9 October 2024
Central Asia Metals
plc
(the 'Group', the
'Company' or 'CAML')
Q3 2024 Operations
Update
Central Asia Metals plc (AIM: CAML) provides
its Q3 2024 operations update for the Kounrad dump leach, solvent
extraction and electro-winning ('SX-EW') copper recovery plant in
Kazakhstan ('Kounrad') and the Sasa zinc-lead mine in North
Macedonia ('Sasa').
Q3 2024 operational
summary
-
Zero lost time injuries ('LTIs') at Kounrad
-
Zero LTIs at Sasa
-
Kounrad copper production of 3,641 tonnes
-
Sasa zinc-in-concentrate production of 4,768
tonnes
-
Sasa lead-in-concentrate production of 6,864
tonnes
Outlook
-
Kounrad on track to achieve 2024 full-year guidance for
copper production (13,000 to 14,000 tonnes)
-
Sasa expected to achieve production towards the lower end of
2024 guidance:
o
zinc-in-concentrate: 19,000 to 21,000 tonnes
o
lead-in-concentrate: 27,000 to 29,000 tonnes
CAML production summary
Metal
production (tonnes)
|
Q3
2024
|
Q3
2023
|
9m
2024
|
9m
2023
|
Copper
|
3,641
|
3,661
|
10,248
|
10,377
|
Zinc
|
4,768
|
5,127
|
13,782
|
14,891
|
Lead
|
6,864
|
7,039
|
19,736
|
20,773
|
Gavin Ferrar, Chief Executive
Officer, commented:
"Kounrad continued to perform well
in Q3 2024, in line with its production performance in the
corresponding period of last year, and maintained its excellent
safety record. Q3 is seasonally Kounrad's strongest quarter, and
the operation remains on track to achieve full-year production
firmly within the guidance range given at the start of this
year.
"Sasa also performed well in Q3
2024, with the tonnage processed recovering from the levels of H1
2024 towards the level recorded in Q3 last year. This represents a
great achievement by the Sasa team, given the challenges posed by
the transition to the new mining system designed to ensure the
operation's long-term future. Head grades, in particular zinc, also
recovered relative to H1 2024. We look forward to maintaining this
progress in Q4, which we expect to result in full-year production
towards the lower end of the guidance range.
"Meanwhile, the Capital
Projects programme at Sasa is nearing completion, which includes
moving to the use of paste backfill in mining and adopting
dry-stack tailings. Together, these technologies form the core of
Sasa's long-term strategy; maximising resource extraction, and
extending the life of TSF 4 and thus avoiding the need for a new
conventional tailings storage facility. Together, these
developments ensure Sasa's planned life to at least
2039."
Health and Safety
Kounrad had no LTIs during Q3 2024,
and at 30 September 2024 had achieved 2,328 consecutive days LTI
free.
Sasa also had no LTIs during Q3
2024, and just one LTI for the nine months to 30 September 2024. At
30 September, Sasa had achieved 94 consecutive days LTI
free.
Kounrad
Production
and sales update
Kounrad Q3 2024 copper production of 3,641
tonnes brings output for the first nine months of 2024 to 10,248
tonnes. Copper sales during Q3 2024 were 3,731
tonnes.
By the end of Q3, winter covering
preparations had been completed at the Western Dumps, and at the
Eastern Dumps completion is expected by mid-October. Trench
extension work was under way during the quarter at the northwestern
edge of the Western Dumps, with 140 metres of the planned 660
metres completed.
Sasa
Production
and sales update
In Q3 2024, 195,659 tonnes of ore were mined
and 193,475 tonnes processed, bringing the total for the nine
months to 30 September 2024 to 561,311 tonnes mined and 561,550
tonnes processed. The average head grades for Q3 were 2.92% zinc
and 3.75% lead, and for the first nine months of 2024 averaged
2.88% and 3.72% respectively. The average Q3 2024 metallurgical
recoveries were 84.4% for zinc and 94.6% for lead.
Sasa produces a zinc concentrate and a separate
lead concentrate. In Q3 2024, 9,550 tonnes of concentrate
containing 49.9% zinc, and 9,647 tonnes of concentrate containing
71.2% lead were produced. This brings total production for the
first nine months of 2024 to 27,463 tonnes of zinc concentrate at a
grade of 50.2% and 27,834 tonnes of lead concentrate at a grade of
70.9%.
Sasa typically receives from smelters
approximately 84% of the value of its zinc-in-concentrate and
approximately 95% of the value of its lead-in-concentrate.
