RNS Number : 9737G
  Avocet Mining PLC
  30 October 2008
   


    Q2 GOLD PRODUCTION
    PRODUCTION AND CASH COSTS IN LINE WITH EXPECTATIONS
    - ON TRACK FOR PRODUCTION INCREASE IN H2

    Avocet Mining PLC ("Avocet" or "the Company") announces gold production in its second quarter to 30 September 2008 of 27,756 ounces, in
line with the expectations set out in the Company's Q1 production release of 31 July 2008 and in line with production in the prior quarter
of 28,022 ounces.  All gold sales were into the spot market during the quarter with an average realised price of US$870/oz compared with
US$684/oz in Q2 last year. 

    Furthermore, the Company is on track to deliver its planned second half production increase, following  progress on the initiatives
outlined in July, and updated below, to enhance grades at Penjom and recovery at North Lanut.  Cash costs continued to reflect high
consumable prices, especially diesel and kerosene as a result of record world oil prices.  Average cash costs in Q2 were US$506/oz, 3% below
the Q1 cost of US$521/oz due to a higher deferred stripping adjustment at Penjom.  

    Appendix 1 sets out key operating statistics including production and cash costs by quarter for this year and the prior year for both
Penjom and North Lanut. Appendix 2 sets out Penjom's waste and ore volumes and mining cost per tonne for each year, as well as the
calculation of stripping costs deferred in  Q2 FY2009.
      
    Penjom, Malaysia

    Gold production in Q2 of 17,793 ounces was 5% below Q1.  Pending the imminent transition to higher grade mining areas, Q2 ore continued
to be sourced predominantly from the bottom of the main Kalampong pit where grades have been lower than anticipated.  In response, changes
to the mine plan have been implemented and good progress was made in the quarter in accessing the new mining areas on the east wall and in
the Janik and Manik areas to the south of the main pit. Stripping was accelerated to bring forward mining in these higher grade areas during
the second half.  A stream diversion was completed on 19 September to facilitate mining of Janik.

    Before adjustment for deferred stripping, Penjom's cash cost per ounce of US$576/oz was the same as  the Q1 cost, with the overall
impact of fuel related costs equal in each quarter.  The high strip ratio of 42.9 in Q2 meant that after deferred stripping adjustment,
Penjom's Q2 reported cash cost was US$420/oz compared with US$481/oz in Q1 when the stripping ratio was 29.4.  In the second half, Penjom's
cash cost per ounce before deferred stripping is expected to fall due to higher production and lower fuel and kerosene prices, although mine
maintenance costs will rise as more of the truck fleet enters a component overhaul programme.  Reported cash costs, after deferred stripping
adjustment, will depend on the level of stripping in Q3 and Q4.  The strip ratio is expected to fall significantly in the second half as
mining focuses again on ore mining after a period of heavy waste stripping in Q2.

    North Lanut, Indonesia

    North Lanut's gold production in Q2 of 9,963 ounces was 7% above Q1 as higher tonnes processed more than compensated for lower recovery.
 Ore treated was highly sulphidic throughout the quarter, and recovery at 31% was therefore lower than the 38% achieved in Q1, which
benefited from a higher proportion of oxide material.  During Q2 several projects were progressed with a view to enhancing recovery, as
outlined in the Company's Q1 release. A new mobile crusher and a leach plant upgrade were commissioned at the end of the quarter and work
continued on the new HLP3 leach pad which will provide separate cells for the different ore types.  In addition, a decision was made to
bring forward mining of the Effendi deposit to the north of the Riska pit, as Effendi ore is mainly oxide and therefore yields a higher
recovery from dump leaching. Pre-treatment of Riska's sulphide ore is being evaluated to improve subsequent leaching.

    North Lanut's cash cost of US$661/oz was 10% above Q1, with diesel prices and lime consumption both higher, the latter reflecting the
more sulphidic material treated and the timing of lime dosing.  In the second half, costs are expected to benefit from lower fuel prices and
higher production.  

    Further details of production and cash costs will be provided in the interim results to be announced on 12 November 2008.



