Sigma Lithium Resources Corporation (“
Sigma” or
the “
Company”) (
TSX-V:
SGMA ) (
OTC- QB: SGMLF )
is pleased to announce the exceptional results of a Preliminary
Economic Assessment (the “
PEA”) for an expansion
of its Grota do Cirilo Project (the “
Project”),
doubling its annual production capacity of battery-grade,
high-purity, environmentally sustainable 6% lithium concentrate
(“
Green Battery Grade Lithium Concentrate”) to
approximately 440,000 tpa (66,000 LCE).
The expansion of Project achieves significant
operational economies of scale resulting from adding a second
environmentally friendly dense media separator processing line
train to its digitally automated production plant (the
“Production Plant”). The second line is expected
to produce an average of 222,000 tpa (33,000 LCE) of Battery Grade
Green Lithium Concentrate (“Phase 2”),
doubling the initial planned annual production capacity of
220,000tpa (33,000 LCE) (“Phase 1”).
Phase 1 is described in the Sigma’s technical
report titled “Grota do Cirilo Lithium Project, Araçuaí and
Itinga Regions, Minas Gerais, Brazil, National Instrument 43-101
Technical Report on Feasibility Study Final Report” dated October
18, 2019 (the “2019 Feasibility Study
Report”).
The exceptional PEA results demonstrate the cost
benefit of vertically integrating the second production line and
utilizing as a feedstock spodumene ore from the Project’s second
deposit Barreiro (the “Second Deposit” or
“Barreiro”), mining an average of 1.68Mt per year
during 12.7 years of mine life. Barreiro is a high-purity,
high-grade lithium deposit, with 20.485Mt of measured &
indicated mineral resources at 1.43% Li2O and 1.909Mt of inferred
mineral resources and shallow, near surface mineralization ideal
for open pit mining. The Second Deposit’s mineral reserve is
expected to be declared later this quarter when the ongoing
pre-feasibility study (“PFS”) is completed.
The PEA projects capital expenditures of US$44.5
million (year 0) including plant and mine construction, based on an
optimized mine plan. Incremental expenditures of US$28.9 million
(additional mine stripping on year 5) and US$9.6 million
(additional mine stripping on year 6) is expected to be covered by
the Company’s internal cash flow generation. As Phase 2
construction is planned sequentially to the commissioning and
production ramp up of Phase 1, the Company is expected to be fully
operational with Phase 1 by the time Phase 2 is commissioned.
Therefore, additional working capital for commissioning of the
second DMS line as well as certain deferred capital expenditures
may potentially also be covered by the internal cash flow
generation of the business.
According to the PEA, Phase 2 could potentially
double total estimated NPV of the Project to US$844 million:
- NPV of Phase 2 Production is estimated to be US$449 million by
the PEA.
- NPV of Phase 1 Production is estimated to be US$395 million by
the 2019 Feasibility Study Report (calculated with price curves
starting from US$650/t in 2021, below current market prices at CIF
China port, and operational expenditures reductions limited by the
sensitivity analysis in 2019 to be 20%, despite Brazilian currency
devaluation since 2019 of approximately 35%)
Barreiro, the Project’s second deposit, has a
similar exceptional mineralization to the Project’s first deposit,
Xuxa, with large crystals of coarse spodumene. As a result, the
lithium achieves outstanding recoveries in an environmentally
friendly DMS plant, with similar flowsheet (and capital costs) to
the first production line, without requiring a significantly more
capital-intensive flotation process.
During Detailed Engineering for Phase 1, the
Company evaluated operational and capital expenditure trade-offs to
be achieved in the expansion of the Production Plant capacity,
including design features to allow for the seamless incorporation
of a second production line.
Metallurgical HLS tests performed on the
spodumene ore for Phase 2 in sizes of 6.3mm and 10mm achieved
excellent lithium recoveries of 70.2% and 66.1%, respectively,
producing a 6% Li2O battery-grade spodumene concentrate within the
highest levels of specifications demanded by the chemical lithium
market without the use of flotation or
hazardous chemical reagents, in the concentration process. This is
consistent with Sigma’s intention to continue to process its
lithium ore in a “green” environmentally friendly and
sustainable manner.
The Company has been working with SGS and
Primero to prepare a PFS for the Phase 2 production, targeting its
completion in June 2021, further continuing towards feasibility
analysis in the second half of 2021. The Company and Primero
completed all the metallurgical and variability DMS pre-feasibility
test work at SGS laboratories.
The Project is located in one of the world’s
largest mining provinces in southeast of Brazil: with full mining
infrastructure and highways linking the Project to a commodities
shipment capable port. Site infrastructure has been mostly in place
and is currently being upgraded for Phase 1 production. The Project
is powered by 100% clean energy: transmission towers and lines on
site link the Project to a hydroelectricity plant 50km away.
SIGMA PHASED PRODUCTION APPROACH FOR THE
PROJECT AND COMMERCIAL STRATEGY
As a result of the substantial size of its
mineral resources, the Company has sub-divided the development of
the Project into an incremental and phased build-out.
Sigma is working to advance Phase 2 to a
construction ready status by the end of 2021 or early 2022. Phase 2
construction is projected to commence once the commissioning and
production ramp up of Phase 1 is completed, which is expected in
the third quarter of 2022.
This phased approach to development of the
Project increases financial flexibility and reflects the Company’s
ethos and discipline in managing construction risk, while seeking
to create substantial shareholder value. It also reduces commercial
risk by aligning commercial integration of the Project’s production
growth profile with the demand of its customers in the lithium-ion
battery supply chain.
As a result of the high quality and low
impurities of its lithium products, the Company has experienced
significant commercial success with various customers in the
electric vehicle supply chain. As a result, the Company made a
decision to accelerate the required studies for the development of
Phase 2, to potentially respond to a significant increase in demand
from its customers, following the significant improvement in the
outlook of global demand for ESG-sustainable lithium products.
By demonstrating its ability to expand
production in the near term, the Company seeks to take advantage of
the current strong demand, and solidify its unique commercial
advantage in delivering environmentally, socially sustainable and
low carbon high purity lithium products to like-minded cathode and
battery producers.
The technical report for the PEA will be filled
on SEDAR (and will also be available at www.sigmalithium
resources.com within 45 days of this news release. Readers are
encouraged to read the technical report in its entirety, including
all qualifications and assumptions related to the PEA results
announced in the news release.
