TIDMBSE 
 
AIM and Media Release 
 
19 October 2021 
 
BASE RESOURCES LIMITED 
Quarterly Activities Report - September 2021 
 
Key Points 
 
  * Ongoing strong demand for all products supported further price increases in 
    the quarter. 
  * Kwale Operations mine life extended to December 2023 following finalisation 
    of mining lease extension. 
  * Bumamani PFS released concluding that higher grade subsets of the Bumamani 
    and Kwale North Dune deposits can be economically mined, which would extend 
    Kwale mine life to mid-2024. 
  * Three Tanzanian prospecting licences granted, with a fourth pending, and 
    preparatory work for an exploration program commenced. 
  * Ranobe Mineral Resources and Ore Reserves estimates updated to incorporate 
    drilling program results. 
  * Toliara Project scale and economics enhanced with release of DFS2. 
  * FY21 full-year dividend of AUD4.0 cents per share paid, totalling US$34.8 
    million. 
 
African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (Base 
Resources or the Company) is pleased to provide a quarterly operational, 
development and corporate update. 
 
COVID-19 UPDATE 
 
Base Resources continues to closely monitor the COVID-19 pandemic and its 
impacts on the Company's business, people and wider stakeholders.  The 
Company's Kwale Operations in Kenya operates under a suite of controls and 
mitigations aimed at protecting the health and safety of our employees and 
neighbouring communities, including modified workplace practices and a focus on 
hygiene and social distancing.  On site rapid antigen COVID-19 testing is 
utilised and employees have been encouraged to access the Government of Kenya 
vaccination program.  The Company continues to assist governments and 
communities with initiatives focused on the construction of hygiene facilities, 
and the donation and distribution of food and medical supplies and equipment. 
 
KWALE OPERATIONS 
 
Production & Sales      Sept 2020     Dec 2020      Mar 2021      June 2021     Sept 2021 
                         Quarter       Quarter       Quarter       Quarter       Quarter 
 
Production (tonnes) 
 
        Ilmenite         65,863        78,500        84,178        88,735        72,866 
 
        Rutile           15,513        18,171        19,448        20,116        17,762 
 
        Zircon            6,000         6,677         7,388         7,057         6,069 
 
        Zircon low         426           516           482           454           506 
grade* 
 
Sales (tonnes) 
 
        Ilmenite         75,502        53,798        97,179        93,959        34,107 
 
        Rutile           11,651        12,017        26,074        24,597        13,791 
 
        Zircon            7,336         6,399         6,612         7,690         5,622 
 
        Zircon low         505            -            502           698           617 
grade* 
 
*Reported as tonnes of zircon concentrate which contains low grades of zircon 
and rutile credits. 
 
Mining operations continued to plan on the South Dune orebody with mined 
tonnage decreasing due to two mining block moves during the quarter.  As 
expected, heavy mineral (HM) grade for the quarter was lower at 3.26% (last 
quarter: 3.65%) due to mining commencing on the lower grade fringes of the new 
mining blocks. 
 
Mining & WCP           Sept 2020     Dec 2020      Mar 2021      June 2021     Sept 2021 
Performance             Quarter       Quarter       Quarter       Quarter       Quarter 
 
Ore mined (tonnes)     3,938,494     4,600,172     4,695,052     4,748,860     4,409,883 
 
HM %                     3.12          3.43          3.58          3.65          3.26 
 
VHM %                    2.36          2.62          2.80          2.78          2.50 
 
HMC produced            103,730       142,309       149,618       162,428       133,874 
(tonnes) 
 
Wet concentrator plant (WCP) production of heavy mineral concentrate (HMC) was 
lower as a consequence of the lower mined tonnes and ore grade.  HMC stocks 
were slightly lower at 16.5kt (last quarter: 20kt).  Sand tails continued to be 
deposited into the mined-out Central Dune area and capped with a 2m thick 
co-disposed slimes/sand layer to aid water retention and subsequent 
rehabilitation or alternate land use.  Agricultural trials on the co-disposed 
water retention layer are proving successful.  Rehabilitation of the mined-out 
sections of the South Dune proceeded according to plan. 
 
