TORONTO, Nov. 2, 2023
/PRNewswire/ - Denison Mines Corp. ('Denison' or
the 'Company') (TSX: DML) (NYSE American: DNN) is pleased to
announce the successful completion of the recovered solution
management phase of the Phoenix in-situ recovery ('ISR')
Feasibility Field Test ('FFT') at the Company's 95% owned
Wheeler River project ('Wheeler River' or the 'Project'). View PDF
version
The FFT was highlighted by the recovery of 14,400 lbs
U3O8 dissolved in solution generated
during the leaching and neutralization phases of the FFT in late
2022. The solution recovered during the operation of these phases
was stored on site in accordance with permit conditions and in
anticipation of the recovered solution management phase of the FFT.
This phase was initiated during the first half of 2023 and involves
the treatment of the recovered solution via an on-site
purpose-built treatment system. Following treatment, a uranium
bearing mineralized precipitate and a treated effluent were
produced. The treated effluent was tested to ensure compliance with
permit conditions before being injected into a designated
subsurface area. The mineralized precipitates have been recovered
from the process and are safely stored on surface in accordance
with permit conditions.
Kevin Himbeault, Denison's Vice
President Operations & Regulatory Affairs, commented, "The
completion of the recovered solution management phase of the FFT
has allowed Denison to demonstrate our operational
capabilities from start to finish of the ISR mining
process – from the construction and commissioning of
the FFT facilities and development of
the wellfield, to control of
mining solutions, recovery of uranium bearing solutions,
neutralization of the portion of the ore
zone used for the FFT, and finally the
treatment of solutions for safe discharge to the
environment and storage. We are proud of our
team of operators and technical personnel for the
safe execution of the entire FFT program."
Completion of the Recovered
Solution Management Phase
The recovered solution management phase of the FFT commenced in
April 2023 with the set-up and
commissioning of the solids management and water treatment circuit.
Approximately 560 m3 of
recovered solution plus wash water used for cleaning of storage
tanks and site equipment were processed during the operation of the
treatment circuit. Treatment of recovered solutions concluded in
October 2023, resulting in the safe
and successful treatment of all recovered solution, which ensured
compliance with all provincial permit conditions.
The approximately 14,400 lbs U3O8
estimated to be contained within the recovered solution from the
leaching and neutralization phases were precipitated during the
recovered solution management phase with over 99.99% efficiency,
further validating the Company's processing designs and
assumptions for the future Phoenix processing plant.
The treated effluent injected into the subsurface during the
recovered solution management phase was monitored for injection
pressure and contained to the designated injection area, with no
migration of the treated effluent observed above, below or outside
of the injection area.
Decommissioning of the Feasibility
Field Test Site
With the completion of the recovered solution management phase,
Denison has initiated decommissioning of the FFT facilities, in
accordance with its permit conditions. Decommissioning involves the
cleaning, deconstruction, and shipment of equipment used during the
leaching, neutralization, and solution management phases. Given the
expected onset of winter weather conditions, Denison expects
to complete the majority of the decommissioning of the FFT in
2024.
Northern Indigenous
Employment and Business Contributions
Denison is also pleased to recognize the significant
contributions of several members of the English River
First Nation ('ERFN') and various Indigenous owned businesses
to the successful completion of all the phases of the FFT
in 2022 and 2023. Tron Construction & Mining, a
well-established operator in northern Saskatchewan that is part of the Des Nedhe
Group and owned 100% by ERFN, and PBN Construction, a Northern
Saskatchewan Indigenous owned and operated
contractor, provided qualified support for commissioning,
maintenance, and decommissioning work throughout the various phases
of the FFT.
Feasibility Field Test
Background
The FFT was designed to use the commercial-scale ISR test
pattern, installed at the Phoenix
deposit in 2021 (see news releases dated July 29, 2021, and October
28, 2021), to facilitate a combined assessment of the
deposit's hydraulic flow properties and its leaching
characteristics previously determined through the metallurgical
core-leach testing program.
The operation of the FFT occurred in three phases: (1) the
leaching phase, (2) the neutralization phase, and (3) the recovered
solution management phase. The FFT is fully permitted, having been
authorized by both the Saskatchewan Minister of Environment (see news
release dated July 12, 2022) and the
Canadian Nuclear Safety Commission (see news release dated
August 8, 2022).
Overall, the FFT provided further verification of the
permeability, leachability, and containment parameters needed for
the successful application of the ISR mining method at Phoenix and validates and informs various
design elements – including the expected production and remediation
profiles reflected in the results announced from the Feasibility
Study for Phoenix during the
summer of 2023.
