Kodal
Minerals Plc / Index: AIM / Epic: KOD / Sector: Mining
5 September 2024
Kodal Minerals
plc
("Kodal
Minerals", "Kodal" or the "Company")
Bougouni Lithium Project Mine
Construction Update
& Boumou Prospect
Drilling Update
Kodal Minerals, the mineral
exploration and development company, is
pleased to provide an update on the progress of construction of the
Dense Media Separation ("DMS") processing plant and mining at the
Ngoualana open pit mine at its flagship fully funded Bougouni
Lithium Project in Southern Mali ("Bougouni" or the "Project"). The
Project is fully funded through the US$117.5m Hainan funding
transaction, (see RNS as previously announced by the Company on 15
November 2023). This funding transaction includes a US$100m
investment into Kodal Mining UK Limited ("KMUK"), a company owned
51% owned by the Hainan Group and 49% by Kodal, who is the
developer of the Project.
We also provide a further update on
drilling assay results returned at the Boumou prospect, located
within the Bougouni Lithium Project in Southern Mali. These
reported assay results are from reverse circulation ("RC") drill
holes completed in April and May 2024, which continue to return
lithium mineralisation and define the geological controls on the
Boumou prospect's pegmatite bodies. Final assay results for
the RC drilling programme and all assay results for the diamond
core drilling are pending, with results expected in due
course.
Highlights:
· The first two shipments from China carrying the critical long
lead equipment items and structural steelwork for the plant
buildings have arrived at the Abidjan Port in Côte
d'Ivoire;
·
Offloading at the port has progressed quickly,
utilising the services of Africa Cargo Central, a West African
specialist supply chain and logistics management
company;
·
First convoy of trucks arrived at the Bougouni
customs post and upon final clearance will deliver goods to
site;
·
The civil construction works have continued to
progress well at Bougouni and overall completion has reached 85%
with the completion of only minor floor slabs and smaller footings
remaining;
·
Open Pit mining at the main Ngoualana pit is
progressing, with the removal of overburden continuing and
completion of three blasts of exposed hard rock and pegmatite
bodies completed. This will ensure stockpiles of Ngoualana ore will
be available well in advance of commissioning in Q4
2024;
·
Wide, high-grade extensions returned at the Boumou
Prospect include:
o 7m
at 1.16% Li2O from 147m in drill hole
KLRC223;
o 13m
at 1.07% Li2O from 71m in drill hole KLRC224;
·
Diamond core drilling is continuing at the Boumou
prospect to provide detailed geological information as well as
samples for future metallurgical test work and geotechnical logging
for open pit optimisation parameters.
Bernard Aylward, CEO of Kodal Minerals,
remarked: "I am delighted to report
that the Stage 1 development of the Bougouni Lithium Project
continues to rapidly advance. The DMS and Ngoualana open pit
development continues to advance with the open pit mining currently
ahead of schedule, with no impact from the heavy rainfall
experienced in July and early August associated with a heavy rainy
season in 2024. Ahead of the assembling of the DMS processing
plant, site works have continued to advance as planned with the
completion of the foundations for the DMS units, and processing
infrastructure and the crushing circuit. The area of the
processing plant, office buildings and the open pit have remained
outside of high-water levels and provide confidence of future
mining and processing activities throughout the
year."
"The arrival of the first shipping cargoes into the Abidjan
Port, and subsequent commencement of transport to the site is yet
another positive step towards the successful development of the
Bougouni Lithium Project. The contract for the DMS site
installation has been awarded to local company, Bambara Resources
SARL and subcontractor partner Jinpeng, who have recently completed
the installation of a similar DMS processing plant in
Nigeria. In addition, the site installation will be supported
by expert engineers from Beijing High Dynamic, for the crushing
circuit and from Haiwang Technology Group for the DMS units.
This oversight will provide additional guidance and design
verification for the successful plant commissioning of the
operation."
"The development of Bougouni the Project is now entering a
critical and exciting phase as the construction assembling of the
processing circuit commences and we will continue to provide
regular updates as work progresses."
