Base Resources Limited Further supporting information for Bumamani PFS
2021年9月3日 - 5:40PM
RNSを含む英国規制内ニュース (英語)
TIDMBSE
AIM and Media Release
3 September 2021
BASE RESOURCES LIMITED
Further supporting information for Bumamani PFS
African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (Base
Resources or the Company) provides the following further supporting information
in respect of the outcomes of the Bumamani pre-feasibility study announced
earlier today (Bumamani PFS).
Mining method
The mining method assumed for the Bumamani PFS was hydraulic mining, utilising
Kwale Operations' existing hydraulic mining units (HMUs). This mining method
has been successfully used at Kwale Operations since 2017. It is
non-selective, with hydraulic mining units using high pressure water jets to
sluice the entire ore face, creating an ore slurry which can then be pumped to
the wet concentrator plant.
Processing method
Material mined would be processed through Kwale Operations' existing wet
concentrator plant and mineral separation plant. Recovery factors assumed are
the same as those currently experienced at Kwale Operations and are set out in
the table below. This is supported by the metallurgical testwork carried out
on the Kwale North Dune (which includes the P199 section the subject of the
Bumamani PFS).
The metallurgical testwork comprised wet concentrator and mineral separation
plant tests on bulk samples collected from two 61cm diameter holes drilled in
the Kwale North Mineral Resource, as part of the earlier Kwale North
pre-feasibility study1. One of the holes (KN091) was adjacent to the P199
section, which forms part of the Bumamani PFS. Discrete ore zones were sampled
(Ore1, Ore4 and Ore5) from each hole. The samples were dried and shipped to
Brisbane, Australia for processing through IHC Robbins' laboratory. Samples of
the fine tailings generated by IHC Robbins were sent to Outotec Metso for
thickener testwork. The results of the testwork were not materially different
to the run of mine results currently being achieved from mining the Kwale South
Dune deposit. No metallurgical testwork was completed on the Bumamani deposit,
however, it exhibits similar characteristics (including particle size) to ore
currently mined at Kwale South Dune and is expected to achieve similar
processing results, including mineral recoveries, as those achieved from mining
the Kwale South Dune ore. With material from the Bumamani deposit and the P199
section to be mined and processed concurrently with the Kwale South Dune
deposit, product recoveries similar to those currently achieved from mining
Kwale South Dune ore were assumed for the Bumamani PFS.
Description Units Testwork Result Bumamani PFS
(consistent with
current)
Concentrate grade % 85.1 85
HM recovery - wet concentrator % 83.0 79.5
plant
Ilmenite recovery - wet % 94.6 91.8
concentrator plant
Rutile recovery - wet concentrator % 94.8 91.2
plant
Zircon recovery - wet concentrator % 98.0 96.3
plant
Ilmenite recovery - mineral % N/A 100
separation plant
Rutile recovery - mineral % N/A 100.5
separation plant
Zircon recovery - mineral % N/A 84
separation plant
[Note (1): For further information, refer to Base Resources' market
announcement on 1 April 2021 "Kwale North Dune PFS outcomes" available at
https://baseresources.com.au/investors/announcements/.]
Mining schedule
Pursuant to the Bumamani PFS, four existing HMUs will be utilised instead of
three (as is current mining practice at Kwale South Dune), two continuing to
mine at Kwale South Dune and two at the pits the subject of the Bumamani PFS.
After the transition to four HMUs, in both areas one HMU will operate at 800
tph and one at 400 tph to give a total feed rate of 2400 tph, consistent with
the present feed rate at Kwale South Dune. HMUs are capable of mining at
either 400 or 800 tph by operating either one or two high pressure monitors,
each capable of 400 tph.
A shutdown of mining operations and the wet concentrator plant is scheduled for
February 2023 to relocate HMUs and associated pumping infrastructure, after
which mining at the Bumamani pit will commence. Following depletion of the
Bumamani pit in July 2023, all mining equipment will relocate to P199 while
mining continues at Kwale South Dune. A mine move at Kwale South Dune is
scheduled for March 2024, during which mining operations will continue at the
P199 section. During planned shuts for the relocation of mining operations,
the feed rate of mining units that remain operational will be maximised.
For a chart summarising the mining schedule assumed for the Bumamani PFS,
compared to the mine plan if the Bumamani Project does not proceed and figures
depicting the planned HMU and tailings schedules for the Bumamani PFS, refer to
the full PDF version of this announcement available from the Company's website:
https://baseresources.com.au/investors/announcements/ .
ENDS.
For further information contact:
James Fuller, Manager Communications and Investor UK Media Relations
Relations
Base Resources Tavistock Communications
Tel: +61 (8) 9413 7426 Jos Simson and Gareth Tredway
Mobile: +61 (0) 488 093 763 Tel: +44 (0) 207 920 3150
Email: jfuller@baseresources.com.au
About Base Resources
Base Resources is an Australian based, African focused, mineral sands producer
and developer with a track record of project delivery and operational
performance. The company operates the established Kwale Operations in Kenya
and is developing the Toliara Project in Madagascar. Base Resources is an ASX
and AIM listed company. Further details about Base Resources are available at
www.baseresources.com.au
PRINCIPAL & REGISTERED OFFICE
Level 3, 46 Colin Street
West Perth, Western Australia, 6005
Email: info@baseresources.com.au
Phone: +61 (0)8 9413 7400
Fax: +61 (0)8 9322 8912
NOMINATED ADVISOR
RFC Ambrian Limited
Stephen Allen
Phone: +61 (0)8 9480 2500
JOINT BROKER
Berenberg
Matthew Armitt / Detlir Elezi
Phone: +44 20 3207 7800
JOINT BROKER
Canaccord Genuity
Raj Khatri / James Asensio / Patrick Dolaghan
Phone: +44 20 7523 8000
END
(END) Dow Jones Newswires
September 03, 2021 04:40 ET (08:40 GMT)
Base Resources (LSE:BSE)
過去 株価チャート
から 9 2024 まで 10 2024
Base Resources (LSE:BSE)
過去 株価チャート
から 10 2023 まで 10 2024