FIRST QUARTER 2021 RESULTS: PHASE 1
CONSTRUCTION & PROJECT DEVELOPMENT UPDATE
The Company has reported unaudited financial and
operating results for the first quarter ended March 31, 2021
(“1Q 2021”). Overall, the Company made significant
progress towards construction, despite the circumstances created by
the COVID-19 pandemic.
Highlights of Phase 1 construction update
include:
- All Detailed Engineering and Pre-Construction workstreams
continued to advance to achieve production in the third quarter of
2022.
- At the end of Detailed Engineering, the Project will move to
the Implementation/Deployment Stage (FEL 3 / Class 3) in the third
quarter of 2021, with increased accuracy from the capital estimates
included in the Feasibility Study Report.
- Strict COVID-19 health and safety protocols are in place.
Without any cases of COVID-19 reported at site since April 30,
2021.
- Construction site early works are ongoing (clearing and
grubbing, laydowns & topsoil removal):
- Followed by additional topsoil removal and foundation
preparations, once results and geotechnical modelling of Production
Plant foundation are concluded.
- Concluded all field Pre-Construction activities for the
Production Plant.
- Primero conducted a review of the current designs, assessing
the impact on the foundation design and earthwork quantities, based
on the geotechnical assessment for the civil engineering and
concluded that the soil condition does not create any risk for
construction of the foundations of the Production Plant.
- Completed trade-off studies for the optimization and
expandability/scalability of the overall plant design, evaluating
multiple design options, performing tests and analysis to select
the preferred option.
- Expansion design features are being determined in order to
allow for the incorporation of a second production line for
Production Phase 2.
- Concluded the definition of the streamlined scope and design of
the non-process, non-plant infrastructure (building
infrastructure).
- Completed several critical workstreams involved in the
Pre-Construction of the Phase 1 Mine within the scheduled and
budgeted parameters.
- This includes all field-based activities required for the
geotechnical validation at detailed engineering level, as well as
critical field work of hydrogeological validation.
- All remaining state permits required to commence construction
are forecasted to be issued by the third quarter of 2021.
Highlights of ESG:
- Significantly advanced the life cycle analysis and carbon
credits audit workstreams, planning to publish results in the third
quarter of 2021, including more information on its carbon
in-setting and offsetting strategy.
- Continued to progress on the creation and structuring of an
independent agency for private investment promotion and economic
diversification of the region (“Investment
Agency”), with institutional support from the development
bank of the state of Minas Gerais (“BDMG”), from
the secretary of special development projects
(“INDI”) and from the Mayors of the two
municipalities.
- Expanded humanitarian relief during the months of COVID-19
pandemic for the population living in extreme vulnerability in the
region, as follows:
- Distributed 1,200 basic food baskets in two months, feeding
approximately 2,400 people per month.
- Agreed to extend the initiative in a collaboration with Rotary
Club, distributing an additional 1,000 food baskets (feeding an
additional 4,000 people).
- Repeated COVID-19 prevention initiatives from March 2020, and
distributed 12,000 units of hospital disinfectant, as well as 2,400
hand sanitizers “family size”, totaling 840 kg of the product.
- Initiatives funded at cost as a result of financial sponsorship
from Sigma’s key shareholders and stakeholders.
Corporate:
- As at the date of this MD&A, the Company has $41.3 million
(US$33.6 million) in cash and cash equivalents, out of which
approximately $33.8 million (US$28 million) is held in a
construction segregated savings account.
- Additionally, it has an undrawn credit line balance of
US$4,037,150 under the US$5,000,000 unsecured revolving credit
facility (the “A10 Credit Facility”)
- The Company has announced that it is considering a potential
listing of the Common Shares in a major U.S. stock exchange market
with a view to increasing access to U.S. capital markets and
enhancing overall shareholder value.
- Consistent with its retention policies to manage human capital
as well as with its ethos of aligning incentives amongst all
stakeholders and shareholders, most of the compensation of the
Company’s key personnel is equity based.
- To that regard, the Company grated an aggregate of 996,333
Restricted Share Units to officers and an aggregate of 385,000
Restricted Share Units to key employees and consultants. As per the
ESOP, Ana Cabral-Gardner and Calvyn Gardner were not awarded equity
compensation.
Calvyn Gardner, Sigma CEO said that “We continue
to progress updating the current Feasibility Study Report with the
pre-feasibility for the Phase 2, which would be fully integrated
into the production complex for the Phase 1, currently in
pre-construction. The previous work undertaken when completing our
2019 Feasibility Study Report, as well as detailed engineering
phase of pre-construction for Phase 1, means that substantial plant
engineering design as well as mining cost databases are available
to support the technical studies required for this update,
expediting and de-risking its execution.”
Ana Cabral-Gardner, Sigma President and Chief
Operating Officer stated that “The doubling of Sigma’s near-term
planned capacity to 66,000 LCE, with low additional capex has the
potential to significantly transform our scale and relevance. It
further increases our uniqueness as a global supplier of
environmentally sustainable green lithium concentrate, while
consolidating our strategic importance upstream as a source of
high-purity green lithium products for our current and new
customers, as they advance their plans for cathodes and battery
cell production facilities in Europe and the United States,
effectively building a sizable Atlantic lithium supply chain”.
Figure 1a: Plant 3D layout of the
industrial complex and production facility for Phase 1 and Phase
2
https://www.globenewswire.com/NewsRoom/AttachmentNg/97c94eae-2ada-4337-abbc-0ea37cc1790e
Figure 1b: Plant 3D layout of the
industrial complex and production facility for Phase 1 and Phase
2
https://www.globenewswire.com/NewsRoom/AttachmentNg/d56a4a2d-f9a8-4006-81cd-a6f598fd9cfe
1 - SUMMARY OF PROJECT FINANCIAL
PERFORMANCE RESULTS
1.1 Project Economics
An economic analysis for Phase 2 was developed
using the discounted cash flow method and was based on the data and
assumptions for capital and operating costs for mining, processing
and associated infrastructure. The basis for forecasted spodumene
concentrate lithium pricing was provided by Roskill’s arm’s length
price curve with an internal adjustment starting with 2022 price of
US$750/t (below current 2021 spot market). Although approximately
70% of the Company’s operational costs are incurred in Brazilian
reais, the assumptions were fixed in USD, the base currency for the
financial model. Key assumptions and results of the economic
evaluation are displayed in the tables 1 and 2 below.