MSP Performance        Sept 2020     Dec 2020      Mar 2021      June 2021     Sept 2021 
                        Quarter       Quarter       Quarter       Quarter       Quarter 
 
MSP Feed (tonnes of     114,873       134,019       145,110       160,691       137,182 
HMC) 
 
MSP feed rate (tph)       61            64            69            76            64 
 
MSP recovery % 
 
        Ilmenite          100           102           102           101           100 
 
        Rutile            102           102           100           100           104 
 
        Zircon            86            87            85            86            84 
 
Mineral separation plant (MSP) feed tonnage of 137kt was lower than the prior 
quarter (last quarter: 161kt), being limited by HMC feed availability. 
Underlying MSP product recoveries were steady, with the increase in reported 
rutile recoveries due to a one-off stock adjustment.  Production of final 
products was in line with plan.  Production of HMC, MSP feed and final product 
output are expected to increase in the coming quarter as higher-grade mining 
areas are accessed. 
 
Bulk loading operations at the Company's Likoni export facility continued to 
run smoothly, dispatching a combined 54kt of bulk ilmenite and rutile during 
the quarter (last quarter: 104kt).  Containerised shipments of rutile and 
zircon through the Mombasa Port proceeded to plan. 
 
Summary of unit costs         Sept 2020   Dec 2020    Mar 2021    June 2021   Sept 2021 
& Revenue per tonne (US$)      Quarter     Quarter     Quarter     Quarter     Quarter 
 
Unit operating costs per        $189        $161        $142        $148        $174 
tonne produced 
 
Unit cost of goods sold per     $192        $207        $169        $202        $264 
tonne sold 
 
Unit revenue per tonne of       $413        $464        $478        $497        $668 
product sold 
 
Revenue: Cost of goods sold      2.1         2.2         2.8         2.5         2.5 
ratio 
 
Total cash operating costs of US$16.9 million were steady compared to the prior 
quarter (last quarter at US$17.2 million), however lower production results in 
higher unit operating costs of US$174 per tonne produced (rutile, ilmenite, 
zircon and low-grade zircon) (last quarter: US$148 per tonne). 
 
Unit cost of goods sold is influenced by both the underlying operating costs 
and product sales mix.  Operating costs are allocated to each product based on 
revenue contribution, which sees the higher value rutile and zircon products 
attracting a higher cost per tonne than the lower value ilmenite.  Therefore, 
the greater the sales volume of rutile and zircon relative to ilmenite in a 
quarter, the higher both unit revenue per tonne and unit cost of goods sold 
will be. 
 
Ilmenite, and most rutile, is sold in bulk, with typical shipment sizes of 50kt 
for ilmenite and 10kt for rutile, which means any given quarter will usually 
contain either one or two bulk ilmenite and rutile sales.  Zircon is sold in 
smaller parcels and sales generally align with production volume.  Product 
sales mix will therefore vary depending on the number of bulk shipments of 
ilmenite and rutile in each quarter. 
 
Cost of goods sold of US$264 per tonne sold (operating costs, adjusted for 
stockpile movements, and royalties) increased due to the sales mix (last 
quarter: US$202 per tonne).  Average unit revenue increased to US$668 per tonne 
(prior quarter: US$497 per tonne) due to sales mix and increased prices for all 
products.  Due to the above factors and the timing of sales, the revenue to 
cost of goods sold ratio for the quarter remained steady at 2.5 (last quarter: 
2.5). 
 
FY22 PRODUCTION GUIDANCE 
 
Kwale Operations production guidance for the 2022 financial year remains at: 
 
  * Rutile - 73,000 to 83,000 tonnes. 
  * Ilmenite - 310,000 to 340,000 tonnes. 
  * Zircon - 24,000 to 28,000 tonnes. 
 
This guidance is based on the following assumptions: 
 
  * Mining of 17.4Mt at an average HM grade of 3.53%. 
  * Average MSP feed rate of 68tph. 
  * Average MSP product recoveries of 101% for rutile, 101.5% for ilmenite and 
    84.5% for zircon. 
 
The possibility of a halt to, or curtailment of, operations at some point in 
the future remains if a severe COVID-19 outbreak occurs on site or if 
government health directives change. 
 
MARKETING 
 
Despite the usual seasonal dip in the Chinese pigment market at the start of 
the northern hemisphere summer, which has since recovered, overall global 
pigment demand remained very strong through the quarter leading to ongoing 
robust demand for titanium feedstocks.  As a result, pigment prices maintained 
upward momentum with further price increases expected in coming months. 
 
