IDM Mining Ltd. (TSX.V:IDM) (OTCQB:IDMMF) (“IDM”
or the “Company”) is pleased to provide an update on its Red
Mountain Gold Project (“Red Mountain” or the “Project”), located 15
km northeast of Stewart, BC. Since announcing a positive
feasibility study for a near-term, high-grade underground
bulk-mineable gold operation with low capital and operating costs
in June 2017, IDM has continued to advance engineering studies to
optimize potential production and development, as well as to
support Mines Act permitting through detailed engineering and
design. This work has been performed on all facets of the
project, including: mining, metallurgy and processing,
infrastructure, power, tailings and water management, geotechnical
and hydrology.
“The objective of our pre-development Value
Engineering work completed by our engineering team and
industry-leading consultants is to further enhance and optimize the
economics and proposed operations for a potential mine at Red
Mountain,” said Robert McLeod, President and CEO of IDM
Mining. “Coupled with the successful results from our 2017
resource expansion and exploration drilling program, we have
continued to add value to the Project while we progress through the
formal review phase of our Project Application and EIS.”
Key Project Highlights:
- Potential modifications to underground mine design, including:
run-of mine cemented backfill, decrease in the longhole stopes
footwall angles, and modified low-cost bulk mining techniques such
as the Holloway method.
- Currently performing additional metallurgical test work
including an alternative, modified flowsheet
(floatation-regrind-leach) and further fine-grinding studies.
- Completed a geotechnical Site Investigation (“SI”) drilling
program comprised of sixteen core holes during August and September
of 2017 to evaluate the geotechnical and hydrogeological conditions
at the Bromley Humps Tailings Management Facility (“TMF”), process
plant and topsoil stockpile locations. This SI program was to
meet detailed engineering requirements necessary for the Mines Act
permitting.
- Completed three geotechnical core holes at the proposed
secondary portal (“the Lower Portal”) location to meet detailed
engineering requirements necessary for Mines Act permitting.
- Completed a hydrotechnical assessment of Bitter Creek and
advanced the access road in-fill works and free-span bridge
crossings to a detailed design level.
- Completed a SI program, including geotechnical analysis for the
access and haul road alignment in support of detailed
engineering.
- Completed a soils, vegetation and construction materials
characterization program to meet detailed engineering requirements
necessary for Mines Act permitting.
- IDM entered into an agreement with BC Hydro to complete a
System Impact Study (“SIS”) to evaluate the proposed
interconnection point and energy demand.
“Following the delivery of our positive
Feasibility Study, IDM has completed all of the requisite
field-based technical work for Mines Act permitting and detailed
engineering,” said Ryan Weymark, VP Project Development of IDM
Mining. “We are focused on continuing to advance Project
Design and enhance the strong economics for the Red Mountain
Project in support of a potential construction decision in
2018.”
IDM retained Osisko Gold Royalties’ Technical
Services team to complete a review and provide recommendations of
major Project components during the Value Engineering phase, with
an emphasis on mining, metallurgy and processing, production rate
alternatives.
Red Mountain Project Update
i. Underground Mine Design
IDM has been reviewing potential refinements and
modifications to the Feasibility Study underground mine design
during this Value Engineering phase. Several changes could
potentially be made to optimize the mine design and reduce both
operating and sustaining capital costs, while reducing operation
risks. Potential refinements and modifications
include:
- Reducing longhole footwall angle from 55o to 43o to convert cut
& fill to longhole stopes, reducing operating costs and
sustaining capital;
- Eliminating the need to crush Cemented Rock Fill (“CRF”) and
utilize run-of-mine waste rock for CRF;
- Increasing the underground dewatering and pumping
infrastructure;
- Expanding critical components of underground mobile mining
fleet;
- Suggesting alternative mining methods for shallow-dipping, bulk
mineable mineralization (i.e. SAMSTM or Holloway mining technique)
as an alternative to cut and fill; and
- Optimizing longhole stope designs and mine scheduling.
