Torex Gold Resources Inc. (the “Company” or “Torex”) (TSX: TXG)
provides the second quarterly update on the development of its
Media Luna Project (“Media Luna”). Unless otherwise stated,
progress and milestones referenced in this press release are as of
March 31, 2023.
Jody Kuzenko, President & CEO of Torex,
stated:
“With a full year of execution now behind us and
21 months remaining, the Media Luna Project continues to track to
overall schedule and budget. At quarter-end, the project was 24%
complete across engineering, procurement, underground development,
and surface construction. With no major changes to the project
execution plan, first concentrate production remains on track for
late 2024, with commercial production still anticipated in early
2025. At quarter end, 34% of upfront project expenditures had been
committed, including 22% incurred. The level of spending on the
project is expected to increase throughout the remainder of the
year, with total project expenditures of $390 million to $440
million guided in 2023.
“Detailed engineering and procurement activities
increased significantly during the quarter, with several key
purchase orders awarded, the most significant being the order for
the primary mine production fleet. The fleet consists of 35 pieces
of equipment including 15 battery electric and 20 diesel powered
machines. First deliveries under the purchase order are expected
later this year, in line with the project schedule. Post quarter
end, the contract for the mobile production support equipment was
signed. Contracts for the personnel transportation vehicles,
underground construction, and underground vertical development are
expected to be finalized shortly.
“Surface and underground development continue on
pace. The schedule critical Guajes Tunnel has exceeded the
4-kilometre mark, with 18 active headings opened up within the
deposit, and civil works for future infrastructure on both sides of
the Balsas River in various stages of progress. With strong
available liquidity and robust forecast cash flow from El Limón
Guajes through the end of 2024, we are well-positioned to not only
fund the development of Media Luna, but to continue to advance
additional value-enhancing initiatives with a view to continuing to
extend mine life and optimize economics at our flagship Morelos
Property.”
CAPITAL EXPENDITURES
Total upfront expenditures related to the
development of Media Luna are tracking to the initial estimate of
$874.5 million. As at quarter-end, Torex had incurred $191.1
million of project period expenditures (22% to date) and $298.9
million of expenditures committed and incurred (34% to date).
Table 1: Media Luna Project – Project
Expenditures (April 1, 2022 through March 31, 2023)
Millions of U.S. dollars |
Project To DateQ1 2023 |
Project expenditures per 2022 Technical Report |
$ |
848.4 |
|
Adjustment for underspend in Q1 2022 |
$ |
26.1 |
|
Total project expenditures |
$ |
874.5 |
|
Total project expenditures incurred to date |
($ |
191.1 |
) |
Remaining project expenditures |
$ |
683.4 |
|
Committed expenditures (inclusive of total project expenditures
incurred to date) |
$ |
298.9 |
|
Uncommitted expenditures |
$ |
575.6 |
|
1) Project period commenced on
April 1, 2022; excludes capital expenditures incurred prior to
Board approval on March 31, 2022.2) Project period
is defined as April 1, 2022 through December 31,
2024.3) Excludes borrowing costs capitalized.The
Company expects to incur $390 to $440 million of capital
expenditures related to the development of the Media Luna Project
in 2023 ($66.4 million accrued during the first quarter), which is
forecasted to be the peak year of investment. Quarterly
expenditures are expected to increase into H2 2023, and remain
relatively consistent through H1 2024, before declining as
development activities wind down ahead of commercial production,
which is anticipated in early 2025.
More detail on the Media Luna Project, including
the feasibility study results, can be found in the Company’s most
recent Technical Report dated effective March 16, 2022, filed on
March 31, 2022 (“Technical Report”).
PROJECT COMPLETION
As at quarter-end, development of Media Luna was
tracking to overall schedule, with the project 24% complete, up
from the 15% complete status at the end of 2022. Detailed
engineering is nearing the 50% completion mark, while procurement
is almost 40% complete, with a majority of the schedule critical
purchase orders either awarded, or soon to be awarded. Based on the
current schedule, first concentrate production remains on track for
late 2024.
Table 2: Media Luna Project – Project Completion
(April 1, 2022 through March 31, 2023)
|
Project To DateQ1 2023 |
Procurement |
36 |
% |
Engineering |
47 |
% |
Underground development/construction |
23 |
% |
Surface construction |
15 |
% |
Total Project |
24 |
% |
Notes to Table1) Physical progress measured
starting as of April 1, 2022; excludes progress made prior to Board
approval on March 31, 2022.2) Project period is defined as
April 1, 2022 through December 31, 2024.
3) Total Project is weighted average based
on activity levels.ProcurementDuring the quarter, the Company
executed several key purchase orders, including those for the
filter presses and positive displacement pump for the paste plant,
filter presses for the copper concentrate circuit, the gravity
concentrator, the reverse osmosis unit for the water treatment
plant, and fixed equipment for the underground operation
(conveyors, belt magnets, and vibratory feeders).