Demand for ilmenite as a feedstock for Chinese pigment producers was again very 
strong in the quarter, enabling further ilmenite price gains.  Increased 
ilmenite supply from some African sources, Vietnamese exports and Chinese 
domestic production through 2021 is not yet sufficient to meet demand and 
ilmenite prices are expected to continue their upward trend through the 
December quarter.  However, escalating bulk freight costs to China are 
partially eroding these price gains. 
 
Demand for high grade feedstocks (which includes rutile) increased 
significantly through the quarter as western pigment producers sought to 
maximise output rates and the welding consumable and titanium metal sectors 
continued to strengthen.  The tight market for high grade feedstocks is being 
exacerbated by supply constraints and uncertainties at major high grade 
feedstock producers.  Rutile prices increased through the quarter and are 
expected to accelerate further through the coming quarters. 
 
Zircon demand continues to be very strong due to recoveries in all end use 
sectors and regions, which, when combined with limited supply and minimal 
inventories, has resulted in a tightening zircon market and significant upward 
price pressure.  Zircon prices for the Company's September quarter contracts 
increased by approximately US$150/t from the June quarter and prices agreed for 
the Company's December quarter contracts have increased by an additional US$600 
/t. 
 
SAFETY 
 
There were no lost time injuries during the quarter, or in the past year, at 
Kwale Operations or the Toliara Project, resulting in a lost time injury 
frequency rate (LTIFR) for the Company of zero.  Compared to the Western 
Australian All Mines 2019/2020 LTIFR of 2.1, this is an exceptional performance 
reflective of the ongoing focus and importance placed on safety by management. 
Base Resources group employees and contractors have now worked 25.9 million 
hours lost time injury (LTI) free, with the last LTI recorded in early 2014. 
 
Two medical treatment finger injuries were recorded during the quarter.  As a 
result, Base Resources' total recordable injury frequency rate is 0.50 per 
million hours worked. 
 
COMMUNITY AND ENVIRONMENT 
 
Kwale Operations 
 
Base Resources has continued to assist the Kwale community through the COVID-19 
pandemic, including collaborating with county and national health authorities 
to provide public education through community health workers. 
 
Agricultural livelihood programs in Kwale continued through the PAVI farmer's 
cooperative although, with rains being significantly below average throughout 
most of the year, alternative drought resistant crop variants have been 
planted.  Poultry and beekeeping continue to expand and provide farmers and 
community groups with substantial incomes. 
 
Implementation of the Community Development Agreements (CDAs) with the 
Msambweni, Lunga and Likoni communities progressed well.  Representing their 
respective communities, each committee undertook further training and capacity 
building to ensure more efficient delivery of community development projects 
set out in each CDA. 
 
Rehabilitation activities on the mined-out sections of the South Dune continued 
in the quarter with community groups supplying indigenous legumes, grass seed 
and manure. 
 
The heads of several government ministries and lead agencies visited Kwale 
Operations in the quarter to see the success of ongoing rehabilitation 
activities and the agricultural potential of rehabilitated land on the South 
Dune.  This information sharing is key to creating awareness and understanding 
among stakeholders of the various options being considered for post-mining land 
use.  Crops harvested from trial plots on the South Dune continue to be 
distributed to local schools and children's homes. 
 
Toliara Project 
 
All community training programs, and social infrastructure construction, 
remained on hold with the Government of Madagascar's suspension of the Toliara 
Project's on-the-ground activities.  The 24 Malagasy apprentices, who recently 
completed their two-year training programs in Kenya at Kwale Operations, 
returned to Madagascar following their certification through the Kenyan 
training authority and completion of further work experience at Kwale 
Operations. 
 
Base Resources partnered with local governments and community health groups in 
the Toliara region to provide additional support to vulnerable communities 
affected by COVID-19, including programs to address food insecurity and 
hygiene. 
 
BUSINESS DEVELOPMENT 
 
Toliara Project development - Madagascar 
 
In November 2019, the Government of Madagascar required the Company to suspend 
on-the-ground activity on the Toliara Project while discussions on fiscal terms 
applying to the project were progressed.  Activity remains suspended as Base 
Resources continues to engage with the Government in relation to the country's 
Large Mining Investment Law regime, fiscal terms applicable to the Toliara 
Project and the lifting of the on-the-ground suspension. 
 