Table 1.1.1: Financial Results Summary for Phase 2
During the Estimated Life of Mine
Financial Summary |
Unit |
Total |
|
|
|
Net Present Value (NPV 8%) After-Tax |
US$ M |
$449 |
Internal Rate of Return (IRR) After-Tax |
% |
208% |
|
|
|
After-Tax Payback Period |
Years |
0.4 |
Capital Intensity (Initial Capex/ Annual Production) |
US$ per tonne |
$200 per tonne |
NPV: Capex (ratio) |
Ratio X:1 |
10:1 |
|
|
|
Table 1.1.2: Key Assumptions Utilized in
the Project Economics
Assumptions |
Unit |
Total |
Annual Lithium Concentrate Production at 6% |
tonnes |
222,147 |
Project Estimated Life (Integrated Mine/Plant) |
years |
12.7 |
Discount Rate |
% |
8 |
Total Royalty (1) |
% |
3 |
Average Corporate Tax (2) |
% |
15.3 |
CAPEX |
|
|
Year 0 (plant construction and starter mining pit) |
US$ M |
44.5 |
Year 5 (pit expansion) |
US$ M |
28.9 |
Year 6 (pit expansion) |
US$ M |
9.7 |
OPEX |
|
|
Average total cash cost (FOB Plant) |
US$/t |
256 |
All-in sustaining cost (“AISC”) CIF China |
US$/t |
360 |
Average Selling Price |
US$/t |
750 |
|
|
|
(1) CFEM and NSR#1
Royalties(2) Sudene Corporate Tax
Benefit During 8 first years. 34% for the following
years
Table 1.1.3: Phase 2 Estimated Revenue,
Operating Costs and EBITDA
Production: Total tonnes of lithium
concentrate |
|
2,870,444 tonnes |
Average Price for project life |
|
$750/t |
|
AnnualizedUS$ M |
TotalUS$ M |
Gross Revenue |
$ 170 |
|
US$ 2,153 |
Less: Total Royalties |
($5) |
|
($61) |
(-)
CFEM |
($3) |
|
($43) |
(-) Net
Smelter Royalties |
($1) |
|
($18) |
Net Revenues |
$165 |
|
$2,092 |
Less: Site Operating Costs |
($84) |
|
($1,066) |
(-)
Mining |
($45) |
|
($571) |
(-)
Processing |
($12) |
|
($156) |
(-)
Selling, General & Administration |
($1) |
|
($8) |
(-)
Transportation Costs |
($24) |
|
($299) |
(-)
Depreciation |
($2) |
|
($32) |
EBIT |
$81 |
|
$1,026 |
% EBIT Margin |
49% |
|
49% |
|
|
|
(+)
Depreciation |
$2 |
|
$32 |
EBITDA |
$83 |
|
$1,058 |
% EBITDA Margin |
51% |
|
51% |
|
|
|
(-)
Taxes |
($16) |
|
($203) |
(+/-)
WC |
($0) |
|
($3) |
(-)
Capex |
($7) |
|
($85) |
After-Tax Free Cash Flow |
$60 |
|
$767 |
% Margin |
37% |
|
37% |
1.2 - Capital and Operating Costs
SGS and GE-21 completed the Class 5 estimate
(+/- 30%) of the capital and operating costs, incorporating
engineering from the ongoing detailed engineering and FEED (front
end engineering design) of Sigma’s Phase 1 Production Plant. The
Capex has been prepared to reflect optimized site layouts, mine
scheduling, plant and equipment design and installation. Phase 2
development significantly leverages the Production Plant
infrastructure that will be constructed for Phase 1. Site
infrastructure has been mostly in place (Sigma’s assets are from a
brownfield project) and is currently being upgraded for Phase
1.
Operating cost estimates were provided by GE-21
and are based on an owner-operated model and have an accuracy of
+/-30 %. The crushing contracting, substation rental, mobile
equipment rental and product transport operating costs were
incorporated in the overall operating cost.
The cash operating costs were developed based on
third party contract mining and outsourced crushing, as well as on
the Phase 2 Plant processing cost. The Phase 2 Production is
forecasted to have very low operating costs at US$256 per tonne of
concentrate as a result of its high grade, high DMS recoveries, low
levels of impurities, low cost of electricity and general low
country costs. Table 1.2.1 shows the anticipated average operating
costs over the LOM. Table 1.1.3 presents the forecast revenue and
costs on both a total and average LOM basis.
Table 1.2.1: Operating Cost Estimate
Cost Category |
LOM AverageUS$/t |
Mining |
$199 |
Processing |
54 |
SG&A |
3 |
Sub-Total |
$ 256 |
Transportation by Truck Mine to Port |
34 |
Shipping to China Port (average) |
70 |
Sub-Total |
104 |
Total |
$ 360 |
The CAPEX has been prepared to reflect optimized
site layouts, mine scheduling, plant and equipment design, supply
and installation. Phase 2 development significantly leverages the
plant infrastructure that will be constructed for Phase 1. Site
infrastructure has been mostly in place (Sigma’s assets are from a
brownfield project) and is currently being upgraded for Phase
1.
The Company has evaluated operational and
capital expenditure trade-offs to be achieved as a result of
possible design alternatives for the crushing circuit to be
installed at the Production Plant. These trade-offs aim to further
de-risk and optimize the construction of the Production Plant. The
scalability of the Production Plant was also studied to determine
expansion design features to allow for the incorporation of a
second production line for Phase 2 high-grade green lithium
production.
The total initial development CAPEX for Phase 2
is estimated to be US$ 44.5 million. The estimate is detailed in
Table 1.2.2 and includes processing, mine equipment purchases,
infrastructures, contingency and other direct and indirect costs.
Incremental expenditures of US$28.9 million (additional waste mine
stripping in year 5) and US$9.6 million (additional waste mine
stripping in year 6) can be funded by internal cash flow
generation.