About Wheeler River
Wheeler River is the largest undeveloped uranium project in
the infrastructure-rich eastern portion of the
Athabasca Basin region, in
northern Saskatchewan. The project
is host to the high-grade Phoenix
and Gryphon uranium deposits, discovered by Denison in 2008 and
2014, respectively, and is a joint venture between Denison (90% and
operator) and JCU (Canada)
Exploration Company Limited (10%). In August 2023, Denison filed a technical report
summarizing the results of (i) the feasibility study completed
for ISR mining of the high-grade Phoenix uranium deposit and (ii) a cost update
to the 2018 Pre-Feasibility Study for conventional underground
mining of the basement-hosted Gryphon uranium deposit. Based
on the respective studies, both deposits have the potential to be
competitive with the lowest cost uranium mining operations in the
world. Permitting efforts for the planned Phoenix ISR
operation commenced in 2019 and have advanced significantly, with
licensing in progress and a draft Environmental Impact Statement
submitted for regulatory and public review in October 2022. More information is available in
the technical report titled "NI 43-101 Technical Report on the
Wheeler River Project Athabasca Basin, Saskatchewan, Canada" dated August 8, 2023 with an effective date of
June 23, 2023, a copy of which
is available on Denison's website and under its profile on
SEDAR+ at www.sedarplus.ca and on
EDGAR at www.sec.gov/edgar.shtml.
About Denison
Denison is a uranium exploration and development company with
interests focused in the Athabasca
Basin region of northern Saskatchewan,
Canada. In addition to the Company's effective 95% interest
in its flagship Wheeler River Uranium Project, Denison's interests
in Saskatchewan include a 22.5%
ownership interest in the McClean Lake Joint Venture, which
comprises several uranium deposits and the McClean Lake uranium
mill that is contracted to process the ore from the Cigar Lake mine
under a toll milling agreement, plus a 25.17% interest in the
Midwest Main and Midwest A deposits and a 67.41% interest in the
Tthe Heldeth Túé ('THT') and Huskie deposits on the Waterbury Lake
property. The Midwest Main, Midwest A, THT and Huskie deposits are
located within 20 kilometres of the McClean Lake mill.
Through its 50% ownership of JCU, Denison holds additional
interests in various uranium project joint ventures in Canada, including the Millennium project (JCU,
30.099%), the Kiggavik project (JCU, 33.8118%) and Christie Lake (JCU, 34.4508%).
Denison's exploration portfolio includes further interests in
properties covering ~285,000 hectares in the Athabasca Basin region.
Follow Denison on Twitter @DenisonMinesCo
Qualified Persons
The technical information contained in this release has been
reviewed and approved by Mr. Chad
Sorba, P.Geo., Denison's Director, Technical Services, who
is a Qualified Person in accordance with the requirements of NI
43-101.
Cautionary Statement Regarding
Forward-Looking Statements
Certain information contained in this news release
constitutes 'forward-looking information', within the meaning of
the applicable United States and
Canadian legislation, concerning the business, operations and
financial performance and condition of Denison. Generally,
these forward-looking statements can be identified by the use of
forward-looking terminology such as 'potential', 'plans',
'expects', 'budget', 'scheduled', 'estimates', 'forecasts',
'intends', 'anticipates', or 'believes', or the negatives and/or
variations of such words and phrases, or state that certain
actions, events or results 'may', 'could', 'would', 'might' or
'will' 'be taken', 'occur' or 'be
achieved'.
In particular, this news release contains forward-looking
information pertaining to the following: scope, objectives
and interpreted results of the FFT program and other
evaluation programs conducted with respect to the Phoenix deposit; permitting of
the FFT and the ability to satisfy permit conditions;
and expectations regarding its joint venture ownership
interests and the continuity of its agreements with its partners
and third parties.
Forward looking statements are based on the opinions and
estimates of management as of the date such statements are made,
and they are subject to known and unknown risks, uncertainties and
other factors that may cause the actual results, level of activity,
performance or achievements of Denison to be materially different
from those expressed or implied by such forward-looking statements.
For example, the modelling and assumptions upon which the plans for
Wheeler River are based may not be maintained after further work is
completed. In addition, Denison may decide or otherwise be required
to discontinue testing, evaluation and other
work if it is unable to maintain or otherwise secure the
necessary resources (such as testing facilities, capital funding,
regulatory approvals, etc.). Denison believes that the
expectations reflected in this forward-looking information are
reasonable but no assurance can be given that these expectations
will prove to be accurate and results may differ materially from
those anticipated in this forward-looking information. For a
discussion in respect of risks and other factors that could
influence forward-looking events, please refer to the factors
discussed in Denison's Annual Information Form dated March 27, 2023 or
subsequent quarterly financial reports under the heading 'Risk
Factors'. These factors are not, and should not be construed as
being exhaustive.
Accordingly, readers should not place undue reliance on
forward-looking statements. The forward-looking information
contained in this news release is expressly qualified by this
cautionary statement. Any forward-looking information and the
assumptions made with respect thereto speaks only as of the date of
this news release. Denison does not undertake any obligation to
publicly update or revise any forward-looking information after the
date of this news release to conform such information to actual
results or to changes in Denison's expectations except as otherwise
required by applicable legislation.
View original content to download
multimedia:https://www.prnewswire.com/news-releases/denison-announces-successful-completion-of-recovered-solution-management-phase-of-phoenix-isr-feasibility-field-test-301975387.html
SOURCE Denison Mines Corp.