In September, updated Ranobe Mineral Resources and Ore Reserves estimates were 
released, incorporating available assay results from the 2018/19 drill 
program.  This resulted in the Ranobe Mineral Resources almost doubling to 
2,580Mt (597Mt Measured, 793Mt Indicated, 1,190Mt Inferred) at an average HM 
grade of 4.3% and Ore Reserves contained heavy mineral tonnes increasing by 45% 
to 55Mt (30Mt Proved, 25Mt Probable) at 6.1% HM grade.1 
 
The substantially increased Ranobe Ore Reserves estimate, combined with the 
attractive long-term supply-demand outlook for mineral sands, provided the 
opportunity for Base Resources to complete an enhanced Definitive Feasibility 
Study (DFS2) for the Toliara Project incorporating an increase in scale, the 
outcomes of which were released in September 2021.  DFS2, compared to the 2019 
DFS, has delivered a substantial improvement in the forecast financial returns 
for the Toliara Project, including a post-tax/pre-debt (real) NPV10 of US$1.0 
billion and an average revenue to cost of sales ratio of 3.5, over an initial 
38-year mine life.2 
 
The DFS2 schedule assumes construction will commence at the start of 2023, at a 
capital cost of US$520 million, which would see production starting in early 
2025.  However, timing of the Final Investment Decision (FID) to proceed with 
the construction of the Toliara Project remains subject to lifting of the 
suspension of on-the-ground activities and agreeing acceptable fiscal terms 
with the Government of Madagascar.  Once these two key milestones are achieved, 
there will be approximately 11 months' work to complete prior to reaching FID, 
including finalising funding, completing the land acquisition process, 
concluding major construction contracts and entering into offtake agreements 
with customers.  Resumption of reasonable international travel will also be 
required to complete a significant portion of this pre-FID work and the Company 
maintains readiness to accelerate progress when conditions support. 
 
Total expenditure on the Toliara Project for the quarter was US$2.1 million 
(last quarter: US$3.1 million). 
 
[Notes: 
 
(1) For further information, refer to Base Resources' announcement on 27 
September 2021 "Updated Ranobe Mineral Resources and Ore Reserves estimates". 
Base Resources confirms that it is not aware of any new information or data 
that materially affects the information in this announcement and that all 
material assumptions and technical parameters underpinning the estimates in 
that announcement continue to apply and have not materially changed. 
 
(2) For further information, refer to Base Resources' announcement on 27 
September 2021 "DFS2 enhances scale and economics of the Toliara Project". 
Base Resources confirms that all the material assumptions underpinning the 
production information and forecast financial information in this announcement 
continue to apply and have not materially changed.] 
 
Kwale mine life extension 
 
Significant progress was made in the quarter to extend mine life at Kwale 
Operations. 
 
In anticipation of completing tenure arrangements to extend the boundary of 
Kwale's Special Mining Lease 23 (SML 23), the Kwale South Dune Ore Reserves 
estimate was updated to incorporate previously defined Mineral Resources 
falling outside of SML 23, resulting in Ore Reserves of 40Mt (30Mt Proved, 11Mt 
Probable) at an average grade of 3.3% for 1.3Mt of contained HM as at 30 June 
2021.3  The Company subsequently finalised a Deed of Variation with the 
Government of Kenya to extend the boundary of SML 23 to incorporate these 
additional South Dune Ore Reserves, taking mine life to December 2023. 
 
In addition, Base Resources completed the Bumamani pre-feasibility study (PFS) 
which concluded that it was economically viable to mine higher-grade subsets of 
the Bumamani and Kwale North Dune (P199) deposits, which would extend mine life 
at Kwale Operations by a further 7.5 months to July 2024.4  A DFS is now 
underway to improve the accuracy of project estimates and is expected to be 
completed in the first half of 2022. 
 
Refer to the full PDF version of this announcement, available from Base 
Resources' website (https://baseresources.com.au/investors/announcements/), for 
a map showing the extended boundary of SML 23 and the location of the P199 
higher grade subsets. 
 
[Notes: 
 
(3):  For further information, refer to Base Resources' announcement on 20 
August 2021 "Updated Kwale South Dune Mineral Resources and Ore Reserves 
estimates". Base Resources confirms that it is not aware of any new information 
or data that materially affects the information in this announcement and that 
all material assumptions and technical parameters underpinning the estimates in 
that announcement continue to apply and have not materially changed. 
 