Table 1.2.2 Summary of Capital Costs
Estimates and Operating Cost Infrastructure Phase 2
Capex Item (US$ Thousands) |
Year 0 |
Year 5 |
Year 6 |
MC |
Processing Line (Plant) |
29,884 |
– |
– |
– |
Plant Additional Infrastructure |
6,959 |
– |
– |
– |
Owners Cost |
1,172 |
– |
– |
– |
Mine Preparation & Infrastructure |
6,511 |
– |
– |
– |
Further Opening of Mining Pit (Year 5) |
– |
28,975 |
– |
– |
Further Opening of Mining Pit (Year 6) |
– |
– |
9,658 |
– |
Mine Closure |
– |
– |
– |
2,180 |
Total Capex (Phase 2) |
44,527 |
28,975 |
9,658 |
2,180 |
Table 1.2.2 Detailed Capital Costs
Estimates for Second Line Plant and Infrastructure
AREA |
DIRECT |
INDIRECT |
CONTINGECY |
RECOVERABLE |
TOTAL |
(USD) |
(USD) |
(USD) |
(USD) |
(USD) |
PROCESSING PLANT |
|
|
|
|
|
010 - Engineering, Procurement and Management |
|
– |
|
2,562,000 |
|
384,000 |
|
(88,000 |
) |
|
2,858,000 |
015 - Commissioning |
|
– |
|
1,096,000 |
|
164,000 |
|
(30,000 |
) |
|
1,230,000 |
030 - Vendor Representatives |
|
– |
|
114,000 |
|
18,000 |
|
(1,000 |
) |
|
131,000 |
040 - Construction Indirects - Contractors |
|
– |
|
1,722,000 |
|
258,000 |
|
(35,000 |
) |
|
1,945,000 |
200 - Process Plant Overall |
|
130,000 |
|
– |
|
12,000 |
|
(24,000 |
) |
|
118,000 |
220 - Contract Crushing |
|
4,044,823 |
|
– |
|
621,545 |
|
|
4,666,368 |
310 - DMS |
|
13,853,000 |
|
– |
|
1,694,000 |
|
(2,173,000 |
) |
|
13,374,000 |
314 - Ultrafines DMS |
|
2,599,000 |
|
– |
|
305,000 |
|
(401,000 |
) |
|
2,503,000 |
340 - Concentrate Handling |
|
1,014,000 |
|
– |
|
110,000 |
|
(110,000 |
) |
|
1,014,000 |
350 - Tails Handling |
|
1,945,000 |
|
– |
|
197,000 |
|
(290,000 |
) |
|
1,852,000 |
370 - Process Plant Services |
|
194,000 |
|
– |
|
23,000 |
|
(24,000 |
) |
|
193,000 |
Subtotal Processing Plant |
$ |
23,779,823 |
$ |
5,494,000 |
$ |
3,786,545 |
$ |
(3,176,000 |
) |
$ |
29,884,368 |
SITE INFRASTRUCTURE |
|
|
|
|
|
010 - Engineering, Procurement and Management |
|
– |
|
1,662,000 |
|
22,000 |
|
(30,000 |
) |
|
1,654,000 |
020 - Subconsultants |
|
– |
|
– |
|
– |
|
– |
|
|
– |
040 - Construction Indirects - Contractors |
|
– |
|
293,000 |
|
5,000 |
|
(11,000 |
) |
|
287,000 |
120 - Bulk Earthworks |
|
2,220,300 |
|
– |
|
263,100 |
|
(75,900 |
) |
|
2,407,500 |
370 - Process Plant Services |
|
107,000 |
|
– |
|
7,000 |
|
(16,000 |
) |
|
98,000 |
390 - Plant Buildings |
|
151,000 |
|
– |
|
16,000 |
|
(6,000 |
) |
|
161,000 |
600 - Infrastructure |
|
756,000 |
|
– |
|
55,000 |
|
(110,000 |
) |
|
701,000 |
620 - Water & Sewerage |
|
483,000 |
|
– |
|
52,000 |
|
(45,000 |
) |
|
490,000 |
630 - Infrastructure General |
|
327,000 |
|
– |
|
60,000 |
|
(11,000 |
) |
|
376,000 |
650 - Substation |
|
8,000 |
|
– |
|
1,000 |
|
– |
|
|
9,000 |
660 - Buildings - Admin |
|
558,000 |
|
– |
|
18,000 |
|
(19,000 |
) |
|
557,000 |
770 - Mine Mobile Equipment - LME |
|
60,000 |
|
– |
|
6,000 |
|
(2,000 |
) |
|
64,000 |
780 - Fuels |
|
152,000 |
|
– |
|
14,000 |
|
(11,000 |
) |
|
155,000 |
Subtotal Site Infrastructure |
$ |
4,822,300 |
$ |
1,955,000 |
$ |
519,100 |
$ |
(336,900 |
) |
$ |
6,959,500 |
OWNERS COST |
|
|
|
|
|
810 - Owners Project Costs |
|
– |
|
973,000 |
|
146,000 |
|
(33,000 |
) |
|
1,086,000 |
811 - Owners Temporary Infrastructure |
|
– |
|
– |
|
– |
|
– |
|
|
– |
840 - Spares |
|
– |
|
91,000 |
|
13,000 |
|
(18,000 |
) |
|
86,000 |
Subtotal Owners Cost |
|
– |
|
1,064,000,0 |
|
159,000,0 |
|
(51,000,0 |
) |
|
1,172,000,0 |
TOTAL CAPEX FOR THE PHASE 2 PRODUCTION PLANT |
$ |
28,602,123 |
$ |
8,513,000 |
$ |
4,464,645 |
$ |
(3,563,900 |
) |
$ |
38,015,868 |
Table 1.2.3 Detailed of Capital Costs Estimates for
Phase 2 Mining
Capex Item (US$) |
Year 0 |
Year 5 |
Year 6 |
MC |
Mine Preparation & Infrastructure |
$ 6,511 |
|
– |
|
– |
|
– |
Further Opening of Mining Pit (Year 5) |
|
– |
$ 28,975 |
|
– |
|
– |
Further Opening of Mining Pit (Year 6) |
|
– |
|
– |
$ 9,658 |
|
– |
Mine Closure |
|
– |
|
– |
|
– |
$ 2,180 |
Total Capex |
|
6,511 |
|
28,975 |
|
9,658 |
|
2,180 |
1.3 - Sensitivity Analysis
As displayed in Table 1.1.1, the PEA projects
potential strong financial outcomes with a pre-tax NPV (discounted
at 8%) of US$449 million and IRR of 208%. Table 1.3. analyses the
impact on NPV when spodumene pricing and recovery percentages
fluctuate.
The Project NPV is most sensitive to movements
in the price of spodumene, metallurgical recovery rate of the
lithium at the Second Plant. Foreign exchange fluctuations impact
operating cash costs (mostly derived from Brazilian Real) and
development capital (approximately 70% derived from Brazilian Real
prices)
Table 1.3: Sensitivity Analysis: NPV to
Price and Recovery
Sensitivity Matrix |
After-Tax NPV (US$ M) |
|
|
Spodumene Price (CIF
China)(US$/t) |
Recovery (%) |
|
60.4 |
% |
66.0 |
% |
|
|
|
$ 650 |
$ 260 M |
$ 320 M |
|
|
700 |
|
319 |
|
384 |
|
|
750 |
|
378 |
|
449 |
|
|
800 |
|
437 |
|
513 |
|
|
850 |
|
496 |
|
578 |
|
1.4 – Commercial and Offtake Strategies
As a result of the high quality and low
impurities of its planned lithium concentrate Sigma has experienced
significant commercial success in negotiating offtake agreements
with various customers in the electric vehicle supply chain. Sigma
entered the offtake negotiations undertaking a long-term view for
the growth of the market and decided to replicate the longer term
(five years) contract structures practiced by the lithium chemicals
with their cathode industry and other customers in the supply
chain. Sigma has been negotiating offtake agreements with fixed
volumes with a multiyear duration.
