Bazalgette Finance PLC Strategy/Company/Ops Update (0472V)
2019年4月4日 - 4:00PM
RNSを含む英国規制内ニュース (英語)
TIDM38LO
RNS Number : 0472V
Bazalgette Finance PLC
04 April 2019
4 April 2019
Bazalgette Finance plc
SUPER SEWER NOW 40 PER CENT COMPLETE AS TIDEWAY REPORTS ON YEAR
OF PROGRESS
The company building London's new super sewer has completed 40
per cent of construction and is on track to deliver the project on
time in 2024.
As the 2018/19 financial year closes and with the first stages
of the project now complete, Tideway has updated its cost estimate
based on the work left to do.
The team has achieved complex engineering feats - building seven
new pieces of land in the Thames, including at Chelsea, Blackfriars
and Putney, and digging five giant shafts up to 50m deep below
London.
A workforce of more than 2,000, including miners from across the
world, are now tunnelling underground to create the 25km-long
tunnel. The first kilometre from Battersea to Chelsea was completed
at the end of March and two other huge tunnelling machines have
also started their journeys.
Five years since the project was given the green light Tideway
is now updating its estimate of overall costs based on work left to
do. With the first and most unpredictable phase of the project now
complete, the Company's revised estimate is GBP3.8bn compared to
GBP3.52bn (GBP3.14bn in 2014 prices) which represents an eight per
cent increase.
There will be no change to the estimated GBP20-25 annual cost
for Thames Water bill-payers, as costs remain well within the
original projection for customer charges. The company has already
raised enough money to complete the project and requires no further
funding as a result of this cost revision.
Andy Mitchell, Tideway's CEO said: "To build the super sewer we
are working in an unforgiving tidal river in the centre of one of
the busiest cities in the world. We have got train lines and
bridges above our heads, and the tube and utility pipes below our
feet.
"As we approach the half way point of construction, the time is
right to update our cost estimate. The most important thing to say
is that there will be no impact on the estimated cost to Thames
Water bill payers and to recognise that our teams have done a great
job in getting us this far and keeping us on schedule. Every day we
get closer to our aim of giving London a cleaner river."
The tunnel, which will run from Acton in west London to
Stratford in east London, will extend London's Victorian sewer
system, stopping millions of tonnes of raw sewage polluting the
Thames.
Construction is taking place at 23 sites across the city and
Tideway is using the river instead of roads as far as possible to
build the project, cutting the impact on road congestion and air
quality. By the end of April 2019, one million tonnes of material
will have been moved by river - keeping 60,000 HGV movements off
London's roads so far.
Earlier this year, Tideway announced it had avoided the need to
divert a Victorian gas main at Blackfriars, one of its most complex
sites. The diversion would have meant a closure of the Embankment
to traffic for up to six months. To avoid the diversion, Tideway
had to make fundamental changes to the construction methodology for
the site, adding costs to the original estimate.
At Tideway's King Edward Memorial Park site in Wapping the team
found difficult and unexpected ground conditions which meant they
have had to do significant work to reinforce the ground to make it
stable for construction, also adding cost.
Tideway also took the decision to reduce HGV movements, which
required additional investment in the infrastructure needed to move
materials by river, as well as investment in skills and jobs
through the new Thames Skills Academy. This will cut the number of
lorry movements by 360,000, reducing impacts on congestion and air
quality.
Tideway will publish its full annual report and accounts in
June. For more information, visit www.tideway.london
For further information, please contact:
investor.relations@tideway.london
press@tideway.london
Natalie Wheble 07789228900
Bazalgette Finance plc
Cottons Centre
Cottons Lane
London
SE1 2QG
This information is provided by RNS, the news service of the
London Stock Exchange. RNS is approved by the Financial Conduct
Authority to act as a Primary Information Provider in the United
Kingdom. Terms and conditions relating to the use and distribution
of this information may apply. For further information, please
contact rns@lseg.com or visit www.rns.com.
END
UPDEXLFBKZFXBBQ
(END) Dow Jones Newswires
April 04, 2019 03:00 ET (07:00 GMT)