The major procurement achievement in the quarter
was awarding the purchase order for the primary production fleet to
Sandvik, an order worth approximately $63 million with deliveries
scheduled to begin in Q3 2023. The order includes 35 vehicles in
total, including 15 battery electric vehicles which, according to
Sandvik, is the company’s third-largest battery electric vehicle
fleet order to date.
The process for technical and commercial
evaluation of bids for the underground construction vertical
development contracts is nearing completion, with contract awards
anticipated shortly. Mobilization of the successful underground
construction contractor is anticipated during Q2 2023.
EngineeringThe pace of detailed engineering
increased during the first quarter and continues to track well with
procurement activities. Key engineering packages that advanced
during the quarter included equipment specifications for soliciting
pricing from vendors, finalization of deliverables ahead of surface
construction activities, final orientation of ore and waste
handling infrastructure, and initial simulations with charging of
batteries for the electric vehicle fleet.
Underground Development and ConstructionSteady
progress was made in advancing the Guajes Tunnel and South Portal
Lower. Breakthrough of the Guajes Tunnel on the south side of the
Balsas River remains on track for Q1 2024, if not earlier. The
thousand plus conveyor tables to be installed in the tunnel have
now been ordered from a Mexican supplier and delivery is expected
to commence mid-year.
As at the end of April, the Guajes Tunnel had
advanced 4,080 metres, with daily advance rates
averaging 7.0 metres over the last three months, including a record
average daily rate of 7.4 metres in February. At South Portal
Lower, development rates have increased throughout 2023 with a
3-month average daily advance rate of 4.3 metres through April
(including 5.1 metres per day in April), compared with an average
rate of 3.8 metres over the last twelve months. The increased rates
reflect improved ground conditions now that tunnelling has moved
into the competent granodiorite lithology from the less competent
shale and limestone lithologies encountered last year. With the
lower access tunnel completed on the south side, development of the
main lower spiral ramp is underway and is on track for completion
by the end of June.
Figure 1: Breakthrough of Guajes Tunnel on
schedule for early Q1 2024 (advance rates as at end of April)
Steady progress was also made on ventilation and
in-mine development during the quarter. The Guajes Tunnel
ventilation raise was completed and the pilot hole for the first
ventilation raise within the Media Luna underground commenced. As
at the end of March, there were 18 active headings, including 6 in
Media Luna Lower and 12 in Media Luna Upper. Development across all
headings continues to advance well, with high monthly development
rates achieved as ground conditions have improved and intermittent
water inflows are less frequent and well managed. Vertical
development was initiated with the start of raise-boring in Media
Luna Upper.
Surface ConstructionNew work fronts were started
on the north side of the Balsas River during the quarter, including
civil development for the water treatment plant as well as rough
grading for the 230 kV substation. Expansion of the additional
laydown area in Atzcala also commenced, which included mobilization
of additional camp modules to house project staff. Installation of
new buried power conduits around the flotation plant began in
anticipation of starting civil works later this year.
On the south side of the Balsas River, expansion
of the construction camp pad continued ahead of the receipt of
additional camp modules by the end of June. Slope remediation of
the South Portal access road neared completion which, once
complete, will allow for civil works to continue at a more rapid
pace on the sediment and decant ponds. During the quarter, final
blasts related to the paste plant excavation were completed, with
pouring of the concrete generator pad to commence shortly.
Operational ReadinessIn parallel with
development and construction activities, the surface and
underground operational readiness planning is progressing to plan.
Operational readiness teams are accountable for ensuring that
processes and systems for all new work areas are established and
ready in advance of the handover from the project team to
operations. This includes workforce transition planning and
training (hiring for roles has commenced with initial job-specific
training expected to start shortly), developing the operating
strategy (including all standard operating procedures), maintenance
plans for all fixed and mobile equipment, blend and feed
strategies, detailed commissioning plans, first fills, concentrate
shipment logistics, and all other requirements to ensure a smooth
ramp up to commercial production in Q1 2025.
PROJECT EXECUTION PLAN
Based on progress made during Q1 2023, the
project execution plan is unchanged compared to the prior plan
outlined within the inaugural Media Luna update press release
published on February 9, 2023.
Figure 2: Project execution plan for the Media
Luna Project
The current project plan relative to the
Technical Report reflects the Company’s estimates for the
completion of key project deliverables. These updated deliverables
have not impacted the overall project schedule given the original
plan had assumed the potential for schedule adjustments and the
possibility for supply chain disruptions.
ABOUT TOREX GOLD RESOURCES
INC.
Torex is an intermediate gold producer based in
Canada, engaged in the exploration, development, and operation of
its 100% owned Morelos Property, an area of 29,000 hectares in the
highly prospective Guerrero Gold Belt located 180 kilometres
southwest of Mexico City. The Company’s principal asset is the
Morelos Complex, which includes the El Limón Guajes (“ELG”) Mine
Complex, the Media Luna Project, a processing plant, and related
infrastructure. Commercial production from the Morelos Complex
commenced on April 1, 2016 and an updated Technical Report for the
Morelos Complex was released in March 2022. Torex’s key strategic
objectives are to optimize and extend production from the ELG Mine
Complex, de-risk and advance Media Luna to commercial production,
build on ESG excellence, and to grow through ongoing exploration
across the entire Morelos Property.