Accordingly, Q3 2024 payable production was 4,004 tonnes of zinc
and 6,521 tonnes of lead, bringing total payable production for the
first nine months of 2024 to 11,585 tonnes of zinc and 18,749
tonnes of lead.
Payable base-metal-in-concentrate sales for Q3
2024 were 4,031 tonnes of zinc and 6,636 tonnes of lead,
essentially in line with production.
During Q3 2024, Sasa sold 105,627 ounces of
payable silver to Osisko Gold Royalties, in accordance with its
streaming agreement.
|
Units
|
Q3
2024
|
Q3
2023
|
9m
2024
|
9m
2023
|
Ore
mined
|
t
|
195,659
|
199,085
|
561,311
|
595,319
|
Plant
feed
|
t
|
193,475
|
199,427
|
561,550
|
596,099
|
Zinc
grade
|
%
|
2.92
|
3.04
|
2.88
|
2.94
|
Zinc
recovery
|
%
|
84.4
|
84.6
|
85.1
|
84.8
|
Lead
grade
|
%
|
3.75
|
3.79
|
3.72
|
3.74
|
Lead
recovery
|
%
|
94.6
|
93.1
|
94.5
|
93.1
|
Zinc
concentrate
|
t (dry)
|
9,550
|
10,249
|
27,463
|
29,506
|
- Grade
|
%
|
49.9
|
50.0
|
50.2
|
50.5
|
- Contained
zinc
|
t
|
4,768
|
5,127
|
13,782
|
14,891
|
Lead
concentrate
|
t (dry)
|
9,647
|
9,919
|
27,834
|
29,221
|
- Grade
|
%
|
71.2
|
71.0
|
70.9
|
71.1
|
- Contained
lead
|
t
|
6,864
|
7,039
|
19,736
|
20,773
|
Capital
Projects - the transition to paste-fill mining and dry-stack
tailings
During Q3 2024, the Paste Backfill
Plant ('PBF') continued to operate consistently, with approximately
76,000 tonnes of paste placed in the voids between the 990 and 910
metre levels and in the cut-and-fill production stopes on the
800-metre level. The first long-hole stopes are in production, and
additional stopes will follow during the remainder of 2024 and
thereafter.
As in H1 2024, some previously mined
voids proved of greater volume than anticipated, increasing the
volume of tailings that can be stored underground. This
void-filling also provides the necessary ground stability for
current and future mining. Since the commissioning of the PBF
Plant, over 207,000 tonnes of paste have been placed underground,
representing around 50% of the total tailings generated during this
period.
Construction of the Dry Stack
Tailings ('DST') Plant remains on track, with dry commissioning
started in September. Meanwhile, the first phase of the engineered
landform has been completed, ready for the placing of geosynthetic
materials prior to full commissioning of the DST Plant. Initial
placement of filter cake remains on schedule for Q4
2024.
In the third element of Sasa's
Capital Projects, around 3,500 metres of the Central Decline have
been developed. Completion and connection with the 750-metre level
remains on track for Q4 2024.
For further
information contact:
Central Asia Metals
|
Tel: +44 (0) 20 7898 9001
|
Gavin Ferrar
|
|
CEO
|
|
Louise Wrathall
|
|
CFO
|
|
Richard Morgan
|
richard.morgan@centralasiametals.com
|
Investor
Relations Manager
|
|
|
|
Peel Hunt (Nominated Adviser and Joint
Broker)
|
Tel: +44 (0) 20 7418 8900
|
Ross Allister
|
|
David McKeown
Emily Bhasin
|
|
|
|
BMO
Capital Markets (Joint Broker)
|
Tel: +44 (0) 20 7236 1010
|
Thomas Rider
|
|
Pascal Lussier Duquette
|
|
|
|
BlytheRay (PR
Advisers)
|
Tel: +44 (0) 20 7138 3204
|
Tim Blythe
|
|
Megan Ray
|
|
|
|
Note to
editors:
Central Asia Metals, an AIM-quoted UK company
based in London, owns 100% of the Kounrad SX-EW copper project in
central Kazakhstan and 100% of the Sasa zinc-lead mine in North
Macedonia. The Company also owns an 80% interest in CAML
Exploration, a subsidiary formed to progress early-stage
exploration opportunities in Kazakhstan, and a 28.7% interest in
Aberdeen Minerals Ltd, a privately-owned UK company focused on the
exploration and development of base metals opportunities in
northeast Scotland.
For further information, please visit
www.centralasiametals.com and follow CAML on X at @CamlMetals and
on LinkedIn at Central Asia Metals Plc