TORONTO, July 15, 2019 /CNW/ - Anaconda Mining Inc.
("Anaconda" or the "Company") (TSX: ANX) (OTCQX: ANXGF) is pleased
to announce production results and certain financial information
from the three and six months ended June 30,
2019 ("Q2 2019"). All dollar amounts are in Canadian
Dollars. The Company expects to file its second quarter financial
statements and management discussion and analysis on or around
August 1, 2019.
Q2 2019 Highlights
- Anaconda sold 3,153 ounces of gold in Q2 2019, generating metal
revenue of $5.5 million at an average
realized gold price1 of $1,739 per ounce. As at June 30, 2019, the Company also had over 565
ounces in gold doré and bullion inventory, which was subsequently
sold in July 2019.
- The Company produced 78,123 tonnes of ore during the second
quarter, predominantly from mining at the Stog'er Tight Mine, a
138% increase over Q2 2018. Material moved also included 270,552
tonnes of waste development for a pushback of the Pine Cove Pit,
which also contributed 14,690 tonnes of ore in Q2 2019.
- The Company ended the second quarter with stockpile of over
15,800 tonnes of ore at an estimated average grade of 1.62 grams
per tonne ("g/t").
- The Pine Cove Mill processed 96,895 tonnes during Q2 2019, a
20% reduction compared to Q2 2018 due to lower mill availability
resulting from planned maintenance activities on the main ball
mill, unplanned maintenance of the regrind mill, and the decision
to accelerate other maintenance programs to minimize future down
time. Mill availability was back up over 92% for the month of
June.
- Milled tonnes per day ("tpd") of 1,241 were down 8% compared to
Q2 2018 due to lower mill availability, however a marked
improvement of 9% from Q1 2019 when mill maintenance programs were
initiated.
- Following the positive drill results in February 2019 which successfully infilled and
extended mineralization near the margins of the existing pit
outlines at Pine Cove and Stog'er Tight, the Company has initiated
further drilling at these locations which continues to demonstrate
the potential for further expansion of mine life.
- As at June 30, 2019, the Company
had a cash balance of $3.1 million,
neutral preliminary working capital1, and
additional available liquidity of $1,000,000 from an undrawn revolving line of
credit facility. On July 10, 2019,
Anaconda successfully completed a non-brokered private placement
for $4.69 million, which will fund
exploration at the Tilt Cove Gold Project and continued advancement
of the Goldboro Gold Project, in addition to continued investment
at the Point Rousse Complex and other corporate initiatives.
1 Refer to Non-IFRS
Measures Section below.
|
"The second quarter was challenging for Anaconda as the
unplanned maintenance of the regrind mill impacted mill
availability, which in turn impacted throughput and recovery. We
took the opportunity to accelerate other planned maintenance
programs to minimize future mill downtime and made significant
investments in critical spares and upgrading key parts of the mill.
We have also brought on a new General Manager with strong mining
experience to provide the oversight required to ensure
sustainability of the operation, and have bolstered the maintenance
team and programs, all of which have led to the improvement of
throughput and recovery into July. Despite the challenging quarter,
Anaconda continues to advance its Feasibility Study at the Goldboro
Gold Project and with the closing of a private placement financing
is in a position to commence exploration on the prospective Tilt
Cove Gold Project, located approximately 40 kms east of the Pine
Cove Mill and along strike from the past-producing, high-grade
Nugget Pond Gold Mine."
~ Kevin Bullock, CEO, Anaconda
Mining Inc.
Updated Guidance – As a result of recent successful
infill and expansion drilling at the Pine Cove open pit mine
announced in February 2019, the
Company continues to see potential to expand the mine life at Pine
Cove and consequently will defer the development of the Argyle
Deposit into 2020. As a result, the Company is revising its
guidance for 2019 to 16,000 to 17,000 ounces of gold from its
initial guidance of 19,000 to 20,000 ounces. The Pine Cove Mine is
immediately adjacent to the processing facility and is very well
understood geologically and from a mining perspective, limiting
technical risk, and requires low capital expenditure to continue
production. Ongoing mining at Pine Cove also has the benefit of
increasing the Company's permitted in-pit tailings storage
capacity. This will allow the Company to continue to optimize the
Argyle Deposit, incorporating recent drilling results, and complete
all required permitting activities, while deferring the related
capital to develop the site. The Company has now received a Mining
Lease for the Argyle Deposit and has submitted the development and
rehabilitation plan for regulatory review.