(4):  For further information, refer to Base Resources' announcements on 3 
September 2021 "Bumamani PFS supports extension of Kwale mine life" and 
"Further supporting information for Bumamani PFS".  Base Resources confirms 
that all the material assumptions underpinning the production information and 
forecast financial information in these announcements continue to apply and 
have not materially changed.] 
 
Extensional exploration - Kenya & Tanzania 
 
No further work was conducted on Vanga Prospecting License (PL/2015/0042) in 
the quarter and completion of the remaining drilling program (4,200 metres) in 
the North-East Sector (Kwale East) of PL 2018/0119 remains on hold pending 
community access being secured. 
 
Prospecting licence applications lodged for an area in the Kuranze region of 
Kwale county, about 70 km west of Kwale Operations (applications 2019 0260, 
2510 and 2512), together with an area south of Lamu (applications 2019 0263, 
0265, 0266), remain in progress towards granting.  An additional prospecting 
licence application has been lodged for the area surrounded by the Kuranze 
applications in Kenya, however application numbers and boundaries have not yet 
been issued.  A Government of Kenya moratorium on the issuance of prospecting 
licences in November 2019 has affected the progress of all licence 
applications.  The Company continues to work with the Government, and other 
mining sector stakeholders, to see the moratorium lifted and recommencement of 
the issuance of mineral rights. 
 
During the quarter, the Company received three prospecting licences in Tanzania 
for areas adjacent to the Kuranze region in Kenya with a fourth licence 
pending.  Training of a Tanzanian exploration field team is underway ahead of 
an auger drilling program planned to commence in the December quarter. 
 
Refer to the full PDF version of this announcement, available from Base 
Resources' website (https://baseresources.com.au/investors/announcements/), for 
a map showing the location of the Company's Tanzanian prospecting licences and 
remaining prospecting licence application, and Kuranze prospecting licence 
applications. 
 
Expenditure on exploration activities in Kenya during the quarter was US$0.3 
million (last quarter: US$0.1 million) and in Tanzania was US$0.1 million (last 
quarter: zero). 
 
CORPORATE 
 
FY21 full-year dividend payment 
 
Following release of the Company's FY21 annual financial results, the 
disciplined application of the Company's capital management policy saw a 
full-year dividend of AUD 4.0 cents per share (unfranked) paid to shareholders 
on 29 September 2021, representing a cash payment of US$34.8 million (in 
aggregate).  This takes total dividends in respect of FY21 to US$61.4 million, 
representing AUD 7.0 cents per share (unfranked). 
 
Kenyan VAT receivable and Kwale royalty rate 
 
During the period Base Titanium Limited, Base Resources' wholly owned Kenyan 
Subsidiary, and the Government of Kenya signed Deeds of Variation for the Kwale 
SML 23 that amended the mining lease boundary and increased the rate of 
royalties payable5 to the Government of Kenya, such that: 
 
  * For the period from the date of first export of minerals to 30 June 2018, 
    the royalty is increased to 3%. 
  * For the period from 1 July 2018 to the end of SML 23, the royalty is 
    increased to 5%. 
 
[Note (5):  For further information, refer to Base Resources' announcement on 
30 September 2021 "Kwale mining lease extension secured and royalty discussions 
finalised".] 
 
Prior to being varied, the applicable royalty rate under SML 23 was 2.5% and it 
is on this basis that royalties have been paid.  However, from first export of 
minerals, royalty costs have been provided for, and expensed, by the Company at 
an assumed royalty rate of 5%, based on an expected outcome from the long 
running discussions with the Government of Kenya.  In consideration for entry 
into the Deeds of Variation, in particular agreement to a royalty for the 
period to 30 June 2018 at a rate lower than had been accrued, Base Titanium 
withdrew its claim for refund of VAT receivables related to the construction of 
Kwale Operations. 
 
On the basis of values at 30 June 2021, the net effect of the above is: 
 
  * Payment by Base Titanium of US$18.6 million for the agreed increases in 
    royalty rates, consisting of the 0.5% increase for the period to 30 June 
    2018 and the 2.5% increase for the period from 1 July 2018.The related 
    accruals will be extinguished. 
  * A net US$3.2 million expense will be recorded in the Company's financial 
    statements, consisting of the write back of the excess 2% royalty accrual 
    for the period to 30 June 2018, totalling US$12.8 million, and the 
    write-off of the construction period VAT receivable of US$16.0 million. 
 
