Pan
African Resources PLC
(Incorporated
and registered in England and Wales under the Companies Act 1985
with registered number 3937466 on 25 February 2000)
Share code
on AIM: PAF
Share code
on JSE: PAN
ISIN:
GB0004300496
ADR ticker
code: PAFRY
("Pan
African" or the "Company" or the "Group")
|
Pan
African Resources Funding Company Limited
Incorporated
in the Republic of South Africa with limited liability
Registration
number: 2012/021237/06
Alpha
code: PARI
|
Pan
African
is
pleased
to
provide
shareholders
and
noteholders
with
an
update
as
follows:
Group
production
and
cost
guidance
-
Production
guidance for the year ending 30 June
2024 (current financial year) narrowed to between 186,000oz
to 190,000oz (previously 180,000oz to 190,000oz)
-
In the
second half of the financial year, the Group ceased processing of
marginal surface sources
at
Evander
Gold
Mines
(EGM)
due
to
this
business,
which
contributed
approximately 2,500oz in the first half of the current financial
year, becoming
uneconomical
-
If
production from these sources was maintained in the second half of
the financial year, Group production for the full financial year
would have been in excess of
190,000oz
-
Group
AISC
guidance
for
the
current
financial
year
maintained
at
between
$1,325/oz
to
$1,350/oz (assumed
exchange
rate:
ZAR/US$:18.50)
-
Production
guidance
for
the
2025
financial
year
of
215,000oz
to
225,000oz.
MTR
Project
(The
Project)
-
The
Project is on schedule for commissioning and steady state
production during December
2024
-
Capital
cost
for
the
Project
remains
on
budget,
with
no
expenditure
overruns
expected
-
The
Project's financial model, based on its definitive feasibility
study (DFS), was updated to include the latest operating cost and
production estimates, forecast ZAR/US$ exchange rate and US$ gold
price. These updates are as follows:
- Exchange
rate
and
gold
price
revisions:
- Exchange
rate
of
ZAR/US$:19.00
(initial
DFS
model:
ZAR/US$:15.50)
-
Gold
price
of
US$2,200/oz (initial
DFS
model:
US$1,750/oz)
-
The
updated DFS financial model outputs (relative to the initial DFS
model) are as
follows:
-
The model
Pre-tax NPV increased to US$183
million (initial DFS model: NPV of US$63 million)
-
The
ungeared
real
IRR
increased
to
41.7%
(initial
DFS
model:
IRR of
20.1%)
-
Payback on
upfront capital investment of ~US$135.1
million reduced to approximately 2 years (initial DFS model:
3.5 years), post commissioning.
An
internal
pre-feasibility
study
(PFS)
for
the
Soweto cluster
was
also
completed
in
March
2024,
based
on the
drill
results
from
the
2L16
and
2L24
tailings
storage
facility
(TSF).
The
PFS
considered
numerous
options, with the most feasible being:
-
Development
of
re-mining,
overland
piping
and
pumping
infrastructure
at
the
Soweto cluster
resource to process the material at the MTR plant
-
Using this
option, the MTR plant's capacity can be expanded to process 1
million tonnes per month of feed material, compared to the current
design capacity of 800ktpm, resulting in a
life-of-mine (LOM)
of 21
years for the
combined Mogale and
Soweto cluster resources.
The
resultant tailings can be
deposited into the expanded Mogale TSF at the West Wits pit and
1L23-25 footprint.
The
outcomes
of
the
PFS
are
as
follows:
-
Processing
of
the
Soweto Cluster
has
the
potential
to
expand
the
MTR
operation
-
The
MTR
plant
infrastructure
can
be expanded
to
treat
1
million
tonnes
per
month
from year 6 of
the MTR operation's LOM
-
The
addition of the 110 million tonne Soweto Cluster Mineral Resource
has the potential to increase MTR production to approximately
60koz/year over a 21-year LOM
-
Total
additional capital requirement of US$113
million (approximately US$83
million would be incurred from year 4 to year 6 and
US$29 million in year 10 of the MTR's
operation)
-
At
US$2,200/oz and an exchange rate of
ZAR/US$:19.00, the Pre-tax NPV combined for Mogale and
the Soweto
Cluster is
US$283 million, representing an increase
of
US$96 million,
relative to Mogale's updated standalone financial model
-
The
real
ungeared
IRR
increases
to
44.0%,
relative
to
the
IRR
of
41.7%
in
the
updated
Mogale
financial model.
The Group
will now
proceed with the necessary permitting
and servitudes required for the
re-mining
and processing of the Soweto Cluster, with a final investment
decision in due course.
Pan
African
CEO
Cobus
Loots
commented:
"We
are
pleased
that
Pan
African
will
achieve
the
upper
end of
our
full year
production
guidance,
and
would have exceeded guidance had we continued with the processing
of surface material at Evander in the second half of the financial
year.
The
robust
production
results,
combined
with
record
Rand
gold
prices,
should
see
the
Group
deliver
an
excellent financial performance for the year.
Our
MTR project remains on schedule and on budget, and we look forward
to commissioning it later in 2024. We have now demonstrated that
the addition of the Soweto Cluster resources further improves the
economic attractiveness of this world class
project."
Final
results
for
the
twelve
months
ended
30
June
2024
Pan
African
will
announce
its
final
results
for
the
current
financial
year
on
11
September
2024.
The
information
contained
in
this
update
is
the
responsibility
of
the
Pan
African
board
of
directors
and has
not been reviewed or reported on by the Group's external
auditors.
Certain
information communicated in this announcement was, prior to its
publication, inside information for the purposes of Article 7 of
Regulation 596/2014.
Rosebank
9
May
2024
For
further
information
on
Pan
African,
please
visit
the
Company's
website
at
www.panafricanresources.com
Corporate
information
|
Corporate
office
|
Registered
office
|
The
Firs
Building
|
2nd
Floor
|
2nd
Floor,
Office
204
|
107
Cheapside
|
Cnr.
Cradock
and
Biermann
Avenues
|
London
|
Rosebank,
Johannesburg
|
EC2V
6DN
|
South
Africa
|
United
Kingdom
|
Office:
+
27
(0)11
243
2900
|
Office:
+
44
(0)20
7796
8644
|
info@paf.co.za
|
info@paf.co.za
|
Chief
executive
officer
|
Financial
director
|
Cobus
Loots
|
Deon
Louw
|
Office:
+
27
(0)11
243
2900
|
Office:
+
27
(0)11
243
|
|
2900
|
Head:
Investor
relations
Hethen
Hira
Tel:
+
27
(0)11
243
2900
E-mail:
hhira@paf.co.za
|
Website:
www.panafricanresources.com
|
Company
secretary
Jane
Kirton
St
James's
Corporate
Services
Limited
Office:
+
44
(0)20
7796
8644
|
Nominated
adviser
and
joint
broker
Ross
Allister/Georgia Langoulant Peel
Hunt LLP
Office:
+44
(0)20
7418
8900
|
JSE
Sponsor
and
JSE
debt
sponsor
Ciska
Kloppers
Questco
Corporate
Advisory
Proprietary
Limited
Office:
+
27
(0)11
011
9200
|
Joint
broker
Thomas
Rider/Nick Macann BMO
Capital
Markets
Limited
Office:
+44 (0)20 7236 1010
|
|
Joint
broker
Matthew
Armitt/Jennifer Lee Joh.
Berenberg,
Gossler
&
Co
KG
Office:
+44 (0)20 3207 7800
|