Pan
African Resources PLC
(Incorporated
and registered in England and Wales
under
Companies Act 1985 with registered
number
3937466 on 25 February 2000)
Share code
on AIM: PAF
Share code
on JSE: PAN
ISIN:
GB0004300496
ADR code:
PAFRY
(“Pan
African” or “the Company” or “the Group”)
|
Pan
African Resources Funding Company Limited
Incorporated
in the Republic of South Africa
with
limited liability
Registration
number: 2012/021237/06
Alpha
code: PARI
|
|
OPERATIONAL
UPDATE FOR THE YEAR ENDED 30 JUNE
2024 AND BOARD CHANGE
Pan
African is pleased to provide its shareholders and noteholders with
a preliminary operational update for the financial year ended
30 June 2024 (“Reporting Period”), an
update on the Mogale Tailings Retreatment project (MTR Project)
commissioning and information on progress with its renewable energy
projects. Group full year production of 186,039oz was within
guidance and increased by 6.2% year-on-year. The average achieved
gold price for the Reporting Period was US$2,021/oz (R1,215,827/kg at an exchange rate of
US$/ZAR18:71), and will be the
highest on record for the Group.
KEY
FEATURES
-
Significant
improvement in the Group’s already industry leading safety
statistics across all operations, as follows:
- the total
reportable injury frequency rate reduced to 5.47 per million man
hours (FY2023: 8.13)
- the lost
time injury frequency rate improved to 1.62 per million man hours
(FY2023: 2.54)
- the
reportable injury frequency rate improved to 0.70 per million man
hours (FY2023: 1.29)
-
Gold
production increased by 6.2% to 186,039oz (FY2023: 175,209oz), in
line with the revised guidance previously announced, with
operations performing consistent with expectations: (FY2023 figures
in brackets)
|
71,470oz
(64,586oz)
|
-
Evander
Mines underground:
|
40,869oz
(40,175oz)
|
|
54,812oz
(50,573oz)
|
-
Barberton
Tailings Retreatment Plant (BTRP):
|
18,888oz
(19,875oz)
|
-
The
Group’s all-in sustaining costs (AISC) for the Reporting Period is
expected to be approximately US$1,350/oz, at an average exchange rate of
US$/ZAR: 18.71
-
A delay in
commissioning the ventilation shaft for hoisting at Evander 8
underground operations adversely impacted production in the last
two months of the Reporting Period, resulting in the Group not
achieving the higher end of production guidance and also negatively
impacted unit costs. Work is now scheduled to be completed in the
coming weeks, after which the full benefits of the improved ore
flow will achieve the planned increased production
profile
-
Exceptional
progress has been made with the MTR Project’s construction, which
is nearing its final stages. Plant commissioning and first gold
production is anticipated ahead of schedule in October 2024, with steady state production
expected during December 2024.
Furthermore, the project is expected to be completed below
budget
- Including
the Soweto Cluster Mineral Resources, as per the internal
pre-feasibility study outcomes reported in May 2024, MTR is expected to produce
approximately 60koz/year over a 21-year life of mine, at a forecast
AISC of less than US$900/oz
-
Previously
announced FY2025 production guidance reiterated at between
215,000oz and 225,000oz
-
Net debt
at the end of the Reporting Period increased to US$106.4 million (FY2023: US$22.0 million), mainly attributable to
construction costs at the MTR Project (US$71.5 million for the year), expansion capital
expenditure in respect of Evander 8 Shaft 25-26 Level development
and Elikhulu’s new tailings storage facility extension
(US$23.8 million) and Fairview solar
plant expenditure (US$9.9
million)
-
Construction
of the Fairview Mine’s 8.75MW solar photovoltaic plant has been
completed, with final commissioning in the coming weeks
BOARD
CHANGE
The
Group’s financial director, Deon
Louw, informed the Company of his intention to retire with
effect from 30 September 2024. He
will however, continue as a consultant to the Group. Deon was
appointed in this role in March 2015
and has contributed significantly to Pan African’s operations and
growth throughout his tenure. Marileen
Kok will succeed Deon Louw as
Group financial director and, subject to completion of standard
director due diligence, will be appointed to the Company’s board of
directors. Marileen joined Pan African Resources as Group Financial
Manager in January 2020 and has
extensive experience in financial reporting, corporate finance,
governance and regulatory compliance.
PROGRESS
WITH RENEWABLE ENERGY PROJECTS AND FUNDING
Construction
and mechanical assembly, including installation of the solar
trackers, for Fairview Mine’s 8.75MW solar photovoltaic generating
plant was completed at the end of June
2024, enabling the commencement of the required test work to
ensure that the facility complies with operating standards and
regulatory requirements. First power generation is anticipated in
the next month.
