Critical Elements Lithium Corporation (the
“Corporation” or “Critical Elements”) (TSX-V: CRE) (US OTCQX:
CRECF) (FSE: F12) is pleased to provide an update on its
activities. Over the last few months, Critical Elements has been in
steady communication with Provincial and Federal regulatory
authorities concerning the permitting of the Rose Lithium-Tantalum
project (“Rose” or the “Project”). Critical Elements provided
Québec’s Ministère de l'Environnement et de la Lutte contre les
changements climatiques (the “MELCC”) and the Canadian
Environmental Assessment Agency (the “CEAA”) with requested
information this week and expects feedback within the next 4-6
weeks.
Strategic Partner & Project
Financing Discussions
The Corporation continues to work closely with
its financial advisor, Canaccord Genuity Corp., to evaluate ongoing
interest from global strategic partners that seek to accelerate
Rose Lithium-Tantalum project into production.
As part of the process, Critical Elements and
their advisors have been in contact with a number of logical
potential strategic parties, including OEMs, cathode manufacturers
and battery cell manufacturers. These discussions are expected to
continue into next year.
“Potential end-users recognize that our team has
the capacity to successfully deliver lithium products and that our
development strategy provides the flexibility to meet the current
and future needs of major end-users. We remain confident in our
ability to achieve a strategic partnership with a large lithium
product end-user”, stated Jean-Sébastien Lavallée, Chairman &
CEO of Critical Elements.
In parallel, we continue to work with various
financial institutions and lenders to explore project debt
financing opportunities for the construction of Rose.
Other Key Developments
Critical Elements is also pleased to reiterate
some of the progress that has been made in recent months in terms
of aligning community interests with those of the Corporation, as
well as advancing the project engineering of Rose.
Impact & Benefit Agreement
In July 2019 the Cree Nation of Eastmain, the
Grand Council of the Crees (Eeyou Istchee), the Cree Nation
Government and the Corporation have signed an impact and benefit
agreement, referred to as the Pikhuutaau Agreement (the “Pikhuutaau
Agreement“), concerning the development and operation of Rose in
Eeyou Istchee.
The Pikhuutaau Agreement is a binding agreement
that will govern the long-term working relationship between the
parties while respecting Cree traditional activities and ensuring
the promotion of Cree economic and social development based on
mutual trust and respect during all phases of the Project through a
sustainable development approach. It provides for training,
employment and business opportunities for the Crees and
particularly the Crees of Eastmain at the Project, as well as for
the cooperation and involvement of the Cree parties with Critical
Elements in the environmental monitoring during all phases of the
Project. The Pikhuutaau Agreement also ensures financial benefits
for the Cree parties on a long-term basis, consistent with the Cree
Nation Mining Policy and with Critical Elements’ approach to
develop the Project while ensuring the promotion of Cree economic
and social development in a mutually beneficial manner.
Project Engineering
In October 2019, Primero Group (“Primero”)
successfully completed the first phase of its Early Contractor
Involvement (“ECI”) agreement with the Corporation and provided a
Guaranteed Maximum Price (“GMP”) for the engineering, procurement
and construction (“EPC”) of Rose on a lump sum turnkey basis that
is in line with the Project’s feasibility study published November
29, 2017.
Primero is also offering the Corporation its EPC
services as a fully integrated package if the final lump sum is
within the GMP, and if technical and commercial parameters are met
during the second phase.
A summary of the ECI approach is included
below:
- ECI Phase I – Guaranteed Maximum
Price (completed):
-
- Review and assimilate all of the existing design and data
- Stress test and optimize the design through reviews, specific
value engineering and trade-off studies
- Reconfirm quantities and pricing
- Initiate selected engineering deliverables to achieve nominally
25% engineering definition
- Formulate a GMP for the process plant and associated process
supporting infrastructure
- Submit a proposal and schedule to progress to the next
phase
- ECI Phase II – Front End Engineering Design (“FEED”):
- Progress and finalize a selected set of engineering
deliverables to achieve nominally 40% engineering definition
- Advance long lead and critical equipment packages to “Ready for
Award” status
- Complete the contracting strategy and partnership for
construction
- Optimize and reduce contingency applied to the GMP in order to
formulate a Lump Sum (the “LS”) cost estimate for the EPC of the
process plant and associated process infrastructure
- Submit a complete and firm proposal with schedule to Critical
Elements for the EPC-LS contract (the Corporation expects the lump
sum cost estimated to be in line with the feasibility study (Rose
Lithium-Tantalum project feasibility study, WSP, November 29,
2017))
- Execution of the EPC-LS
- Operation and maintenance support throughout scope of
services
Jean-Sebastien Lavallée (OGQ #773), geologist,
shareholder, Chairman & CEO of the Corporation and a Qualified
Person under NI 43-101, has reviewed and approved the technical
content of this release.