Sigma plans to develop Phase 2 following a
similar integrated strategy of delivering green lithium chemicals
to customers, through tolling partnerships for chemical lithium
products. Discussions are underway with a number of interested
parties, whereby (similarly to Phase 1 production) Phase 2 Battery
Grade Green Lithium Concentrate will be treated at an offsite
downstream conversion facility to produce lithium carbonate or
lithium hydroxide for its life of mine.
1.5 - Project Schedule
The Company has significantly advanced multiple
Project workstreams in geology, geotechnical, metallurgical,
environmental and regulatory permitting with the objective of
preparing for Phase 2 production after 2023. Sigma is advancing
Phase 2 with the goal of being construction ready by the end of
2021. Phase 2 construction is planned to initiate sequentially to
the commissioning and production ramp up of Phase 1 (which is
expected in summer of 2022).
The Company has been working with SGS and
Primero to prepare a PFS for Phase 2 production, further continuing
towards feasibility. The Company and Primero completed all the
metallurgical and variability feasibility test work at SGS
laboratories with the aim of customizing a flowsheet for the second
processing line of Phase 2 production with Barreiro. The Company
completed all the field work for the PFS, including geotechnical
drilling.
The execution plan for Phase 2 of the Project in
2021 focuses on:
- Continuing the engineering activities to complete a PFS and
finalize designs, equipment and plant configurations, which is
expected to reduce risks and enhance yield;
- Progression of the environmental and regulatory approvals;
- Continued discussions with potential downstream and offtake
partners to achieve a fully integrated operation with the battery
industry for electric vehicles; and
- Optimizing the capital structure for the Company and obtain
debt and equity financing for the capital expenditures for Phase
2.
2 – MINING
GE-21, prepared the mining section of PEA aiming
to assess the economic viability of the Phase 2 of the Project. The
Barreiro deposit is located in close proximity to the surface with
shallow, near surface mineralization ideal for open pit mining.
Therefore, the Barreiro deposit will be mined by conventional open
pit methods. Mining will require drilling and blasting and mining
material will be removed using hydraulic excavators and haul
trucks.
Figure 2.1: Plant 3D layout of the
industrial complex and production facility for Phase 1 and Phase
2
https://www.globenewswire.com/NewsRoom/AttachmentNg/a45b8979-f693-4fc1-a46e-845999d275c6
The mining operating costs in Table 2.1.1 were
based on the proposal of U&M Mineração e Construção SA,
presented on July 3rd, 2020, for the Phase 1 contract mining of the
Xuxa open pit mine. The scope of services refers to the provision
of ore and waste handling services involving the drilling &
blasting, excavation, loading and haulage of soil and rock,
conservation and dust control, and other ancillary activities. Only
the cost of ore haulage from the stockyard to the plant was not
part of the scope of the U&M proposal, so it was estimated
based on GE21’s inhouse database.
Table 2.1: Key Mining Assumptions
Utilized in the Project Economics
Item |
Unit |
Total |
Ore Processed |
|
|
Total quantity milled (LOM) |
Mt |
21.3 |
Average Annual run of mine (ROM) milled |
Mt |
1.68 |
Strip ratio |
|
|
Year 1 |
Ratio: |
5.2 : 1 |
Year 5 |
Ratio: |
10.8 : 1 |
Year 6 |
Ratio: |
15.,5 : 1 |
Run of Mine Costs |
|
|
Mining costs per waste and ore mined |
[US$/t mined] |
2.3 |
Processing costs per tonne (ROM) |
[US$/t ROM] |
8.6 |
Pit Optimization
The determination of the optimal pit was based
on:
- A calculation of the interlocking (nested) of optimal pits
using Micromine software;
- Certain technical and economic parameters were used for the
generation of the optimal mathematical pit, which consists of the
pit that maximizes the value of the enterprise and was obtained
through the application of the Lerchs-Grossman algorithm.
- The economic and geometric parameters were defined based first
principles, using GE21's database in accordance with projects of
similar scale and characteristics. The geotechnical assessment was
based on rock quality and visual inspection on undeformed core
samples.
- The selection of the minimum optimal pit with enough
mineralized material to supply a production of 1.680 Mtpa during
LOM.
- All mineralized material was considered in the optimization
process, including that classified as inferred.
The sequence of optimal pits was obtained by
varying the revenue factor from 10% to 200% with respect to the
product's selling price. To determine the evolution of the pits
over time, an annual production scale of 1.680 Mtpa of ROM was
established.
The waste was divided into: Overburden; Fresh
rock; Low grade – Material with a grade below 0.5% LiO2; Percent –
Blocks initially assigned as ROM, but with a block factor smaller
than 1 (part of the blocks that were not inside the mineralized
body); Outside the Model – blocks generated outside the block model
box, to cover the entire length of the pit.
Pit
Design
The open pit mine design, consists of
projecting, based on a selected optimal pit, an operational pit
that allows for the safe and efficient development of mining
operations.
The preliminary pit design extends approximately
0.92 km NW/SE along strike of the pegmatite mineralization and has
an average width of 1.0km. The design is divided into depths of
100m (RL=200m), 220m (RL =100m) and 300m (RL=10m). Mining is
scheduled to achieve low waste stripping in the initial years with
a gradual increase later in the mine life, as per the
table below. The average strip ratio for the LOM plan is 11.6,
as follows:
- Year 2: Ratio – 5.2 : 1
- Year 5: Ratio – 8.8 : 1
- Year 6: Ratio – 10.4 : 1
Thus, the operationalized pit contains 20.485Mt
of measured & indicated mineral resources and 1.909Mt of
inferred mineral resources) and 246.7 Mt of waste rock, leading to
an overall stripping ratio of 11.6, and which results in a mine
life of approximately 13 years. The table 2.2 below shows the
result for the final operational pit that resulted from the mine
design activities.