    Jonathan Henry, Chief Executive Officer, commented:

    "Good progress has been made on a wide range of measures intended to improve gold production at both mines during the second half of
FY2009 and to address the ongoing challenges of grade and recovery we have been facing over the last year.  Together with promising
exploration results I view these efforts as encouraging for the future."  



              Avocet Mining PLC              Buchanan  Ambrian Partners Limited          JPMorgan Cazenove
                                       Communications    NOMAD and Joint Broker                Lead Broker
                                         Financial PR                                                     
                                          Consultants
                                                     
          Jonathan Henry, Chief           Bobby Morse             Richard Brown  Michael Wentworth-Stanley
              Executive Officer
  Mike Norris, Finance Director         Sam Botterill        Richard Greenfield              Sam Critchlow
                  020 7907 9000         020 7466 5000             020 7634 4709              020 7588 2828
               www.avocet.co.uk   www.buchanan.uk.com           www.ambrian.com   www.jpmorgancazenove.com


    Notes to Editors
    Avocet is a mining company listed on the AIM market of the London Stock Exchange (Ticker: AVM). The Company's principal activities are
gold mining and exploration in Malaysia (as 100 per cent owner of the Penjom mine, the country's largest gold producer), and Indonesia (as
80 per cent owner of the North Lanut gold mine and Bakan project in North Sulawesi). The Company has a number of other advanced mining and
exploration projects in South East Asia.

    Background to operations

    The Penjom gold mine is Malaysia's largest gold producer and was developed by Avocet after applying modern technology to grass roots
exploration in an area of historic mining. The mine was commissioned in December 1996 with reserves of 223,000 ounces. Successful resource
development, particularly over the last five years, means Penjom has produced over one million ounces of gold to date and still has nearly
one million ounces of resources. This resource is expected to grow further following a major drilling programme this year which includes
deep drilling to help assess the potential for underground mining in the near future, where areas of high grade ore are known to exist. In
November 2005, the Company announced a significant increase in Penjom's life of mine plan to over half a million ounces, which resulted in
the design of a much larger pit to allow the additional ounces to be mined. Over the last year Penjom has expanded its mining and plant
capacity accordingly.  Avocet was able to overcome initial problems of highly carbonaceous ore at Penjom by developing unique processing systems including complex gravity circuits and
resin-in-leach (RIL) technology. These processes have potential applications at other carbonaceous orebodies.

    The North Lanut gold mine in North Sulawesi, Indonesia, was developed by Avocet from the exploration stage and has produced over 200,000
ounces since it was commissioned in 2004.  Recent high grade exploration drilling results indicate the potential for increases in resources
and mine life.  In 2002 Avocet purchased its 80 per cent interest in PT Avocet Bolaang Mongondow (PT ABM), an Indonesian company holding a
6th generation Contract of Work (CoW), from Newmont Mining Corporation. The North Lanut gold mine is located within the CoW, which includes
exploration and mining rights over approximately 50,000 hectares in an area highly prospective for gold. An Indonesian company, PT Lebong
Tandai, owns the remaining 20 per cent.


    Appendix 1 - Key operating statistics by quarter

                                                        FY2008                          
                                                                                                 FY2009
                                   Q1         Q2         Q3         Q4        Total          Q1         Q2
 Penjom                                                                                 
 Ore mined (tonnes)               155,794    160,625     59,842    185,006     561,267      179,034     86,082
 Waste mined (tonnes)           3,970,228  3,574,009  4,490,503  4,662,010  16,696,750    4,746,786  4,139,994
 Ore and waste mined (tonnes)   4,126,022  3,734,634  4,550,345  4,847,016  17,258,017    4,925,820  4,226,076
 Ore processed (tonnes)           140,185    150,974    151,386    153,600     596,145      190,516    179,059
 Average ore head grade (g/t)        5.62       4.67       4.26       4.87        4.84         3.44       3.53
 Process recovery rate                91%        92%        88%        89%         91%          89%        88%
 Gold Produced (oz)                23,069     20,895     18,253     21,507      83,724       18,729     17,793
                                                                                        
 Cash costs (US$/oz)                                                                    
 Mining                               188        230        260        283         238          329        313
 Processing                            86        100        117         88          97          155        168
 Royalties and overheads               76         71         86         81          78           91         95
                                      351        401        463        452         414          576        576
 Deferred stripping adjustment       (58)       (50)      (187)       (41)        (80)         (95)      (156)
                                      293        352        275        410         334          481        420
                                                                                        