The Company together with Mining Plus
Engineering Canada Ltd. has recently commenced work on detailed
engineering and design for the Lower Portal at Red Mountain.
ii. Power
IDM entered an agreement with BC Hydro in June,
2017 to complete a System Impact Study (“SIS”) to evaluate the
proposed interconnection point and peak load requirements for the
Red Mountain Project. The proposed mill and TMF location is
approximately 14 km to the east of the BC Hydro grid. IDM
expects to receive the SIS Technical Assessment in December, 2017,
and will then commence the Conceptual Design phase, which is
expected to be completed in Q1 2018. Following the completion
of the Conceptual Design, a Facility Impact Study will be
initiated. IDM has retained Allnorth Consultants Ltd. to
support with the BC Hydro studies.
iii. Access & Haul Road
IDM retained Onsite Engineering Ltd. (“Onsite”)
to advance the Access and Haul Road design to meet detailed
engineering requirements necessary for Mines Acts permitting.
Onsite completed a hydrotechnical assessment of Bitter Creek and a
SI program, including a geotechnical analysis of the road alignment
in July and October, 2017.
Onsite has advanced the Access Road detailed
design, including the Bitter Creek in-fill works and free-span
bridge crossings. The Access Road alignment follows an
existing road bed that was constructed in 1994 by Lac Minerals from
Highway 37A to the proposed mill and TMF location. This road
was washed out in areas during a 2011 storm event and is otherwise
overgrown with vegetation.
IDM has applied for a Project Review for the
Bitter Creek in-fill works through Fisheries and Oceans Canada
(DFO) as is legislated to determine if an Authorization is
required.
iv. Metallurgy & Processing
IDM’s team, together with Ausenco Engineering
Canada are managing further metallurgical testing and optimization
work. This includes evaluation of a potential alternative
flowsheet (floatation-regrind-leach) option, which will be compared
with the whole-ore leach process as recommended in the Feasibility
Study. In addition, further fine-grinding test work is being
completed to verify energy requirements and operational
costs. The objective of this work is to potentially improve
gold and silver recoveries and reduce capital and operating
costs.
v. Infrastructure
During the summer of 2017, IDM completed the
Plant Site and topsoil stockpile geotechnical Site Investigation
program that is required to advance foundation designs for Mines
Act permitting and detailed design.
IDM is currently optimizing the Mine Site
infrastructure location and layout to reduce footprint and the
impact associated with high levels of rain and snowfall that are
common in the Stewart area, as well as potentially reducing certain
components of capitals costs from the Feasibility Study
recommendations.
IDM retained Knight Piesold Ltd. (“KP”) to
complete additional terrain stability and rockfall hazard
assessment of the Bromley Humps area, which hosts the proposed
Plant Site and TMF, to meet Mines Act permitting and detailed
engineering requirements.
vi. Tailings and Water Management Design
IDM
completed a Geotechnical Site Investigation drilling program in
August and September of 2017 to evaluate the geotechnical and
hydrogeological conditions at the Bromley Humps TMF, Process Plant
and Topsoil Stockpile locations. Drilling was completed by
More Core Diamond Drilling Services Ltd., a local Stewart-based
company, and was designed and managed by KP to meet Mines Act
permitting and detailed engineering requirements.
KP has commenced work on the Site Water
Management, Sediment and Erosion Control Plan and design to support
early construction work (“ECW”) scopes.
IDM will be evaluating opportunities to increase
the existing TMF capacity in the coming months through completing
conceptual design to incorporate a potential extension to the mine
life.
vii. Underground Geotechnical and
Hydrogeology
The Company completed a three-hole geotechnical
drilling program at the proposed Lower Portal location to meet
Mines Act permitting and detailed engineering requirements.
In addition to the existing Marc Zone portal, this location would
serve as an additional underground entrance, provide access for
potential infill and resource expansion drilling of the 141 Zone
and serve as the main haulage ramp for potential mining.
IDM retained PHC Inc. (“PHC”) to advance the
underground geotechnical design and terrain stability assessments
for the Mine Site area to meet Mines Act permitting and detailed
engineering requirements. PHC is also supporting with the
development of geotechnical monitoring and management plans to
support Mines Act permitting and ECW.
SRK Consulting Inc. continues to support IDM
with the Mine Site hydrogeological and geochemical design in
support of Mines Act permitting and detailed design.
viii. 1,200 tpd Trade-Off Study
IDM is completing an internal trade-off study of
a potential 1,200 tonne-per-day (tpd) mining and processing
alternative, compared to the Feasibility Study design throughput of
1,000 tpd.
