LUNDIN GOLD NOW PAST ONE KILOMETRE OF UNDERGROUND MINE DEVELOPMENT
AT FRUTA DEL NORTE
Lundin Gold Inc. ("Lundin Gold" or the "Company")
(TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce that is
has reached major construction milestones and is now past one
kilometre of underground mine development at its Fruta del Norte
gold project (“Fruta del Norte” or the “Project”) in Ecuador.
Construction Highlights:
- Process plant SAG and ball mill foundation bases have been
poured
- Major earthworks continue with completion of River road, which
significantly improves site logistics
- Completion of first major pond for site water management
system
- Powerline contractor mobilizing to start construction later
this quarter
- 1,000-person construction camp completed
“We continue to advance Fruta del Norte on
budget and on schedule. Overall engineering is 26% complete and
construction is 16% complete, and we are continuously looking for
efficiencies as we move the Project forward,” said Ron Hochstein,
President and CEO of Lundin Gold.
Mine Development
As at March 31, 2018, a total of 1,193 metres
(“m”) of underground mine development has been achieved, with 531 m
and 632 m in the Kuri and K’isa declines, respectively. The average
advance rate for March was 5.95 m per decline per day, versus a
target of 5.17 m per day based on ground type encountered.
All underground development in March was classified as good
ground type conditions.
As well, earlier this month the Company awarded
the underground drill/bolt mining fleet to Epiroc Rock Drills AB.
With this order, over 84% of the production fleet contracts
have been placed. The outstanding mine equipment left to be ordered
is the explosives delivery, shotcrete equipment and mine support
equipment.
Process Plant Construction
Process plant excavation was 65% complete at the
end of March. The ball mill and the SAG mill base concrete
foundations were poured on March 10 and March 25 respectively.
Excavation of the CIL plant area is progressing well.
Over the next couple of months, the Company is planning on
completing the mill foundations, and concrete work on the CIL plant
area is expected to commence.
As part of the overall water management system,
the first of several large lined collection ponds was
completed.
Major Earthworks
With the completion of the River road connecting
the camp to the Project site, site logistics have greatly improved.
Travel time between camp and the Project site is now
approximately 10-15 minutes, whereas it previously took up to 45
minutes using the Mountain Pass road. The North Access road
is now an estimated 42% complete, and work is substantially
complete on the road to the tailings storage facility.
Powerline
The powerline engineering, procurement and
construction contractor is mobilizing and anticipated to begin
construction later this quarter. Easement agreements have
been reached with nearly all the affected landholders, and the
remaining easements are expected to be obtained in the coming
weeks.
Construction Camp
The new 1,000-person construction camp is
complete, and all rooms are available for occupancy. Combined
with the existing Las Peñas camp, over 1,700 people can be
accommodated at site. Occupancy averaged 1,165 people in
March, and total project employment now exceeds 2,200 people,
including contractors. The new kitchen and dining room are
expected to be finished by the end of the month.
About Lundin Gold
Lundin Gold, headquartered in Vancouver, Canada,
is developing its wholly-owned Fruta del Norte gold project in
southeast Ecuador. Fruta del Norte is one of the
highest-grade and largest gold projects currently under
construction. The Company’s board and management team have
extensive expertise in mine construction and operations and are
dedicated to advancing this project through to first gold
production in 2019.
The Company operates with transparency and in
accordance with international best practices. Lundin Gold is
committed to delivering value to its shareholders, while
simultaneously providing economic and social benefits to impacted
communities, fostering a healthy and safe workplace and minimizing
the environmental impact. The Company believes that the value
created through the development of Fruta del Norte will benefit its
shareholders, the Government and the people of Ecuador.
This press release has been reviewed and
approved by Ron Hochstein, P. Eng., a metallurgical engineer and
the Company's President and CEO, who is a Qualified Person under
Canadian National Instrument 43-101.
Additional Information
The information in this release is subject to
the disclosure requirements of Lundin Gold under the EU Market
Abuse Regulation. This information was submitted for publication on
April 16, 2018 at 3:00 am PT through the contact persons set out
below.
Follow Lundin Gold on Twitter
Caution Regarding Forward-Looking
Information and Statements
Certain of the information and statements in
this press release are considered “forward-looking information” or
“forward-looking statements” as those terms are defined under
Canadian securities laws (collectively referred to as
“forward-looking statements”). Any statements that express or
involve discussions with respect to predictions, expectations,
beliefs, plans, projections, objectives, assumptions or future
events or performance (often, but not always, identified by words
or phrases such as “believes”, “anticipates”, “expects”, “is
expected”, “scheduled”, “estimates”, “pending”, “intends”, “plans”,
“forecasts”, “targets”, or “hopes”, or variations of such words and
phrases or statements that certain actions, events or results
“may”, “could”, “would”, “will”, “should” “might”, “will be taken”,
or “occur” and similar expressions) are not statements of
historical fact and may be forward-looking statements.
By their nature, forward-looking statements and
information involve assumptions, inherent risks and uncertainties,
many of which are difficult to predict, and are usually beyond the
control of management, that could cause actual results to be
materially different from those expressed by these forward-looking
statements and information. Lundin Gold believes that the
expectations reflected in this forward-looking information are
reasonable, but no assurance can be given that these expectations
will prove to be correct. Forward-looking information should
not be unduly relied upon. This information speaks only as of
the date of this press release, and the Company will not
necessarily update this information, unless required to do so by
securities laws.
This press release contains forward-looking
information in a number of places, such as in statements pertaining
the timing of first production and the progress of the development,
construction and operation of the Project, improvements to site
logistics and completion of camp infrastructure and the acquisition
of land and surface rights. Factors that could cause actual results
to differ materially from the Company’s expectations include, but
are not limited to; the ability to arrange financing and the
risk to shareholders of dilution from future equity financings; the
ability to maintain its obligations under its current project
financing and other debt; risks related to carrying on business in
Ecuador; volatility in the price of gold; the timely receipt of
regulatory approvals, permits and licenses; risks associated with
the performance of the Company’s contractors; risks inherent in the
development of an underground mine; deficient or vulnerable title
to mining concessions and surface rights; shortages of critical
resources, labour and key executive personnel, such as input
commodities, equipment and skilled labour, and the dependence on
key personnel; risks associated with the Company’s community
relationships; unreliable infrastructure; volatility in the market
price of the Company’s shares; and the potential influence of the
Company’s largest shareholders; uncertainty with the tax regime in
Ecuador; measures required to protect endangered species; the cost
of compliance or failure to comply with applicable laws;
exploration and development risks; the accuracy of the Mineral
Reserve and Resource estimates for the Fruta del Norte Project and
the Company’s reliance on one project; risks related to artisanal
and illegal mining; uncertainty as to reclamation and
decommissioning; risks associated with the Company’s information
systems; competition in the mining industry; the ability to obtain
adequate insurance; risks of bribery or corruption; the
potential for litigation; and limits of disclosure and internal
controls.
There can be no assurance that such statements
will prove to be accurate, as Lundin Gold's actual results and
future events could differ materially from those anticipated in
this forward-looking information as a result of the factors
discussed in the "Risk Factors" section in Lundin Gold's Annual
Information Form dated March 20, 2018, which is available under the
Company’s profile at www.sedar.com.
Lundin Gold (TSX:LUG)
過去 株価チャート
から 11 2024 まで 12 2024
Lundin Gold (TSX:LUG)
過去 株価チャート
から 12 2023 まで 12 2024