Cariboo Gold Project
Brownfield Exploration
Barkerville’s 2017 Exploration program was
focused on it’s flagship Cariboo Gold Project located within
Central British Columbia. The company completed a 157,000
meter drilling campaign focused on resource delineation and
expansion drilling on Cow and Island Mountain, with the majority
focused on the Valley Zone and Shaft Zone. Significant
high-grade intercepts confirmed the mineralization model, grade
continuity, and geometries. Some significant recent drill
intercepts are as follows: 72.23g/t over 12.05m, 53.26g/t
over 11.55m, 18.84g/t over 30.85, 14.69 g/t over 28.5m, and 20.53
g/t over 11.6m. Barkerville was able to identify and
wire frame 145 vein corridors which will be the base for the
resource estimate in 2018.
Greenfield Exploration
Barkerville’s greenfield exploration team was
tasked with developing targets to the southeast of the of the
central project area along the 67 kilometers of strike within the
company’s Cariboo Gold Project. Systematic, scientific
exploration was able to identify 130 new targets through detailed
mapping, soil, and rock sampling. Eleven of these are now at the
drill ready stage.
Operations (Bonanza Ledge)
Portal and underground development began in the
second semester of 2017 at the Bonanza Ledge mine.
Barkerville completed 470 meters of underground development in
2017. Approximately 7000 tonnes of both low and high-grade
development material was processed at the company’s 100% owned QR
mill for commissioning and training purposes. The Mill will be
restarted in March 2018 when a sufficient stockpile is on site at
QR.
2018 Objectives
In 2018 the company is planning to undertake
several actions which are anticipated to be substantial
catalysts for Barkerville. We plan to publish an initial
resource for Cow Mountain, Island Mountain and Valley Zones as well
as an update for Barkerville Mountain,. Barkerville will
initiate drill testing of regional targets to confirm the
mineralization model and district scale upside. Bonanza Ledge
anticipates finishing development in Q1 with stope production to
follow. The company will also start its underground access, permit
depending, in order to explore for increased underground resources
at Cow and Island Mountain targets. This should reduce future
drilling cost and improve our understanding of the mineralization.
This underground access will also allow for trial stoping and bulk
sampling that will supply valuable data related to rock mechanics,
dilution, operating costs and processing.
Management Change
Effective March 1st, 2018, Maggie Layman,
currently Barkerville’s Exploration Manager, will replace Paul
Geddes as Vice President Exploration and QP for the Cariboo Gold
Project. Paul will be pursuing other opportunities in British
Columbia and the Company would like to thank him for his
contributions to the Cariboo Gold Project and wish him all the best
in his future endeavors.
Maggie has worked in mineral exploration with
several other Major and Junior companies managing Brownfields and
Greenfields gold and base metal exploration programs throughout
Canada since 2006. Maggie has worked for BGM since 2015 and is
responsible for directing the exploration programs at the Cariboo
Gold Project. She is an active volunteer with the Association of
Mineral Exploration Aboriginal Relations Committee. Maggie is
a graduate from Memorial University of Newfoundland Earth Science
program and is a P.Geo and member in good standing with APEGBC in
British Columbia. She is the Qualified Person (QP) for BGM in
accordance with National Instrument 43-101 Standards of Disclosure
for Mineral Projects.
For further information on Barkerville Gold
Mines Ltd. please contact:
Chris LodderPresident &
Chief Executive Officer155 University Avenue, Suite 1440Toronto,
Ontario, Canadaclodder@barkervillegold.com
About Barkerville Gold Mines
Ltd. (TSXV:BGM)
The Company is focused on developing its
extensive land package located in the historical Cariboo Mining
District of central British Columbia. Barkerville’s mineral tenures
cover 1,950 square kilometres along a strike length of 67
kilometres which includes several past producing hard rock mines of
the historic Barkerville Gold Mining Camp near the town of Wells,
British Columbia. The QR Project, located approximately 110
kilometres by highway and all weather road from Wells was acquired
by Barkerville in 2010 and boasts a fully permitted 900 tonne/day
gold milling and tailings facility. Test mining of the Bonanza
Ledge open pit was completed in March of 2015 with 91,489 tonnes of
material milled producing 25,464 ounces of gold. The Company has
completed several drilling and exploration programs over the past
20 years and has compiled this data with all historical information
in order develop geologic models which are assisting management in
defining new deposits in the Cariboo Gold Project. An extensive
drill program is currently underway with the goal of delineating
additional high grade gold mineralization.
Cautionary Statement on Forward -Looking
InformationNeither the TSX Venture Exchange (‘TSXV’) nor
its Regulation Services Provider (as that term is defined in the
policies of the TSXV) accepts responsibility for the adequacy or
accuracy of this release. No stock exchange, securities commission
or other regulatory authority has approved or disapproved the
information contained herein. This news release contains
forward-looking information which is not comprised of historical
facts. Forward-looking information involves risks, uncertainties
and other factors that could cause actual events, results,
performance, prospects and opportunities to differ materially from
those expressed or implied by such forward-looking information.
Forward looking information in this news release includes, but is
not limited to, the Company's objectives, goals or future plans,
statements regarding exploration results and exploration plans.
Factors that could cause actual results to differ materially from
such forward-looking information include, but are not limited to,
capital and operating costs varying significantly from estimates,
the preliminary nature of metallurgical test results, delays in
obtaining or failures to obtain required governmental,
environmental or other project approvals, uncertainties relating to
the availability and costs of financing needed in the future,
changes in equity markets, inflation, fluctuations in commodity
prices, delays in the development of projects and the other risks
involved in the mineral exploration and development industry, and
those risks set out in the Company's public documents filed on
SEDAR. Although the Company believes that the assumptions and
factors used in preparing the forward-looking information in this
news release are reasonable, undue reliance should not be placed on
such information, which only applies as of the date of this news
release, and no assurance can be given that such events will occur
in the disclosed time frames or at all. The Company disclaims any
intention or obligation to update or revise any forward-looking
information, whether as a result of new information, future events
or otherwise, other than as required by law.
Barkerville Gold Mines (TSXV:BGM)
過去 株価チャート
から 2 2025 まで 3 2025
Barkerville Gold Mines (TSXV:BGM)
過去 株価チャート
から 3 2024 まで 3 2025