Second Quarter Operating Statistics
|
Three months
ended
June 30,
2019
|
Three months
ended
June 30,
2018
|
Six months
ended
June 30,
2019
|
Six months
ended
June 30,
2018
|
Mine
Statistics
|
|
|
|
|
Ore production
(tonnes)
|
78,123
|
32,833
|
155,490
|
176,673
|
Waste production
(tonnes)
|
427,425
|
356,642
|
706,837
|
606,774
|
Total material moved
(tonnes)
|
505,548
|
389,475
|
862,327
|
783,447
|
Waste: Ore
ratio
|
5.5
|
10.9
|
4.6
|
3.4
|
|
|
|
|
|
Mill
Statistics
|
|
|
|
|
Availability
(%)
|
85.8
|
98.7
|
82.0
|
96.1
|
Dry tonnes
processed
|
96,895
|
121,299
|
176,653
|
230,518
|
Tonnes per day
("tpd")
|
1,241
|
1,350
|
1,191
|
1,326
|
Grade (grams per
tonne)
|
1.25
|
1.38
|
1.55
|
1.41
|
Recovery
(%)
|
74.7
|
85.9
|
79.3
|
85.6
|
Gold Ounces
Produced
|
2,907
|
4,632
|
7,083
|
8,925
|
Gold Ounces
Sold
|
3,153
|
4,330
|
8,404
|
8,856
|
Operations Overview for the Three Months Ended June 30, 2019
Anaconda sold 3,153 ounces of gold during the second quarter of
2019, generating gold and silver revenue of $5.5 million, and year-to-date has sold 8,404
ounces to generate revenue of $14.3
million. As at June 30, 2019,
the Company also had over 565 ounces of gold doré and bullion
inventory, which were sold in early July. The Company has revised
its guidance to 16,000 to 17,000 ounces of gold in light of the
potential expansion opportunities at Pine Cove, which it expects
will require less capital and be easier to permit. The decrease in
guidance reflects the deferral of the development of the Argyle
Deposit into 2020, and the Company continues to advance the related
permitting process. The Company will provide updated guidance for
operating cash costs1 as part of the release of its
financial results on or around August 1,
2019.
1 Refer to Non-IFRS
Measures Section below.
|
Point Rousse Mill Operations – The Pine Cove
Mill processed 96,895 tonnes during Q2 2019, down 20% compared to
the second quarter of 2018, as the mill was ramping up from a
series of planned maintenance programs on the main ball mill,
delayed shipment of trunnion liners, and unplanned maintenance on
the head of the regrind mill. Once the regrind mill trunnion liners
and mill head were installed in April, the mill was able to ramp up
its throughput, which increased 9.3% to 1,241 tonnes per day from
the first quarter of 2019, when it achieved 1,135 tonnes per
day.
Recovery during the second quarter of 2019 was 74.7%, down
significantly from Q2 2018 and from usual recovery levels for the
operation. When the regrind mill was initially taken off-line in Q1
2019, a back-up stirred media detritor ("SMD") system was initiated
to maintain a certain level of throughput, however it was noted
that the system was not able to maintain the optimal grind size and
leach capabilities, leading to recovery losses. To minimize any
loss of gold production, the mill temporarily ceased operations to
allow for the completion of rebuild of the regrind mill head and to
opportunistically complete many significant maintenance programs.
When the mill was brought back on-line, the coarse concentrate from
March made its way through the circuit at lower than usual leach
recoveries, leading to relatively low overall recovery. In
addition, consistency through the regrind mill was challenged after
the ramp-up as the mill calibrated the operating parameters for
bearing temperature, which further impacted leach recovery. With
the circuit now in full operation the mill is now achieving
recoveries in line with historical results.
Average grade during Q2 2019 was 1.25 g/t, a 9.9% decrease from
the second quarter of 2018, and lower than Q1 2019 when Stog'er
Tight was the main ore feed to the Pine Cove Mill. The mill
achieved an average recovery rate of 74.7%, 10% below planned and
historically achieved levels, resulting in gold production of 2,907
ounces for the second quarter of 2019.
Point Rousse Mine Operations – During the
second quarter of 2019, the mine operations produced 78,123 tonnes
of ore, predominantly from the Stog'er Tight Mine. Total material
moved included of 505,548 tonnes also included 295,082 tonnes of
waste development for a pushback at the Pine Cove Pit, which also
contributed 14,690 tonnes of ore in Q2 2019. Tonnes mined were down
from plan as mine operations were scaled back during mill downtime
and more focus was placed on development to support the expanded
mining plan at the Pine Cove Pit. As at June
30, 2019, the operation had stockpiled over 15,800 tonnes of
ore with an estimated average grade of 1.62 g/t.
The mine operations achieved a strip ratio of 3.6 waste tonnes
to ore tonnes between Stog'er Tight and development at Pine Cove,
consistent with the strip ratio in the first quarter of 2019. The
strip ratio has decreased compared to Q2 2018, when development
activity was focused on the initial development of the West Pit of
Stog'er Tight.