 Mining cost per tonne (US$)         1.05       1.29       1.04       1.25        1.16         1.25       1.32
                                                                                        
 North Lanut                                                                            
 Ore mined (tonnes)               550,052    590,024    515,230    313,704   1,969,011      383,787    357,627
 Waste mined (tonnes)             337,962    238,830    283,722    283,982   1,144,496      220,408    305,008
 Ore and waste mined (tonnes)     888,014    828,854    798,952    597,686   3,113,507      604,195    662,635
 Ore processed (tonnes)           469,191    573,719    451,665    188,013   1,682,588      383,787    437,917
 Average ore head grade (g/t)        2.05       3.23       2.47       1.79        2.54         1.99       2.30
 Process recovery rate                51%        39%        58%       136%         54%          38%        31%
 Gold Produced (oz)                15,733     23,133     20,995     14,322      74,183        9,293      9,963
                                                                                        
 Cash costs (US$/oz)                                                                    
 Mining                               161        116        126        174         140          251        295
 Processing                            70         54         67         86          67          198        229
 Royalties and overheads               83         62         83        147          89          152        137
                                      314        232        276        407         295          601        661
                                                                                        
 Total continuing operations                                                            
                                                                                        
 Gold Produced (oz)                38,802     44,028     39,248     35,829     157,907       28,022     27,756
 Cash costs (US$/oz)                                                                    
 Mining                               177        170        188        239         192          303        307
 Processing                            80         76         90         87          83          169        190
 Royalties and overheads               79         66         84        108          83          112        110
                                      336        312        363        434         358          584        607
 Deferred stripping adjustment       (34)       (24)       (87)       (25)        (42)         (64)      (101)
                                      301        289        276        409         316          521        506


    Appendix 2 - Penjom Q2 waste and ore volumes

                                                                      Tonnes mined                                                          
              Bench Cubic Metres mined(1)
                                                            Q2 FY2009             Q2 FY2008              Variance                           
       Q2 FY2009             Q2 FY2008        Variance
 Waste                                                            4,139,994             3,574,009                   16%                     
             1,369,206             1,721,628      -20%
 Ore                                                                 86,082               160,625                  -46%                     
                31,883                59,486      -46%
 Total                                                            4,226,076             3,734,634                   13%                     
             1,401,089             1,781,114      -21%

 Mining cost per tonne/BCM       US$                                   1.32                  1.29                    3%                     
                  3.97                  2.67       49%

 Stripping ratio(1) (2)          x                                                                                                          
                  42.9                  28.9
 Life of mine stripping ratio    x                                                                                                          
                  20.2                  22.5
 Excess stripping ratio          x                                                                                                          
                  22.8                   6.4
 Excess waste stripping(3)       Million BCM                                                                                                
                   0.7                   0.4
 Excess stripping cost           US$m                                                                                                       
                   2.8                   1.0
 deferred(4)
                                 US$oz                                                                                                      
                   156                    49

 (1) Bench cubic metre (BCM) is a measure of volumes mined and is equal to the weight of rock (measured in tonnes) divided by its specific
gravity. BCM is used in mine planning where volumes are
 the key driver and it is necessary to avoid distortion due to differing specific gravities.
 (2) Ratio of waste to ore.
 (3) Represents the amount of waste BCM mined in the period in excess of the life of mine stripping ratio. Calculated as: excess stripping
ratio multiplied by ore BCM mined.
 (4) Represents cost of waste mining carried out as part of the long term pit expansion, rather than associated with the ore mined in the
period.  




This information is provided by RNS
The company news service from the London Stock Exchange
 
  END 
 
MSCQKLFLVBBFFBE

Avocet Mining (LSE:AVM)
過去 株価チャート
から 6 2024 まで 7 2024 Avocet Miningのチャートをもっと見るにはこちらをクリック
Avocet Mining (LSE:AVM)
過去 株価チャート
から 7 2023 まで 7 2024 Avocet Miningのチャートをもっと見るにはこちらをクリック