The above additional royalty payments are due in the December quarter. 
 
Base Resources continues to have refund claims for VAT paid in Kenya relating 
to the period since operations commenced, which totalled approximately US$4.5 
million at 30 September 2021.  No VAT refunds were received during the quarter 
(last quarter: nil). 
 
In summary, as at 30 September 2021: 
 
  * Net cash of US$36.7 million consisting of: 
      + Cash and cash equivalents of US$36.7 million. 
      + No debt. 
 
As at 18 October 2021: 
 
  * 1,178,011,850 fully paid ordinary shares on issue. 
  * 62,435,197 performance rights on issue pursuant to the terms of the Base 
    Resources Long Term Incentive Plan, comprising: 
      + 13,835,392 vested performance rights, which remain subject to 
        exercise6. 
      + 48,599,805 unvested performance rights subject to performance testing 
        in accordance with their terms of issue. 
 
[Note (6):  Vested performance rights have a nil cash exercise price.  Unless 
exercised beforehand, these rights expire five years after vesting.] 
 
FORWARD LOOKING STATEMENTS 
 
Certain statements in or in connection with this announcement contain or 
comprise forward looking statements.  Such statements may include, but are not 
limited to, statements with regard to future production and grades, capital 
cost, capacity, sales projections and financial performance and may be (but are 
not necessarily) identified by the use of phrases such as "will", "expect", 
"anticipate", "believe" and "envisage".  By their nature, forward looking 
statements involve risk and uncertainty because they relate to events and 
depend on circumstances that will occur in the future and may be outside Base 
Resources' control.  Accordingly, results could differ materially from those 
set out in the forward-looking statements as a result of, among other factors, 
changes in economic and market conditions, success of business and operating 
initiatives, changes in the regulatory environment and other government 
actions, fluctuations in product prices and exchange rates and business and 
operational risk management.  Subject to any continuing obligations under 
applicable law or relevant stock exchange listing rules, Base Resources 
undertakes no obligation to update publicly or release any revisions to these 
forward-looking statements to reflect events or circumstances after today's 
date or to reflect the occurrence of unanticipated events. 
 
ENDS. 
 
For further information contact: 
 
James Fuller, Manager Communications and Investor  UK Media Relations 
Relations 
 
Base Resources                                     Tavistock Communications 
 
Tel: +61 (8) 9413 7426                             Jos Simson and Gareth Tredway 
 
Mobile: +61 (0) 488 093 763                        Tel: +44 (0) 207 920 3150 
 
Email: jfuller@baseresources.com.au 
 
About Base Resources 
 
Base Resources is an Australian based, African focused, mineral sands producer 
and developer with a track record of project delivery and operational 
performance.  The Company operates the established Kwale Operations in Kenya 
and is developing the Toliara Project in Madagascar.  Base Resources is an ASX 
and AIM listed company.  Further details about Base Resources are available at 
www.baseresources.com.au 
 
PRINCIPAL & REGISTERED OFFICE 
Level 3, 46 Colin Street 
West Perth, Western Australia, 6005 
Email:  info@baseresources.com.au 
Phone: +61 (0)8 9413 7400 
Fax: +61 (0)8 9322 8912 
 
NOMINATED ADVISOR 
RFC Ambrian Limited 
Stephen Allen 
Phone: +61 (0)8 9480 2500 
 
JOINT BROKER 
Berenberg 
Matthew Armitt / Detlir Elezi 
Phone: +44 20 3207 7800 
 
JOINT BROKER 
Canaccord Genuity 
Raj Khatri / James Asensio / Patrick Dolaghan 
Phone: +44 20 7523 8000 
 
 
 
 
END 
 
 

(END) Dow Jones Newswires

October 19, 2021 02:00 ET (06:00 GMT)

Base Resources (LSE:BSE)
過去 株価チャート
から 7 2024 まで 8 2024 Base Resourcesのチャートをもっと見るにはこちらをクリック
Base Resources (LSE:BSE)
過去 株価チャート
から 8 2023 まで 8 2024 Base Resourcesのチャートをもっと見るにはこちらをクリック