FOR FURTHER INFORMATION, PLEASE
CONTACT:
TOREX GOLD RESOURCES INC.
Jody Kuzenko President and CEODirect: (647)
725-9982jody.kuzenko@torexgold.com |
Dan RollinsSenior Vice President, Corporate
Development & Investor RelationsDirect: (647)
260-1503dan.rollins@torexgold.com |
QUALIFIED PERSON
The technical and scientific information in this
press release has been reviewed and approved by Dave Stefanuto, P.
Eng, Executive Vice President, Technical Services and Capital
Projects of the Company, and a qualified person under National
Instrument 43-101.
CAUTIONARY NOTES
Forward-Looking StatementsThis
press release contains “forward-looking statements” and
“forward-looking information” within the meaning of applicable
Canadian securities legislation. Forward-looking information
includes, but is not limited to, statements that: the Media Luna
Project continues to track to overall schedule and budget; first
concentrate production remains on track for late 2024, with
commercial production still anticipated in early 2025; the level of
spending on the project is expected to increase throughout the
remainder of the year, with total project expenditures of $390
million to $440 million guided for 2023; the expected first
deliveries under the Sandvik purchase order in Q3 2023, in line
with the project schedule; the expected finalization of the
contracts for the personnel transportation vehicles, underground
construction, and underground vertical development; the Company’s
position to not only fund the development of Media Luna, but to
continue to advance additional value-enhancing initiatives with a
view to continuing to extend mine life and optimize economics at
our flagship Morelos Property; expected capital expenditures of
$390 to $440 million related to the development of the Media Luna
Project in 2023 ($66.4 million accrued during the first quarter),
which is forecasted to be the peak year of investment; expectation
that quarterly expenditures to increase into H2 2023, and remain
relatively consistent through H1 2024, before declining as
development activities wind down ahead of commercial production,
which is anticipated in early 2025; contract awards anticipated
shortly for the underground construction vertical development; the
mobilization of the successful underground construction contractor
is anticipated during Q2 2023; breakthrough of the Guajes Tunnel on
the south side of the Balsas River remains on track for Q1 2024, if
not earlier; expected commencement mid year of the delivery of
conveyor tables; completion of the slope remediation of the South
Portal access road allowing for civil works to continue at a more
rapid pace on the sediment and decant ponds; the operation
readiness planning, including workforce transition planning and
training, developing the operating strategy, maintenance plans for
all fixed and mobile equipment, blend and feed strategies, detailed
commissioning plans, first fills, concentrate shipment logistics,
and all other requirements to ensure a smooth ramp up to commercial
production in Q1 2025; the Project execution plan; and the
Company’s key strategic objectives are to optimize and extend
production from the ELG Mining Complex, de-risk and advance Media
Luna to commercial production, build on ESG excellence, and to grow
through ongoing exploration across the entire Morelos Property.
Generally, forward-looking information can be identified by the use
of forward-looking terminology such as “expect”, “plan”,
“strategy”, “schedule”, “anticipate”, “guide”, “continue”,
“forecast”, or variations of such words and phrases or statements
that certain actions, events or results “will” occur or are “on
track” to occur. Forward-looking information is subject to known
and unknown risks, uncertainties and other factors that may cause
the actual results, level of activity, performance or achievements
of the Company to be materially different from those expressed or
implied by such forward-looking information, including, without
limitation, risks and uncertainties identified in the technical
report (“Technical Report”) titled ELG Mine Complex Life of Mine
Plan and Media Luna Feasibility Study, with an effective date of
March 16, 2022, and a filing date of March 31, 2022 and in the
Company’s annual information form (“AIF”) and management’s
discussion and analysis (“MD&A”) or other unknown but
potentially significant impacts. Forward-looking information is
based on the reasonable assumptions, estimates, analyses and
opinions of management made in light of its experience and
perception of trends, current conditions and expected developments
as set out in the Technical Report, AIF and MD&A, and other
factors that management believes are relevant and reasonable in the
circumstances at the date such statements are made. Although the
Company has attempted to identify important factors that could
cause actual results to differ materially from those contained in
the forward-looking information, there may be other factors that
cause results not to be as anticipated. There can be no assurance
that such information will prove to be accurate, as actual results
and future events could differ materially from those anticipated in
such information. Accordingly, readers should not place undue
reliance on forward-looking information. The Company does not
undertake to update any forward-looking information, whether as a
result of new information or future events or otherwise, except as
may be required by applicable securities laws.
Photos accompanying this announcement are available at
https://www.globenewswire.com/NewsRoom/AttachmentNg/287cb9f8-a012-4bdf-ad8e-5eb9d94c846f
https://www.globenewswire.com/NewsRoom/AttachmentNg/2fa856f1-dc79-49c2-be18-ebe6d80fc70f
Torex Gold Resources (TSX:TXG)
過去 株価チャート
から 11 2024 まで 12 2024
Torex Gold Resources (TSX:TXG)
過去 株価チャート
から 12 2023 まで 12 2024