This solar
plant is expected to provide 15% of Barberton Mines’ energy
requirements, with annual electricity cost savings of approximately
USD2.4*
million,
at current Eskom tariffs.
Independent
feasibility studies are in progress to expand Evander Mines’
current 9.975MW solar facility and also for a new solar plant at
the Mogale Tailings Retreatment operation. These studies are
anticipated to be completed in the third quarter of the 2024
calendar year.
Evander
Mines’ and Barberton Mines’ solar photovoltaic generating plants
are now funded by means of a US$19.4
million*,
5-year Green Loan facility which became effective in June 2024. This facility also provides for an
accordion option of US$13.9
million*
to provide
for the Group’s future renewable energy funding
requirements.
*ZAR amounts converted at an exchange rate of US$/ZAR18:00
Pan
African CEO Cobus Loots
commented:
“We
are pleased that the Group has again delivered into its production
guidance, while further improving safety rates and maintaining its
industry leading safety performance during the 2024 financial
year.
The
surface tailings retreatment operations at Elikhulu and the BTRP
performed exceptionally well, with some of the lowest all-in
sustaining production costs in Southern
Africa. The Group is poised to deliver another world class
tailings retreatment operation ahead of schedule and below budget
in the coming months with the MTR Project.
Barberton
Mines has seen a steady improvement in gold production, with
planned optimisation initiatives to increase ore tonnages expected
to further bolster gold production in the next financial year.
Commissioning of the ventilation shaft hoisting system at Evander
underground during the start of the 2025 financial year, will
substantially improve efficiencies and reduce reliance on the
cumbersome conveyor system currently in use, vastly improving this
operation’s production profile and facilitate the 25-26 Level
project’s development.
We
would like to thank Deon for his commitment and the significant
contribution he has made to the Group over the years. We wish him
all the best in his retirement and look forward to continue working
with him on various projects. We would like to extend our
congratulations to Marileen Kok who
will be taking over from Deon as Group financial director, and
trust in her seamless transition into the role.
We
look forward to presenting our 2024 year-end financial results in
September, and to provide further details on developments at our
operations and exciting pipeline of growth projects that will
significantly increase the Group’s total annual gold production in
FY2025.”
FINANCIAL
RESULTS PRESENTATION, OPERATIONAL AND GROWTH PROJECTS
UPDATE
A detailed
update on the Group’s operations and production growth projects
will be included in the Company’s annual final results presentation
and 2024 financial year annual reporting suite, scheduled to be
released on 11 September
2024.
The
information contained in this update is the responsibility of Pan
African’s board of directors and has not been reviewed or reported
on by the Group’s external auditors.
Certain
information communicated in this announcement was, prior to its
publication, inside information for the purposes of Article 7 of
Regulation 596/2014.
Rosebank
29 July 2024
For
further information on Pan African Resources, please visit the
Company's website at
www.panafricanresources.com
Corporate
information
|
Corporate
Office
The Firs
Building
2nd
Floor,
Office 204
Cnr.
Cradock and Biermann Avenues
Rosebank,
Johannesburg
South
Africa
Office: +
27 (0)11 243 2900
info@paf.co.za
|
Registered
Office
2nd
Floor
107
Cheapside
London
EC2V
6DN
United
Kingdom
Office: +
44 (0)20 3869 0706
info@paf.co.za
|
Chief
Executive Officer
Cobus
Loots
Office: +
27 (0)11 243 2900
|
Financial
Director
Deon
Louw
Office: +
27 (0)11 243 2900
|
Head:
Investor Relations
Hethen
Hira
Tel: + 27
(0)11 243 2900
E-mail:
hhira@paf.co.za
|
Website:
www.panafricanresources.com
|
Company
Secretary
Jane
Kirton
St
James's Corporate Services Limited
Office: +
44 (0)20 3869 0706
|
Nominated
Adviser and Joint Broker
Ross
Allister/Georgia Langoulant
Peel
Hunt LLP
Office:
+44 (0)20 7418 8900
|
JSE
Sponsor
Ciska
Kloppers
Questco
Corporate Advisory Proprietary Limited
Office: +
27 (0)11 011 9200
|
Joint
Broker
Thomas
Rider/Nick Macann
BMO
Capital Markets Limited
Office:
+44 (0)20 7236 1010
|
|
Joint
Broker
Matthew
Armitt/Jennifer Lee
Joh.
Berenberg, Gossler & Co KG (Berenberg)
Office:
+44 (0)20 3207 7800
|