DOW JONES NEWSWIRES 
 

The following table lists unplanned and planned production outages at U.S. refineries as reported by Dow Jones Newswires. The information is compiled from both official and unofficial refining sources and doesn't purport to be a comprehensive list.

Delek US Holdings (DK) on April 21 will begin the sequential restart of all processing units at its Tyler, Texas, refinery following a fatal fire and explosion on Nov. 20, 2008.

Total Petrochemicals USA (TOT) on April 20 restarted a steam boiler at its shuttered Port Arthur refinery; it was not clear whether the boiler restart signaled the start-up of other process units. The refinery has been shuttered for economic reasons since March 24.

ConocoPhillips (COP) on April 20 began four days of work at two FCCUs at its Borger, Texas, refinery to replace electronic cards associated with electrostatic precipitator rappers.

BP began work on April 20 at a key gasoline-making unit at its Texas City, Texas, refinery. FCCU 1 will undergo two days of maintenance on the Electrostatic Precipitator Stack starting at 8:00 a.m. on Monday. The work will not impact operations at the plant, a source familiar with operations said.

On April 17, Valero Energy Corp. (VLO) said it was planning maintenance on a hydrotreater at its Port Arthur, Texas, refinery. The company didn't specify when or how long the maintenance would last.

Planned work at ConocoPhillips' (COP) Wood River, Ill., refinery was completed late last week, the company said April 14. In an email, he said that planned maintenance is ongoing at the company's Billings, Mont., and San Francisco area refineries.

The Illinois refinery, which is a joint venture with EnCana Corp. (ECA), has a capacity of 306,000 barrels a day.

For more detailed information, search Dow Jones Newswires using the code N/REF.

 
 
Operator    Refinery    Capacity   Description                  Restart 
                        (in 000s 
                        bbl/day) 
 
EAST COAST 
 
Conoco      Linden        238.0  Reformer shut due to fire       Mar. 30 
            NJ                   on Mar. 21. Second fire 
                                 April 4, reduces rates. 
                                 Restart scheduled for 
                                 April 13.                      April 13 
 
Sunoco      Philadel-    335.0  10 workers hospitalized          n/a 
            phia, PA            Mar. 11 for evaluation after 
                                vapor release at alkylation 
                                unit. 
 
 
Valero      Delaware     210.0  Boiler system inspection and     May 3 
            City, DE            repair extends refinery down- 
                                time by one mo. to early May. 
                                Entire refinery shut Mar. 4 
                               for 30 days maintenance 
                                at coker unit which has been 
                                shuttered since Feb. 15. 
                                FCCU at reduced rates since      n/a 
                                mid-Dec. for economic reasons. 
 
CARIBBEAN 
 
 
GULF COAST 
 
Citgo      Corpus        156.0  April 11  power outage 
                                shuts West plant.                 April 14 
                                SRU restarted. Back to 
                                normal, Co. said April 14. 
 
Conoco     Belle Chasse  247.0  Power outage April 5            mid-April 
           La.                      shuts refinery 
 
 
 
Conoco      Borger, TX   152.0  Work will begin Mar. 27 to       Apr 
                                repair an air blower while       10 
                                FCCU No. 29 remains opera- 
                                tional. The unit may be shut 
                                if necessary. 
 
Conoco      Sweeny Tx    247.0  Fire partially shuts coker unit 
                                April 9th 
 
Delek US    Tyler, TX     60.0  Refinery to begin restart         Apr 21 
                                process on April 21 and will 
                                be fully operational in 7 to 10 
                                days. The refinery was shut 
                                on Nov. 20 following a fatal 
                                fire and explosion. 
 
Valero      Port Arthur  325.0  FCCU at reduced rates since       n/a 
            TX                  mid-Dec. for economic rea- 
                                sons. Shut hydrocracker for 
                                repairs April 3.                  Apr 10-13 
 
 
ROCKY MOUNTAINS 
 
Sinclair     Sinclair,   66.0   Refinery opps at 50%            mid-April 
             Wy                 after March fire. 
 
WEST COAST 
 
 
Flint       North Pole   210.0  One of three processing          n/a 
Hills                           units has been shut due 
                                to low jet fuel demand, 
                                the co. confirmed on Mar. 
                                19. 
 