FURTHER
INFORMATION
Ngoualana DMS and Open Pit
Development
Shipping
Transport
The first two shipments from China
carrying the critical long lead equipment items and structural
steelwork for the buildings have arrived at the Abidjan Port in
Cote d'Ivoire. Offloading at the port has progressed quickly,
utilising the services of West African specialist supply chain and
logistics management company, Africa Cargo Central ("ACC"). The
equipment and materials are being consolidated at ACC's yard in
Abidjan, and then sorted to ensure cargo is transported to site in
priority order. The first convoy of eleven trucks has arrived at
the Bougouni customs post and, following final clearance, is
expected to arrive on site shortly.
The final supply of imported
equipment, goods and materials expected from China will be
dispatched in two shipments: the first shipment is currently being
loaded in Tianjin and will contain predominantly the electrical
equipment, cables and cable supports, and the majority of piping
materials, valves and instruments.
The final shipment will contain the
Project's power plant, transformers and associated materials. In
order to mitigate the impact of any potential impact delays to
commissioning of the DMS processing plant, that may arise with a
delay in the arrival of the power plant, the site team will arrange
for temporary hired generators to be utilised to help conduct the
pre-commissioning of equipment. This will ensure that the main
drivers are operational before connecting to the mains power plant,
in order that commissioning with ore can proceed quickly
thereafter.
Mining
To date, mining works are
progressing ahead of schedule, and the Company is confident that
stockpiles of Ngoualana ore will be available to the plant well in
advance of commissioning.
Mining activities have continued to
predominantly involve the removal of "free-dig" overburden at the
main Ngoualana pit. Recently in some areas of the open pit hard
rock has been reached recently which will require blasting for
removal.
The mining contractor, EGTF Mining
SARL ("EGTF") and Auxin Mining Services Mali SARL ("Auxin"),
successfully conducted the first trial blast on the site ahead of
schedule and has subsequently completed two further blasts of hard
rock and pegmatite material. These initial blasts have enabled the
mining team and contractor to test all the safety, communication
and operational protocols required.
Civil Construction - Concrete
Contract
The civil construction works have
continued to progress satisfactorily and overall completion has
reached 85% with only minor floor slabs and smaller footings
remaining to be finished. It is anticipated that the concrete works
onsite contractor will be fully complete in September 2024,
providing unfettered access to the site for structural, mechanical
and piping installation to proceed.
SMPP Installation
Contractor
The SMPP ("Structural, Mechanical,
Platework and Piping") installation contract has been awarded to
Bambara Resources SARL ("Bambara") together with its key
subcontractor, Jinpeng ("Jinpeng"), a construction and
installations specialist engineering company from China.
Jinpeng last year successfully completed the installation of a DMS
processing plant in Nigeria, which is a plant very similar to the
planned Bougouni DMS and was also designed by the same engineering
company from China, Haiwang Technology Group
("Haiwang").
The Bambara/Jinpeng contract is
similar to the successful implementation strategy used for the
Bougouni civil works whereby Bambara will provide all local labour,
equipment and services and as well as manage Jinpeng, which will
provide the engineering technicians and on-site supervision. Two
expert engineers each from both Beijing High Dynamic (supplier of
the crushing modules) and Haiwang will mobilise to Mali in
mid-September 2024 to provide guidance and design verification
during installation and commissioning. The Project team believes
that this contracting arrangement will be crucial to correctly
interpreting the designs and drawings during construction, since
they were developed using Chinese language, as part of the Haiwang
package. Importantly, the arrangement between Bambara and Jinpeng
as sub-contractor will also ensure compliance with Mali's local
content laws, as stipulated under the country's revised mining code
and will maximise the employment of locals.
Environmental and Social
updates
The Bougouni area has experienced
heavy rainfall in July and early August 2024, resulting in some
flash flooding and damage to the main road ("RN8") used by the
local communities and by the Company. With the help of Malian
mining contractor EGTF Mining SARL, the Company has conducted
multitude of repairs to the RN8 in order to restore the road to a
safe operating condition. The 2024 wet season in Mali has
been a heavier than usual rainfall year with the site experiencing
significant rises in the water levels of the Baoule river as well
as local creek area. Positively, the site area has coped well
with the higher-than-normal water levels with the open pit and
processing areas remains above water level. Access to the
site was restricted for one half day due to road flooding, however,
this has had no impact on the development activities.
The procedure for employing workers
from the local labour pool is also operating well.