Ore mined during Q2 2019 was up significantly over the second
quarter of 2018, when mining activity in the main Pine Cove Pit was
finishing and the focus was on the development of the Stog'er Tight
Pit, while stockpiles from Pine Cove provided mill throughput.
Going forward in 2019, mine operations will remain focused on
pushbacks and mine production from the south and southwest areas of
the Pine Cove Pit. Permitting activities continue with respect to
the Argyle Deposit; the Company has now received a Mining Lease for
Argyle and has submitted the development and rehabilitation plan
for review by the Department of Natural Resources in Newfoundland. With the shift of the mine plan
to Pine Cove, the Company will continue to optimize the Argyle
Deposit, incorporating recent drilling results, while advancing
permitting activities.
Qualified Person
Gordana Slepcev, P. Eng., Chief
Operating Officer, Anaconda Mining Inc., is a "qualified person" as
such term is defined in National Instrument 43-101 and has reviewed
and approved the technical information and data included in this
press release.
ABOUT ANACONDA
Anaconda is a TSX and OTCQX-listed gold mining, development, and
exploration company, focused in Atlantic
Canada. The company operates mining and milling operations
in the prolific Baie Verte Mining District of Newfoundland which includes the
fully-permitted Pine Cove Mill, tailings facility and deep-water
port, as well as ~11,000 hectares of highly prospective mineral
lands including those adjacent to the past producing, high-grade
Nugget Pond Mine. Anaconda is also developing the Goldboro Gold
Project in Nova Scotia, a
high-grade resource and the subject of an on-going feasibility
study.
NON-IFRS MEASURES
Anaconda has included certain non-IFRS performance measures
as detailed below. In the gold mining industry, these are common
performance measures but may not be comparable to similar measures
presented by other issuers. The Company believes that, in addition
to conventional measures prepared in accordance with IFRS, certain
investors use this information to evaluate the Company's
performance and ability to generate cash flow. Accordingly, it is
intended to provide additional information and should not be
considered in isolation or as a substitute for measures of
performance prepared in accordance with IFRS.
Operating Cash Costs per Ounce of Gold – Anaconda calculates
operating cash costs per ounce by dividing operating expenses per
the consolidated statement of operations, net of silver sales
by-product revenue, by the gold ounces sold during the applicable
period. Operating expenses include mine site operating costs such
as mining, processing and administration as well as royalties,
however excludes depletion and depreciation and rehabilitation
costs.
Average Realized Gold Price per Ounce Sold – In the gold
mining industry, average realized gold price per ounce sold is a
common performance measure that does not have any standardized
meaning. The most directly comparable measure prepared in
accordance with IFRS is gold revenue. The measure is intended to
assist readers in evaluating the revenue received in a period from
each ounce of gold sold.
Working Capital – Working capital is a common measure of
near-term liquidity and is calculated by deducting current
liabilities from current assets.
FORWARD-LOOKING STATEMENTS
This news release contains "forward-looking information"
within the meaning of applicable Canadian and United States securities legislation.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as "plans", "expects", or "does
not expect", "is expected", "budget", "scheduled", "estimates",
"forecasts", "intends", "anticipates", or "does not anticipate", or
"believes" or variations of such words and phrases or state that
certain actions, events or results "may", "could", "would",
"might", or "will be taken", "occur", or "be achieved".
Forward-looking information is based on the opinions and estimates
of management at the date the information is made, and is based on
a number of assumptions and is subject to known and unknown risks,
uncertainties and other factors that may cause the actual results,
level of activity, performance or achievements of Anaconda to be
materially different from those expressed or implied by such
forward-looking information, including risks associated with the
exploration, development and mining such as economic factors as
they effect exploration, future commodity prices, changes in
foreign exchange and interest rates, actual results of current
production, development and exploration activities, government
regulation, political or economic developments, environmental
risks, permitting timelines, capital expenditures, operating or
technical difficulties in connection with development activities,
employee relations, the speculative nature of gold exploration and
development, including the risks of diminishing quantities of
grades of resources, contests over title to properties, and changes
in project parameters as plans continue to be refined as well as
those risk factors discussed in Anaconda's annual information form
for the year ended December 31, 2018,
available on www.sedar.com. Although Anaconda has attempted to
identify important factors that could cause actual results to
differ materially from those contained in forward-looking
information, there may be other factors that cause results not to
be as anticipated, estimated or intended. There can be no assurance
that such information will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such information. Accordingly, readers should not place undue
reliance on forward-looking information. Anaconda does not
undertake to update any forward-looking information, except in
accordance with applicable securities laws.
SOURCE Anaconda Mining Inc.