About Critical Elements Lithium
Corporation
The Corporation recently released a financial
analysis for Critical Elements’ wholly-owned Rose Lithium Tantalum
project (Rose Lithium-Tantalum project feasibility study, WSP,
November 29, 2017), which is based on price forecasts of US
$750/tonne for chemical-grade lithium concentrate (5% Li2O), US
$1,500/tonne for technical-grade lithium concentrate (6% Li2O) and
US $130/kg for Ta2O5 in tantalite concentrate, and an exchange rate
of US $0.75/CA $. The internal rate of return (“IRR”) for the Rose
Lithium-Tantalum project is estimated at 34.9% after tax, and net
present value (“NPV”) is estimated at CA $726 million at an 8%
discount rate. The estimated payback period is 2.8 years. The
pre-tax IRR for the Rose Lithium-Tantalum Project is estimated at
48.2% and the pre-tax NPV at CA $1,257 million at an 8% discount
rate (see press release dated September 6, 2017). The financial
analysis is based on the Indicated mineral resource. An Indicated
mineral resource is that part of a mineral resource for which
quantity, grade or quality, densities, shape and physical
characteristics can be estimated with a level of confidence
sufficient to allow the appropriate application of technical and
economic parameters, to support mine planning and evaluation of the
economic viability of the deposit. The life-of-mine (LOM) plan
provides for the extraction of 26.8 million tonnes of ore, 182.4
million tonnes of waste, and 11.0 million tonnes of overburden for
a total of 220.2 million tonnes of material. The average stripping
ratio is 7.2 tonnes per tonne of ore. The nominal production rate
is estimated at 4,600 tonnes per day, with 350 operating days per
year. The open pit mining schedule allows for a 17-year mine life.
The mine will produce a total of 26.8 million tonnes of ore grading
an average of 0.85% Li2O and 133 ppm Ta2O5, including dilution. The
mill will process 1.61 million tonnes of ore per year to produce an
annual average of 236,532 tonnes of technical and chemical grade
spodumene concentrate and 429 tonnes of tantalite concentrate.
FOR MORE INFORMATION:
Jean-Sébastien Lavallée, P.Geo.Chief Executive Officer
819-354-5146 jslavallee@cecorp.ca www.cecorp.ca
CAUTIONARY STATEMENT
CONCERNING FORWARD-LOOKING STATEMENTS
This news release contains “forward-looking
information” within the meaning of Canadian Securities legislation.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as “scheduled”, “anticipates”,
“expects” or “does not expect”, “is expected”, “scheduled”,
“targeted”, or “believes”, or variations of such words and phrases
or state that certain actions, events or results “may”, “could”,
“would”, “might” or “will be taken”, “occur” or “be achieved”.
Forward-looking information contained herein include, without
limitation, statements relating to mineral reserve estimates,
mineral resource estimates, realization of mineral reserve and
resource estimates, capital and operating costs estimates, the
timing and amount of future production, costs of production,
success of mining operations, the ranking of the project in terms
of cash cost and production, permitting, economic return estimates,
power and storage facilities, life of mine, social, community and
environmental impacts, lithium and tantalum markets and sales
prices, off-take agreements and purchasers for the Company’s
products, environmental assessment and permitting, securing
sufficient financing on acceptable terms, opportunities for short
and long term optimization of the Project, and continued positive
discussions and relationships with local communities and
stakeholders. Forward-looking information is based on assumptions
management believes to be reasonable at the time such statements
are made. There can be no assurance that such statements will prove
to be accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on forward-looking
information.
Although Critical Elements has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
information, there may be other factors that cause results not to
be as anticipated, estimated or intended. Factors that may cause
actual results to differ materially from expected results described
in forward-looking information include, but are not limited to:
Critical Elements’ ability to secure sufficient financing to
advance and complete the Project, uncertainties associated with the
Company’s resource and reserve estimates, uncertainties regarding
global supply and demand for lithium and tantalum and market and
sales prices, uncertainties associated with securing off-take
agreements and customer contracts, uncertainties with respect to
social, community and environmental impacts, uncertainties with
respect to optimization opportunities for the Project, as well as
those risk factors set out in the Company’s year-end Management
Discussion and Analysis dated August 31, 2019 and other disclosure
documents available under the Company’s SEDAR profile.
Forward-looking information contained herein is made as of the date
of this news release and Critical Elements disclaims any obligation
to update any forward-looking information, whether as a result of
new information, future events or results or otherwise, except as
required by applicable securities laws.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this release.
Critical Elements Lithium (TSXV:CRE)
過去 株価チャート
から 12 2024 まで 1 2025
Critical Elements Lithium (TSXV:CRE)
過去 株価チャート
から 1 2024 まで 1 2025