Local recruitment numbers from the impacted
villages at Bougouni for the construction phase has reached a total
of 144 personnel. In total, the Project employs upwards of
350 personnel, of which currently approximately 93% are
Malian.
Boumou Prospect Drilling
Update
Further RC drilling results have
been received for the Boumou prospect drilling campaign completed
in April and May this year. The programme consisted of 18 RC
drill holes for a total of 3,234m. The drilling targeted
further westward extensions of the wide pegmatite bodies
intersected in the March 2023 drilling campaign and the updated
Mineral Resource estimate (MRE), which currently is 13.1Mt at 1.04%
Li2O.
The assay results received are from
four RC holes targeting the western extension of the ore body and
highlight a zone of strong alteration and faulting that has
resulted in the thinning of the pegmatite bodies and loss of
lithium mineralisation. This is consistent with the
geological interpretation that highlighted wide continuous
pegmatite bodies up to a marked north-south oriented creek, that
was interpreted to be associated with a fault structure. The
geological team is reviewing and targeting faulted offsets to the
Boumou prospect.
Lithium mineralised results have
been returned for two RC drill holes, targeting the northeastern
extension of the Boumou mineralisation. These drill hole
results are consistent with previous drilling, however, are still
outside of the projected extension of the main zone of wide high
grade pegmatite bodies, and this will be targeted with the diamond
drill holes and further RC drilling. Assay results are
pending for an additional two RC drill holes along with some
re-check sampling.
The Boumou prospect has confirmed a
strike length of over 970m and remains open along strike to the
northeast. Additional drill results from previously reported
are tabled below:
Hole ID
|
From
(metres)
|
To (metres)
|
Width
(metres)
|
Grade Li2O
(%)
|
KLRC223
|
91
|
92
|
1
|
1.11
|
|
97
|
100
|
3
|
1.21
|
|
147
|
154
|
7
|
1.16
|
KLRC224
|
12
|
13
|
1
|
1.46
|
|
15
|
17
|
2
|
1.40
|
|
25
|
26
|
1
|
1.46
|
|
53
|
55
|
2
|
1.14
|
|
71
|
84
|
13
|
1.07
|
|
115
|
125
|
10
|
0.95
|
Notes: Drill holes are RC
drill holes. Drill holes have been sampled on a 1.0m basis
with samples collected via a riffle split system. All drill holes
are geologically logged, and sampling for analysis is based on
geological boundaries. Samples analysed by ALS Global. Assay
results are reported as Li% and converted to
Li2O% by
a factor of 2.153. Intersections are reported using
geological boundaries for logged pegmatite, with a nominal
0.5%Li2O
lower-cut-off and allowing for internal dilution in zones of broad
pegmatite mineralisation.
Diamond core drilling is ongoing to
provide detailed geological information to support the
interpretation of the mineralised zones. The initial
geological logging and comparison of the diamond drill core and the
logging of the RC drill holes has confirmed the continuity of the
pegmatite veins and highlighted the coarse nature and coarse
spodumene mineralisation.
For further information, please
visit www.kodalminerals.com
or contact the following:
Kodal Minerals plc
Bernard Aylward, CEO
|
Tel: +61 418 943 345
|
Allenby Capital Limited, Nominated
Adviser
Jeremy Porter/Vivek
Bhardwaj
|
Tel: 020 3328 5656
|
SP Angel Corporate Finance LLP,
Financial Adviser & Joint Broker
John Mackay/Adam Cowl
|
Tel: 020 3470 0470
|
Canaccord Genuity Limited, Joint
Broker
James Asensio/Gordon
Hamilton
|
Tel: 0207 523 4680
|
Buchanan, Financial PR
Bobby Morse/Oonagh Reidy
|
Tel: +44 (0)20 7466 5000
kodal@buchanancomms.co.uk
|
The exploration results and activity
reported in this announcement have been reviewed by Mr Bernard
Aylward who is a Member of the Australasian Institute of Mining and
Metallurgy. Mr Aylward has sufficient experience that is relevant
to the style of mineralisation and type of deposit under
consideration and to the activity being undertaken to qualify as a
Qualified Person as defined in the AIM Note for Mining and Oil
& Gas Companies dated June 2009. Mr Aylward consents to the
inclusion in this announcement of the matters based on his
information in the form and context in which it appears.