PetroStar   Valdez, AK    48.0  Refinery shut due to Dec.        n/a 
                                28 fire. 
 
 
PLANNED 
 
CANADA 
 
North       Newfound-    115.0  Plantwide shutdown will begin    Early 
Atlantic    land                first week of April for 21       May 
                                days of planned maintenance. 
                                Upgrade work at hydrotreater 
                                will take an additional 14 
                                days. 
 
EAST COAST 
 
Conoco      Linden       238.0  145,000-b/d FCCU shut Feb.       April 3 
            NJ                  18 for about 45 days of 
                                planned turnaround mainte- 
                                nance. In Restart April 3. 
 
Sunoco      Philadelphia 330.0  Reformer unit shut in early      n/a 
            PA               Oct. for economic reasons. 
                                Shutdown to last one to six 
                                months. 
 
Valero      Delaware     210.0  82,000-b/d FCCU operating        n/a 
            DE                  at reduced rate for eco- 
                                nomic reasons, Co. said on 
                                Dec. 16. 
 
Valero      Paulsboro    160.0  27,000-b/d coker unit to        n/a 
            NJ                  shut in April for 35-days 
                                of planned work, the Co. 
                                said on Mar. 11. 
 
GULF COAST 
 
BP          Texas City   437.0  Ultraformer in restart Mar.      Mar. 26 
            TX                  23 following maintenance. 
 
Chevron     Pascagoula   330.0  Pre-commercial heavy oil         2010 
            Miss.               conversion project delayed 
                                from 2008 to 2010 due to 
                                economic factors. 
 
Citgo       Corpus       156.0  Restarted Scot Unit. 
            Christi, Tx 
 
 
Flint       Corpus       288.1  $250 mil. project for new        Spr 
Hills       Christi, TX         diesel desulfurization,          2010 
                                sulfur recovery unit to begin 
                                in Fall 2008. Construction 
                                to last 18 months. 
 
 
Marathon    Garyville    245.0  Project to increase crude oil    4Q 
            LA                  refining capacity by 180,000-    2009 
                                b/d expected to conclude in 
                                4th-quarter, 2009. 
 
Marathon    Texas City    76.0  Platformer and UDEX shut for     n/a 
            TX                  annual planned maintenance 
                                and catalyst change on Feb. 4. 
 
Total       Port Arthur  232.0  Key process units shut due       n/a 
                                to poor economic conditions 
                                on Mar. 24 
 
Valero      Corpus       340.0  20,000-b/d FCCU in East          n/a 
                                Plant shut; West Plant 
                                50,000-b/d FCCU at reduced 
                                rates since mid-Dec. for 
                                economic reasons. 
 
Valero      McKee, TX    170.0  Smaller of two crude units       May/ 
                                at 60,000-b/d to shut in         June 
                                May for 14 days; 55,000-b/d 
                                to shut in May for 21 days. 
 
Valero      Norco, LA    250.0  Upgrade project to build         2012 
                                a new diesel hydrotreater 
                                unit moved from 2010 to 
                                4th-quarter 2012, the Co. 
                                said on Jan. 27. 
 
Valero      Port Arthur  325.0  77,000-b/d FCCU at reduced       n/a 
            TX                  rates since mid-Dec. for 
                                economic reasons. A Hydrotreater 
                                was taken down for planned work 
                                April 17 
 
Valero      Sunray, TX   170.0  55,000-b/d FCCU at reduced       n/a 
                                rates since mid-Dec. for 
                                economic reasons. 
 
Valero      Three Rivers  95.0  24,000-b/d FCCU at reduced       n/a 
            TX                  rates since mid-Dec. for 
                                economic reasons. 
 
 
MID-WEST 
 
BP          Whiting,    410.0   Planned maintenane continues     End 
            IN         on Mar. 16 at the smaller of     Mar 
                                3 crude units. The work began 
                                in early March and is expected   Early 
                                to conclude by the end of the    Apr 
                                month or by early April. 
 
Frontier    El Dorado    130.0  Hydrotreater in restart and      Mar. 
            KS                  expected to produce product by   28-29 
                                Mar. 28-29, the Co. said. 
                                A coker turnaround and expan-    Mid-