The use of a mixed fleet is planned, with road
trucks for haulage the run of mine (“ROM”) and
off-road trucks for haulage of waste rock. Thus, the width of the
access road to the final pit was maintained at 24 m (off-road
truck), apart from the lower pit benches, which are basically
composed of ROM. In this region, a width of 10 m was used for the
access road. Site preparation including logging, clearing, grubbing
and peat/topsoil removal will occur during the project construction
phase. Surface mining equipment requirements are based on mining
10m benches.
The economic analysis was based on potentially
recoverable resources, utilizing a contract mining fleet of
hydraulic excavators, front-end loaders and 100t haul trucks for
waste and 40t haul trucks for the ROM, associated with
correspondent ancillary equipment. Fleet was sized to meet the
planned tonnage requirements to feed the crushing plant at 1.68
Mtpa. Waste rock will be hauled to multiple waste rock and tailings
storage facilities and ROM feed material will be hauled to the ROM
pad.
Haul trucks will be used to transport tailings
from the plant to the proposed waste rock and dry stacked tailings
stockpile areas.
Additional mining engineering undertaken during
the ongoing PFS 2021 should increase the level of confidence in the
current mine plan and will be reported in updated disclosures.
GE-21 is leading the preparation of the mine plan, geotechnical
program and modelling of the Barreiro deposit.
- The drilling of three new geotechnical orientated core holes
and relogging (geotechnically) of 20 selected exploration holes
were completed. The Company engaged Comprobe, a specialist
engineering service company, to conduct downhole geotechnical
surveys using an acoustic televiewer to probe exploration drill
holes. These surveys were completed for the new and historic
exploration holes.
- The field work required for the hydrogeological section of the
PFS has been completed, as well as all water level
measurements.
Table 2.2 - Results - Final
Operational Pit for Barreiro Deposit
Pit |
Tonnes (MT) |
Li2O (%) |
Years |
ROM |
Overburden |
Fresh Rock |
Low Grade |
Percent |
Outside the Model |
Total Waste |
Stripping Ratio |
In Situ |
Diluted |
LOM |
Mathematical |
21.5 |
2.3 |
204.3 |
0.8 |
5.3 |
10.0 |
222.8 |
10.35 |
1.435 |
1.393 |
12.81 |
Operational |
21.3 |
2.2 |
221.9 |
0.9 |
5.2 |
16.4 |
246.7 |
11.56 |
1.438 |
1.396 |
12.70 |
Figure 2.2 - Final Operational Pit
(Ultimate Pit Design).
https://www.globenewswire.com/NewsRoom/AttachmentNg/909960c0-6cfd-478c-856c-6a042e4c06d2
3 – PROCESSING
Plant Flowsheet Design
Detailed engineering and flowsheet design for
the entire Production Plant currently in pre-construction was
performed by Primero, an Australian-based engineering company with
global development experience. The process design (flowsheet) is
based on an annual throughput of 1.5Mt from the crushing plant of
mineralized material (already contemplating a loss of 15% occurred
during the crushing) to produce a final product grade of up to 6.0%
Li2O. The selected process is similar to that utilized at the
Production Plant in pre-construction which incorporates a similar
flowsheet based on crushing and DMS.
Table 3.1 – Processing Costs and
Throughput
Item |
Unit |
Total |
Spodumene Processed |
|
|
Average Annual run of mine (ROM) milled |
Mt |
1.68 |
|
Spodumene ore feed grade LOM average |
% |
1.44 |
|
Loss on Crushing |
% |
15 |
|
High Purity Lithium Concentrate Produced |
LOM Average |
|
Average Lithium Concentrate Produced |
t |
222,147 |
|
Lithium Recovery Rate |
% |
66 |
% |
Lithium Concentrate Grade |
% |
6.0 |
% |
Lithium Carbonate Equivalent Produced |
tonnes LCE |
33,000 |
|
Processing Costs |
|
|
Processing costs per tonne |
US$/t processed |
8.6 |
|
Processing involves a conventional three-stage crushing circuit,
followed by a DMS plant. Similar to the Project’s Xuxa Mine (the
“Project’s First Mine” or “Xuxa
Mine”), the crystal sizes are coarse and therefore
grinding and flotation methods are not necessary, contributing to
low operating costs. Other sub processes include:
- dewatering, filtration and dry stack tailings disposal system
(with waste rock disposal);
- water, air and ancillary services; and
- spodumene concentrate stockpile and dispatch system.
The mineralized material will be fed from the
ROM pad to a three-stage crushing plant consisting of a primary jaw
crusher, a secondary crusher and tertiary crusher. Prior to
entering the DMS cyclones, the material will be mixed with a
ferrosilicon slurry, which acts as a densifying medium to enhance
the gravity separation of the spodumene. The processing plant is
fully automated and the stability of the dense media in the cyclone
is digitally controlled by a proprietary algorithm developed by
Primero.
Figure 3.1- Plant 3D layout of the
industrial complex and production facility for Phase 1 and Phase
2
https://www.globenewswire.com/NewsRoom/AttachmentNg/e1ee09db-bfb2-4c0e-a64f-e089d2e1e00f
Final product grade - Metallurgical HLS Test
A metallurgical test program was carried out by
SGS Lakefield of Ontario, Canada to determine optimal plant
operating recoveries. The metallurgical tests included a heavy
liquid separation (“HLS”) test to evaluate the
extent to which a gravity-based separation process, or
DMS, could successfully recover the lithium from
the spodumene ore. HLS is a perfect separation based on the
minerals’ specific gravity (“SG”) and confirms
that DMS technology can be used.
HLS test work performed on ore sizes of 6.3mm
and 10mm achieved excellent lithium recoveries of 70.2% and 66.1%,
respectively, producing a 6% Li2O battery-grade spodumene
concentrate within the highest levels of specifications demanded by
the chemical lithium market without the
use of flotation or hazardous chemical reagents, in the
concentration process. This is consistent with Sigma’s intention to
continue to process its lithium ore in a “green”
environmentally friendly and sustainable manner.
The DMS performance and separation efficiency is
done in a pilot plant to simulate a real industrial environment.
The DMS test work was conducted on the same sample and achieved
similar recoveries (applied to the sensitivity analysis).
The results indicate that the material from
Barreiro, the Project’s second deposit, can be processed, purified
and concentrated in the same flowsheet ore from the Project’s First
Mine in the same Production Plant, as designed in the Feasibility
Study Report without requiring major flowsheet modifications, and
thus, with low additional capex needs. The results of the
metallurgical tests validated high recovery levels obtained for
lithium utilizing a dense media separation processing circuit with
similar flowsheet to the one designed for the Phase 1 Production
Plant.
