FEASIBILITY STUDY UPDATE: Major component of Study works now complete as geotechnical drill campaign finishes at Lake Giles
2021年10月26日 - 9:00PM
Macarthur Minerals Limited (ASX: MIO)
(TSX-V: MMS) (OTCQB: MMSDF) (the
Company
or
Macarthur) is pleased to provide an update on
the progress of the Feasibility Study for its high-grade magnetite
Lake Giles Iron Project in Western Australia. The geotechnical
drilling programme of works has now concluded at Moonshine and
Moonshine North, and steady progress continues to be made on all
other aspects of the Study, including ongoing metallurgical process
test work, the design of the process plant and the design of
non-process infrastructure (including the tailings storage
facilities, haul road, rail siding, desalination plant, buildings
and port layout).
The Company recently provided updates to the
market regarding the progress of the Feasibility Study on 1 October
2021 (see announcement regarding the progress of metallurgical and
non-process infrastructure design here), on 7 October 2021 (see
announcement regarding the progress of development of the rail and
port concept plan of operations here), and on 12 October 2021 (see
announcement regarding the progress on the geotechnical analysis
and mine planning work for the Study here).
The Company anticipates providing an update to the market
shortly on final timing for completion of the Study, including
target dates for the release of key outputs (such as project
economics) as well as target dates for release of the Mineral
Reserve Statement, the NI43-101 Technical Report and the final JORC
report.
The following summary sets out details of
current progress of the Feasibility Study as it advances closer to
completion.
Highlights
- Geotechnical drilling complete: The slow
progress of drilling due to challenging ground conditions, wet
weather conditions contributed to a longer than anticipated
duration of the works, however the geotechnical drilling programme
at Lake Giles has now concluded. A total of 9 geotechnical
diamond drill holes with depths of between 40 and 230 metres have
been completed by two drill crews during the period from July to
October. The geotechnical drill core will now be delivered to
Bureau Veritas for completion of lab analysis which will clear the
way for completion of the necessary rock mass and structural model
work by PSM Consulting Pty Ltd. PSM’s work will provide the
basis for mine pit slope parameters which facilitate completion of
the second phase of mine planning work which will be undertaken by
Orelogy Consulting Pty Ltd.
- Process test work: Progress
on the metallurgical test work continues to advance with a range of
test work having already been undertaken, and more test work
planned over coming weeks to refine the process flow sheet.
This includes LIMS tests, magnetic and reverse flotation tests and
HGPR test work, as well as the development of a QEMSCAN
programme.
Highlights (continued)
- Process plant design: Progress on the process
plant layout and plant model continues to advance, with over 60% of
the engineering design work completed, including updated water
balance work and electrical load requirements.
- Non-process infrastructure: Work continues to
progress on the haul road plan and profiles, earthworks modelling,
ANFO and magazine location, rail loop design, LNG and fuel storage
facilities, desalination plant for water treatment, and
requirements for bore field power. Modelling of the tailings
storage facility is progressing and work on the proposed port
infrastructure layout plan (consistent with the development
concepts contemplated under the recently released draft Master Plan
for Esperance Port) is also being advanced.
- Financial outputs: FTI Consulting Pty Ltd is
aggregating data from the study outputs to progress the completion
of the detailed economic model that will accompany the delivery of
the final study reports.
- Qualified Person site visit: The final
Feasibility Study for the Lake Giles Iron Project will require
sign-off by Qualified Persons for the purposes of compliance with
National Instrument 43-101 (which governs standards of disclosure
for mineral projects). To facilitate this, a Qualified Person
site visit is currently expected to be conducted at Lake Giles
during November.
The extended drilling period has required an
adjustment to the commencement of the second phase of mine planning
work, however the Company is working to ensure that the remaining
work is delivered as quickly as possible whilst still maintaining
the quality of the Study outputs.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/190d4744-7498-44a7-a10c-4fe458d18970
https://www.globenewswire.com/NewsRoom/AttachmentNg/1022b9b6-445d-4cea-a577-5cbbcf3af129
Andrew Bruton, CEO of Macarthur Minerals
commented:
“It is pleasing that the geotechnical drilling works have come
to a conclusion. Whilst the programme has taken longer than
expected, mining costs are a critical component of the project
economics and so it has been very important to ensure that these
works were carefully completed in order to deliver the necessary
data for delivery of an optimised mine plan.