The 2017 Red Mountain Feasibility Study is
available for review on Sedar and at www.IDMMining.com. It
was prepared and led by JDS Energy & Mining Inc., in
collaboration with broad range of industry-leading consultants, all
Qualified Persons (“QPs”) under National Instrument 43-101.
About Red Mountain
The 17,125 hectare Red Mountain Gold Project is
located in northwestern BC, 15 km northeast of the Town of
Stewart. IDM recently announced the results of a Feasibility
Study for a high-grade, underground gold mine, which includes
primarily bulk underground mining methods and the production of
gold doré on site. The Project is advancing through the
provincial and federal environmental assessment processes, with
comprehensive, thorough, and ongoing consultation with Nisga’a
Nation. The Project is currently in the formal review phase
from the BC Environmental Assessment Office and the Canadian
Environmental Assessment Agency.
Additional information, including the Company’s
NI 43-101 Technical Reports for the Red Mountain gold project, is
available on the Company’s website and at www.sedar.com.
QA/QC AND QUALIFIED PERSONS
Ryan Weymark, P.Eng., Vice-President of IDM
Mining Ltd. is the Qualified Person (QP) responsible for the Red
Mountain Project Development. Rob McLeod, P. Geo, President
and CEO of IDM Mining Ltd. has reviewed and approved the technical
content of this release.
ABOUT IDM MINING LTD.
IDM Mining Ltd. is a mineral exploration and
development company based in Vancouver, BC, Canada. The
Company's current exploration and development activities are
focused on precious metals in British Columbia, with a primary
focus on the high-grade, underground Red Mountain Gold Project,
which is advancing through the BC and Canadian environmental
assessment processes.
ON BEHALF OF THE BOARDof IDM Mining Ltd.
“Robert McLeod”
President, CEO and Director
For more information, contact:
Robert McLeod604-681-5672604-617-0616
cellrm@idmmining.com
Investor Relations:Shobana
Thaya
st@idmmining.com416-807-1009
“Neither the TSX Venture Exchange nor its
Regulation Services Provider (as that term is defined in policies
of the TSX Venture Exchange) accepts responsibility for the
adequacy or accuracy of this release.”
Forward-Looking Statements:
Some statements in this news release contain forward-looking
information or forward-looking statements for the purposes of
applicable securities laws. These statements include, among
others, statements with respect to the proposed exploration and
development activities and their timing, resource estimates and
potential mineralization, the anticipated timing for completion of
a feasibility study for the Project. These statements address
future events and conditions and, as such, involve known and
unknown risks, uncertainties and other factors, which may cause the
actual results, performance or achievements to be materially
different from any future results, performance or achievements
expressed or implied by the statements. Such factors include,
among others and in addition to those described elsewhere in this
release, timing and success of future exploration and development
activities, exploration and development risks, delays in obtaining
or inability to obtain required government or other regulatory
approvals, permits or financing, the risk of unexpected variations
in mineral resources, grade or recovery rates, of failure of plant,
equipment or processes to operate as anticipated, of accidents,
labor disputes, and unanticipated delays in completing other
development activities, the risk that estimated costs will be
higher than anticipated and the risk that the proposed mine plan
and recoveries will not be achieved, equipment breakdowns and bad
weather, the timing and success of future exploration and
development activities, exploration and development risks, mineral
resources are not as estimated, title matters, third party
consents, operating hazards, metal prices, political and economic
factors, competitive factors and general economic conditions.
In making the forward-looking statements, the Company has applied
several material assumptions including, but not limited to, the
assumptions that: required regulatory approval, permits and
financing will be obtained; the proposed exploration and
development will proceed as planned; with respect to mineral
resource estimates, the key assumptions and parameters on which
such estimates are based; that the proposed mine plan and
recoveries will be achieved, that capital costs and sustaining
costs will be as estimated, and that no unforeseen accident, fire,
ground instability, flooding, labor disruption, equipment failure,
metallurgical, environmental or other events that could delay or
increase the cost of development will occur, and market
fundamentals will result in sustained metals and minerals
prices. The Company expressly disclaims any intention or
obligation to update or revise any forward-looking statements
whether as a result of new information, future events or otherwise
except as otherwise required by applicable securities
legislation.
Idm Mining Ltd (TSXV:IDM)
過去 株価チャート
から 11 2024 まで 12 2024
Idm Mining Ltd (TSXV:IDM)
過去 株価チャート
から 12 2023 まで 12 2024