The metallurgical testing was completed from a
sample of 1250kg of spodumene ore composited using drill cores
representative of the early, middle and late years of the Barreiro
deposit
Table 3.2 - Metallurgical Recovery
Assumptions from HLS Test Results for Combined Products
(10.0mm)
Size of 10.0mm or less |
Weight (%) |
Assay (%) |
Distribution (%) |
Li2O |
Fe2O3 |
K2O |
Na2O |
Li |
Fe2O3 |
Combined concentrate (2.81 SG) |
15.9 |
6.00 |
0.55 |
0.60 |
0.57 |
66.1 |
38.9 |
Combined tailings (-2.65 SG) |
67.6 |
0.43 |
0.07 |
3.28 |
4.78 |
20.1 |
21.9 |
Head grade (plant feed grade) |
100.0 |
1.44 |
0.22 |
2.78 |
3.78 |
- |
- |
4 - MINERAL RESOURCES ESTIMATE (“MRE”)
PHASE 2 BARREIRO
The basis for the PEA is the MRE completed by
SGS Geological Services and included in the 2019 Feasibility Study
Report, which remains unchanged from January 10, 2019. The resource
model derived by SGS was used in the development of the PEA. The
table below outlines the total Measured, Indicated and Inferred
Mineral Resources for the Barreiro deposit.
Table 4.1: Mineral Resource Estimate for
Barreiro
Cut-off
Grade(Li2O%) |
Category |
Tonnage |
AverageLi2O% |
0.5 |
Measured |
10,313,000 |
1.4 |
0.5 |
Indicated |
10,172,000 |
1.46 |
0.5 |
Measured+Indicated |
20,485,000 |
1.43 |
0.5 |
Inferred |
1,909,000 |
1.44 |
- The mineral resource estimate was
conducted using the 2014 CIM Definitions Standards for mineral
resources in accordance with National Instrument 43-101, Standards
of Disclosure for Mineral Projects. Mineral resources, which are
not mineral reserves, do not have demonstrated economic viability.
Inferred mineral resources are exclusive of the Measured and
Indicated resources.
- A fixed density of 2.71 t/m3 was
used to estimate the tonnage from block model volumes.
- Resources are constrained by the
the topography
- Geological CoG estimated from Li2O
values of the composite vs value in block
5 - ENVIRONMENTAL AND SOCIAL
IMPACTS
5.1 – Environmental
The Company has ongoing comprehensive
environmental and social programs in process, consistent with its
leadership role in ESG in the lithium mining sector and its
commitment to sustainable mining. The mitigating social and
environmental programs already initiated or to commence during
construction phase aim to establish actions to proactively
mitigate, prevent, control and compensate for the environmental
impacts that could be caused by the mining activity to be carried
out by the Company once it enters the production phase.
Starting in the dry season of the second quarter
of 2020, the Company has been conducted detailed environmental
impact studies for the fauna and the flora in the area of the
Barreiro deposit where the pit and waste piles will be located.
These studies continued in the wet season during the third and
fourth quarters of 2020. The environmental impact studies were
completed and a comprehensive environmental and social impact
assessment report (EIA/RIMA) was prepared and concluded by the
Company. The design proposed by the Company in the EIA/RIMA for the
ADA (Directly Impacted Area by the Project) has followed the
Company’s ESG-centric approach to minimize vegetation suppression
and contemplated the location of its processing tailings dry
stacking piles in the vicinity of the Production Plant with the
selection of areas for waste piles targeting the overall
minimization of vegetation and tree suppression which, in
combination with the vegetation suppression required for the pit
areas, amounts to less than 50 hectares. As a result, the life
cycle analysis of the Company is substantially enhanced, decreasing
its mining carbon footprint.
Once the EIA/RIMA is submitted and approved by
regulators, additional ancillary construction and operation permits
from environmental authorities will be required prior to
construction.
5.2 - Social
The Project is located in one of the poorest
regions of Brazil, the Vale do Jequitinhonha, and within two
municipalities: Itinga and Araçuaí. These towns are located 17km
from the Project site and are the nearest major communities to the
site.
The Company, as part of its ESG-centric strategy
of shared gains and value creation with the communities around the
Project, has determined as a core social objective the principles
and guidelines of UN-SDG #8 of “decent work and economic growth”.
The Company is committed to achieve this by strengthening the
regional socioeconomic environment within the two municipalities
where it operates in the Vale do Jequitinhonha. Sigma has a strong
working relationship with both municipalities and its communities
and conducts regular and meaningful engagement and consultation
with them
Also following the principles and guidelines of
UN-SDG #17 “partnership for the goals”, the Company initiated a
project to lead the creation, structuring and operation of an
independent agency for private investment promotion and economic
diversification of the region (“Investment
Agency”). This workstream was divided in two stages.
- Stage 1, which is expected to be completed by the third quarter
of 2021 is to provide the framework for the Investment Agency,
including: (i) mapping and approaching stakeholders, (ii)
evaluation of the region's “maturity” and “economic engagement”
indices, (iii) definition of the Agency Model for the region, (iv)
consolidation of governance and management models, (v) modulation
of the economic sustainability plan, (v) modulation of “priority
sectors” to attract investments.
- Stage 2 is expected to be implemented over a twelve month
period, and include the following activities: (i) structuring legal
constitution, building councils, and identifying independent
executive leadership, (iii) elaboration of the territory value
proposition to attract investments (competitive differentials),
(iv) validation of “priority sectors” to attract investments, and
(v) execution of the first “territory promotion and facilitation
activities”, and (vi) identification of additional regional
sponsorship.
On April 29, 2021, in line with the principles
and guidelines of UN-SDGs #17 partnership for the goals #1 no
poverty and #2 zero hunger, the Company launched an initiative to
provide humanitarian relief during the next 10 months of pandemic
for the local population living in poverty “Sigma contra a fome”
(Sigma against hunger). The initiative will distribute 600 basic
food baskets per month to 600 families (with an average of four
people), feeding approximately 2,400 people per month. Moreover,
the company revived and expanded the COVID-19 prevention initiative
from March 2020, and it is distributing 12,000 units of hospital
disinfectant, totaling 12 tons, as well as 2,400 hand sanitizers
“family size”, totaling 840 kg of the product.