As reported on 1 October 2021, the metallurgical process test
work and the non-process infrastructure engineering design for the
Study passed the 60% mark several weeks ago. So overall, the Study
is well advanced. With the geotechnical drilling works now
complete, the Company is looking forward to accelerating into the
final phases of the Study’s delivery, including the all-important
second phase mine planning work.
The Company understands the keen interest of shareholders in the
timing for the delivery of the Feasibility Study. The Study is
edging closer to completion, and we anticipate providing an update
to the market shortly on final timing for its completion, including
target dates for the release of key outputs (such as project
economics) and target dates for release of the Mineral Reserve
statement, the NI43-101 Technical Report and the final JORC
report.
In the interim, your Company will continue to release
progressive updates on material advances under the Study over the
coming weeks.”
On behalf of the Board of Directors, Mr Cameron McCall,
Chairman
For more information please contact:
Joe PhillipsManaging Director+61 7 3221
1796communications@macarthurminerals.com
Investor Relations – Australia |
Investor Relations - Canada |
Advisir |
Investor Cubed |
Alex Bunney, Senior Manager Client Services |
Neil Simon, CEO |
alex.bunney@advisir.com.au |
+1 647 258 3310 |
|
info@investor3.ca |
No new informationTo the extent
that this announcement contains references to prior exploration
results and Mineral Resource estimates, which have been cross
referenced to previous market announcements (including supporting
JORC reporting tables) made by the Company, unless explicitly
stated, no new information is contained in accordance with Table 1
checklist in the JORC Code. The Company confirms that it is not
aware of any new information or data that materially affects the
information included in the relevant market announcements and, in
the case of Mineral Resources that all assumptions and technical
parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed.
Company profileMacarthur is an
iron ore development, gold and lithium exploration company that is
focused on bringing to production its Western Australia iron ore
projects. The Lake Giles Iron Project mineral resources include the
Ularring hematite resource (approved for development) comprising
Indicated resources of 54.5 million tonnes at 47.2% Fe and Inferred
resources of 26 million tonnes at 45.4% Fe; and the Lake Giles
magnetite resource of 53.9 million tonnes (Measured), 218.7 million
tonnes (Indicated) and 997 million tonnes (Inferred). The JORC
reporting tables and Competent Person statement for the magnetite
and hematite mineral resources have previously been disclosed in
ASX market announcements dated 12 August 2020 and 5 December 2019.
Macarthur has prominent (~721 square kilometre tenement area) gold,
lithium and copper exploration interests in Pilbara region of
Western Australia. In addition, Macarthur has lithium brine Claims
in the emerging Railroad Valley region in Nevada, USA.
This news release is not for
distribution to United States services or for dissemination in the
United States
Caution Regarding Forward Looking
StatementsCertain of the statements made and information
contained in this press release may constitute forward-looking
information and forward-looking statements (collectively,
“forward-looking statements”) within the meaning of applicable
securities laws. All statements herein, other than statements
of historical fact, that address activities, events or developments
that the Company believes, expects or anticipates will or may occur
in the future, including but not limited to statements regarding
expected completion of the Feasibility Study; conversion of Mineral
Resources to Mineral Reserves or the eventual mining of the
Project, are forward-looking statements. The forward-looking
statements in this press release reflect the current expectations,
assumptions or beliefs of the Company based upon information
currently available to the Company. Although the Company believes
the expectations expressed in such forward-looking statements are
based on reasonable assumptions, such statements are not guarantees
of future performance and no assurance can be given that these
expectations will prove to be correct as actual results or
developments may differ materially from those projected in the
forward-looking statements. Factors that could cause actual
results to differ materially from those in forward-looking
statements include but are not limited to: unforeseen
technology changes that results in a reduction in iron or magnetite
demand or substitution by other metals or materials; the discovery
of new large low cost deposits of iron magnetite; the general level
of global economic activity; failure to complete the FS; inability
to demonstrate economic viability of Mineral Resources; and failure
to obtain mining approvals. Readers are cautioned not to
place undue reliance on forward-looking statements due to the
inherent uncertainty thereof. Such statements relate to future
events and expectations and, as such, involve known and unknown
risks and uncertainties. The forward-looking statements contained
in this press release are made as of the date of this press release
and except as may otherwise be required pursuant to applicable
laws, the Company does not assume any obligation to update or
revise these forward-looking statements, whether as a result of new
information, future events or otherwise.
Macarthur Minerals (TSXV:MMS)
過去 株価チャート
から 11 2024 まで 12 2024
Macarthur Minerals (TSXV:MMS)
過去 株価チャート
から 12 2023 まで 12 2024