale East exploration project4 (within Prospecting Licence 2018/0119)
shortly after the end of the quarter on 3 July 2023. The results confirmed the
presence of HM, with a peak drill hole grade of 6.3% HM, as well as a high value
mineral assemblage. Three areas of mineralisation were identified for further
targeted exploration in the second phase air core drilling program - Magaoni,
Masindeni and Zigira.
The second phase program is now underway and will focus on drilling the
remaining 35% of the highly prospective areas in Magaoni and Zigira as
landholder consents are obtained. All auger holes from Phase 1 with an average
HM grade greater than 1% will be twinned to enable better sample quality and
allow drilling through to basement. It is expected that Phase 2 will be
completed in the December quarter.
[image]
Aircore drill rig in Kwale East
Prospecting licence applications lodged for an area totalling 722 km2 in the
Kuranze region of Kwale County, about 70 km west of Kwale Operations, together
with applications for an area south of Lamu, totalling 888 km2, remain on hold
pending lifting of a Government of Kenya moratorium on issuance of new mineral
rights, in place since November 2019. The Company is working with the
Government, and other mining sector stakeholders, to see the moratorium lifted.
Expenditure on exploration activities during the quarter in Kenya was US$389k
(last quarter: US$312k).
[Note (4): For further information, refer to Base Resources' announcement on 3
July 2023 "Kwale East exploration drilling update" available at
https://baseresources.com.au/investors/announcements/. Base Resources confirms
that it is not aware of any new information that materially affects the
information included in that announcement.]
Extensional exploration - Tanzania
The Umba South Project in northern Tanzania is located approximately 75km west
-south-west of the Company's Kwale Operations in Kenya. Exploration at Umba
South was designed to test the southern extremity of a prominent north-south
trending ridge of quartzite and gneiss that extends 35km north to the Kuranze
region of Kenya, where initial rock chip and soil sampling indicated the
presence of rutile. Exploration activity in this area has so far been confined
to areas south of the Umba River, while the Company seeks to obtain the
necessary approvals from various government departments to explore in the
Mkomazi Game Controlled Area to the north which hosts the target ridge feature
extending north to the Kenyan border.
Results from 122 holes drilled for 3,015m in the first phase reconnaissance
exploration program were released in the quarter5. Three primary geological
domains were identified. While rutile mineralisation was present in each
domain, factors unique to each domain were identified which would be expected to
limit any significant economic potential. They included a lack of
mineralisation thickness, a lack of continuity of mineralisation, or the
presence of known deleterious elements for mineral sands processing.
A second phase infill drilling program to assess the continuity of rutile
mineralisation in the saprolite layer completed 86 holes for 2,128m. Assaying
of these drill samples has commenced at the Kwale Operations laboratory but
assay priority is currently being given to Kwale East exploration drill samples
and therefore results are not expected until late in the September quarter.
These results will assist in planning future exploration activity at Umba South
and elsewhere along the prospective geological zone once necessary land access
approvals are obtained.
Expenditure on exploration activities during the quarter in Tanzania was US$101k
(last quarter: US$431k).
[Note (5): For further information, refer to Base Resources' announcement on 8
May 2023 "Tanzanian exploration - Umba South Phase 1 drill results" available at
https://baseresources.com.au/investors/announcements/. Base Resources confirms
that it is not aware of any new information that materially affects the
information included in that announcement.]
CORPORATE
The Company is targeting release of its FY23 audited consolidated financial
statements in the week commencing 28August 2023. Confirmation of timing and
investor webcast details will be advised closer to the planned release.
As at 30 June 2023, the Company had cash of US$92.9 million and no debt.
The Company has the following securities on issue:
· 1,178,011,850 fully paid ordinary shares.
· 53,598,359 performance rights issued pursuant to the terms of the Base
Resources Long Term Incentive Plan, comprising:
· 1,872,852 vested performance rights, which remain subject to exercise6; and
· 51,725,507 unvested performance rights subject to performance testing in
accordance with their terms of issue.
[Note (6): Vested performance rights have a nil cash exercise price. Unless
exercised beforehand, these rights expire five years after vesting.]
ENDS.
Forward looking statements
Certain statements in or in connection with this announcement contain or
comprise forward looking statements. Such statements may include, but are not
limited to, statements with regard to future production and grades, capital
cost, capacity, sales projections and financial performance and may be (but are
not necessarily) identified by the use of phrases such as "will", "expect",
"anticipate", "believe" and "envisage". By their nature, forward looking
statements involve risk and uncertainty because they relate to events and depend
on circumstances that will occur in the future and may be outside Base
Resources' control. Accordingly, results could differ materially from those set
out in the forward-looking statements as a result of, among other factors,
changes in economic and market conditions, success of business and operating
initiatives, changes in the regulatory environment and other government actions,
fluctuations in product prices and exchange rates and business and operational
risk management. Subject to any continuing obligations under applicable law or
relevant stock exchange listing rules, Base Resources undertakes no obligation
to update publicly or release any revisions to these forward-looking statements
to reflect events or circumstances after today's date or to reflect the
occurrence of unanticipated events.
For further information contact:
+--------------------------------+-----------------------------+
|Australian Media Relations |UK Media Relations |
+--------------------------------+-----------------------------+
|Citadel Magnus |Tavistock Communications |
+--------------------------------+-----------------------------+
|Cameron Gilenko and Michael Weir|Jos Simson and Gareth Tredway|
+--------------------------------+-----------------------------+
|Tel: +61 8 6160 4900 |Tel: +44 207 920 3150 |
+--------------------------------+-----------------------------+
This release has been authorised by the Board of Base Resources.
About Base Resources
Base Resources is an Australian based, African focused, mineral sands producer
and developer with a track record of project delivery and operational
performance. The Company operates the established Kwale Operations in Kenya, is
developing the Toliara Project in Madagascar and is conducting exploration in
Tanzania. Base Resources is an ASX and AIM listed company. Further details
about Base Resources are available at www.baseresources.com.au.
PRINCIPAL & REGISTERED OFFICE
Level 3, 46 Colin Street
West Perth, Western Australia, 6005
Email: info@baseresources.com.au
Phone: +61 8 9413 7400
Fax: +61 8 9322 8912
NOMINATED ADVISER & JOINT BROKER
Canaccord Genuity Limited
James Asensio / Raj Khatri / Patrick Dolaghan
Phone: +44 20 7523 8000
JOINT BROKER
Berenberg
Matthew Armitt / Detlir Elezi
Phone: +44 20 3207 7800
This information was brought to you by Cision http://news.cision.com
END
(END) Dow Jones Newswires
July 25, 2023 02:22 ET (06:22 GMT)
Base Resources (LSE:BSE)
過去 株価チャート
から 9 2024 まで 10 2024
Base Resources (LSE:BSE)
過去 株価チャート
から 10 2023 まで 10 2024