5.3 – Permitting
The Company obtained a key permit for Phase 2
production with the Agência Nacional de Mineração (the
“ANM”) approving its economic feasibility study
(“Plano Econômico de Avaliação” - PAE). This
approval advanced the Phase 2 production permitting process to the
mining concession request stage (“Requerimento de Concessão
de Lavra”)
The PEA is preliminary in nature and
includes inferred mineral resources that are considered too
speculative geologically to have economic considerations applied to
them that that would enable them to be categorized as mineral
reserves. There is no certainty that the PEA results will be
realized. Mineral resources that are not mineral reserves do not
have demonstrated economic viability.
ABOUT SIGMA LITHIUM
The Company is developing, with an environmental
sustainability focused and ESG-centric strategy, the largest hard
rock lithium deposits in the Americas, located in its wholly owned
Grota do Cirilo Project in Brazil with the goal of participating in
the rapidly expanding global supply chain of electric vehicles.
Based on the 2019 Feasibility Study Report, the
Company plans to produce 220,000/t annually of battery grade
lithium concentrate (33,000 t of lithium carbonate equivalent in
Phase 1 production and expects to be amongst the world’s lowest
cost producers. In Phase 2 production, if warranted after ongoing
feasibility study, production would be increased to 440,000 t
(66,000 tonnes of LCE) annually. The first phase of production for
the Project will utilize as feedstock spodumene from the Project’s
Xuxa deposit. The next production phase of the Project would be
increased production including feedstock from the Project’s
Barreiro deposit.
Since 2018, the Company has been producing low
carbon high purity lithium concentrate at an on-site demonstration
pilot plant with the objective to ship samples to potential
customers for product certification and testing. This pilot
production has been an important part of the successful commercial
strategy of the Company allowing it to ship samples of its low
carbon “green & sustainable” high purity lithium to leading
global potential customers, for product certification and
testing.
The Company is in pre-construction and detailed
engineering of an environmentally friendly, fully automated, dense
media separator production plant that applies proprietary
algorithms to digitally control the dense media (the
“Production Plant”). The Production Plant will be
vertically integrated into the Company ́s mining operations,
exclusively utilizing as feedstock the high purity spodumene ore
with exceptional mineralogy from the Project. The Production Plant
will process the spodumene ore into a high purity 6% battery-grade
lithium concentrate engineered to the specifications of its
customers in the lithium- ion battery supply chain for EVs.
In order to secure a leading position supplying
the clean mobility and green energy storage value chains, the
Company has adhered consistently to the highest standards of
environmental, social and governance practices, which were
established as part of its core purpose at inception in 2012. Its
production process will be powered by clean energy and the Company
will use state-of-the art water recirculation circuits in its
processing combined with dry stacking tailings management. The DMS
process of the Production Plant does not utilize hazardous
chemicals, as a result its tailings are 100% recyclable into
ancillary industries, such as ceramics.
The Company plans to achieve net zero carbon
emission targets by 2023, partly as a result of its strategic
decision to pursue generation of carbon credits through
“in-setting” carbon credits (preserving and developing the
agroforestry systems within its regional ecosystem). The Company is
currently undergoing an independent assessment of its net carbon
footprint, conducting an independent ISO 14000 compliant audit of
its life cycle analysis together with an independent expert
validation of its carbon credits generated by its internal
preservation, reforestation, and compensation forestry programs.
The Company expects to complete this workstream in the second half
of 2021.
Sigma has significant potential for additional
future expansion and growth, as it owns 27 mineral rights spread
over 191 km2 (which include mining concessions, applications for
mining concessions, exploration authorizations and applications for
mineral exploration authorizations). The Grota do Cirilo Project
area includes nine past producing lithium mines.
QUALIFIED PERSONS
The technical and scientific information related
to geology and mineral resource estimate in this news release has
been reviewed and approved by Marc-Antoine Laporte P.Geo., M.Sc.,
of SGS Geological Services. Mr. Laporte is a Qualified Person as
defined by National Instrument 43-101 and is independent of
Sigma.
The mining and financial information in this
news release has been reviewed and approved by Porfirio Cabaleiro
Rodriguez P.Eng, Mining Engineer of GE21 Consultoria Mineral
Brazil. Mr Rodriguez is a Qualified Person as defined by National
Instrument 43-101 and is independent of Sigma.
FOR ADDITIONAL INFORMATION PLEASE CONTACTAna
Cabral-Gardner(Sao Paulo) +55 11 2985-0089
ana.cabral@sigmaca.com
FORWARD-LOOKING STATEMENTS
This news release includes certain
"forward-looking statements" under applicable Canadian securities
legislation including statements relating to the ultimate duration,
impact and severity of the COVID-19 pandemic (including its impact
on financial markets and national and multinational economies
generally, and its impact on the growth of the electric vehicle
market and other impacts on the demand for lithium products) and
other forward-looking statements. Forward-looking statements are
necessarily based upon a number of estimates and assumptions that,
while considered reasonable, are subject to known and unknown
risks, uncertainties, and other factors which may cause the actual
results and future events to differ materially from those expressed
or implied by such forward-looking statements. All statements that
address future plans, activities, events, or developments that the
Company believes, expects or anticipates will or may occur are
forward-looking information, including statements regarding the
potential development of resources and drilling plans which may or
may not occur. Forward-looking statements and information contained
herein are based on certain factors and assumptions regarding,
among other things, the ability to complete the Annual Filings and
Interim Filings; the market price of the Company's securities,
metal prices, exchange rates, taxation, the estimation, timing and
amount of future exploration and development, capital and operating
costs, the availability of financing, the receipt of regulatory
approvals, environmental risks, title disputes, litigation risks,
failure of plant, equipment or processes to operate as anticipated,
accidents, labour disputes, claims and limitations on insurance
coverage and other risks of the mining industry, changes in
national and local government regulation of mining operations, and
regulations and other matters including the COVID-19 pandemic.
There can be no assurance that such statements will prove to be
accurate, as actual results and future events could differ
materially from those anticipated in such statements. Accordingly,
readers should not place undue reliance on forward-looking
statements. The Company disclaims any intention or obligation to
update or revise any forward-looking statements, whether as a
result of new information, future events or otherwise, except as
required by law. For more information on the risks, uncertainties
and assumptions that could cause our actual results to differ from
current expectations, please refer to our public filings available
at www.sedar.com.
Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in the
policies of the TSX Venture Exchange) accepts responsibility for
the adequacy or accuracy of this news release.
Sigma Lithium (TSXV:SGMA)
過去 株価チャート
から 11 2024 まで 12 2024
Sigma Lithium (TSXV:SGMA)
過去 株価チャート
から 12 2023 まで 12 2024