$477 Million
pre-tax NPV5%; pre-tax IRR OF 37.3% (post-tax
$328 Million and 30.2%) at
US$1,600 per ounce gold
TSX: TML OTCQX:
TSRMF
Highlights (all currencies are reported in Canadian
dollars unless otherwise specified):
- LOW CAPITAL INTENSITY PROJECT WITH PRE-PRODUCTION CAPITAL COST
OF $233 MILLION AND PRE-TAX PAYBACK
PERIOD OF LESS THAN 2 YEARS
- ROBUST ECONOMICS WITH POST-TAX $328
MILLION NPV5%; IRR OF 30.2%; AT US$1,600 PER OUNCE GOLD
- MINE LIFE OF 13 YEARS, WITH AVERAGE ANNUAL GOLD PRODUCTION
DURING FIRST 9 YEARS OF 102,000 OUNCES AND TOTAL LOM RECOVERED GOLD
OF ~1.1 MILLION OUNCES
- WORLD-CLASS INFRASTRUCTURE INCLUDES EXISTING HYDRO POWER,
NATURAL GAS AND CP RAIL LINES PLUS TRANS-CANADA HIGHWAY
- BOARD APPROVAL TO ADVANCE THE PROJECT TO THE PRE-FEASIBILITY
STUDY STAGE
- LEVERAGE TO GOLD PRICE: $726
MILLION NPV5% PRE-TAX AT RECENT SPOT PRICE OF US$1,850 PER OUNCE GOLD
TORONTO, Feb. 2, 2021 /PRNewswire/ - Treasury
Metals Inc. (TSX: TML) (OTCQB: TSRMF) (Frankfurt: TRC1)
("Treasury" or the "Company") is pleased to announce
the results from a preliminary economic assessment ("PEA") for the
Company's Goliath Gold Complex ("GGC" or the "Project"), which
includes the Goliath, Goldlund and Miller deposits along a
prospective 65-kilometre trend in northwestern Ontario. The PEA, prepared by Ausenco
Engineering Canada Inc. ("Ausenco") in accordance with National
Instrument 43-101 ("NI 43-101"), demonstrates the potential to
develop a low-cost 5,000 tonnes per day ("tpd") combined open pit
and underground mining operation with strong economics and the
opportunity for significant benefit to the Company, Indigenous
Nations and local stakeholders.
"With the announcement of the PEA results today, combined with
receipt of the federal Environmental Assessment approval in 2019,
we have confirmed the Goliath Gold Complex has sufficient critical
mass and we expect Treasury Metals to become one of Ontario's next gold producers. Our robust base
case for the project supports a 13-year mine life with average
annual production of 102,000 ounces of gold for the first nine
years with a post-tax NPV of $328
million and IRR of 30.2%," said Jeremy Wyeth, President and CEO of Treasury
Metals. "The project is underpinned by a high-quality resource, and
we have taken a conservative approach to resource estimation, with
the total M&I ounces virtually unchanged from previous
estimates. We also see significant exploration potential across our
330-square-kilometre land package. In 2021, we are focusing on
in-fill and definition drilling to better define the resource,
while also initiating step-out drilling to test new targets around
both the Goliath and Goldlund deposits."
Treasury continues to advance Goliath Gold Complex through the
commencement of trade-off optimization studies as part of the
pre-feasibility level study work, baseline environmental work,
community engagement and other critical activities to the required
level to facilitate the provincial permitting process.
Goliath Gold Complex PEA Overview
The Goliath Gold Complex PEA was prepared by Ausenco in
collaboration with other technical consultants and the Company's
operations and exploration teams (see Qualified Persons section
below).
The PEA was prepared in accordance with National Instrument
43-101 and the technical report that summarizes the results of the
Goliath Gold Complex PEA will be filed on the Company's website and
on SEDAR (www.sedar.com) within 45 days of this news
release.
PEA Assumptions and Economic Results
General
|
Gold price
assumption
|
per
ounce
|
US$1,600
|
Exchange
Rate
|
($US:$CAD)
|
0.75
|
Economics
(pre-tax)
|
Net present value
(NPV 5%)
|
$
millions
|
$477
|
Internal rate of
return (IRR)
|
%
|
37.3%
|
Payback
(undiscounted)
|
Years
|
1.92
|
Average annual cash
flow*
|
$
millions
|
$74
|
Cumulative cash flow
(undiscounted)*
|
$
millions
|
$991
|
Economics
(post-tax)
|
|
|
Net present value
(NPV 5%)
|
$
millions
|
$328
|
Internal rate of
return (IRR)
|
%
|
30.2%
|
Payback
(undiscounted)
|
Years
|
2.17
|
Average annual cash
flow*
|
$
millions
|
$58
|
Cumulative cash flow
(undiscounted)*
|
$
millions
|
$775
|
Mining
|
|
|
Mine life
|
years
|
13.5
|
Total LOM recovered
gold
|
,000
ounces
|
1,064
|
Average annual mining
rate
|
million
tpa
|
1.8
|
Average annual gold
production, years 1-9
|
ounces/year
|
102,000
|
Peak gold production
in year 5
|
ounces
|
119,000
|
Gold Recovery
(LOM)
|
%
|
93.64%
|
Initial capital
costs
|
$
millions
|
$233
|
AISC**
|
US$ per ounce
Au
|
$911
|
*Cash flows during
operational period
|
**AISC includes cash
costs plus sustaining capital, closure cost and salvage
value
|
The PEA is preliminary in nature, includes inferred mineral
resources that are considered too speculative geologically to have
the economic considerations applied to them that would enable them
to be categorized as mineral reserves, and there is no certainty
that the PEA will be realized. Mineral resources that are not
mineral reserves do not have demonstrated economic viability.
Mining and Processing
The PEA considers a combined
open pit and underground mining operation utilizing the resources
from three different pit areas over the life of the mine. It is
envisioned that mining will be initiated at the Goliath project due
to both its proximity to the processing facility and its existing
federal EA approval. With significant environmental and baseline
work underway it has been assumed that mining at the Goldlund
deposit will follow the initial start of production by
approximately one year. The Goliath underground operations are
expected to begin development in year three with first underground
production to come in year four of the proposed mining operations.
Proposed open pit and underground mining is envisioned as being
conventional truck and loader/shovel and long hole stoping,
respectively.
The process plant will treat 1.8Mt of ore per year at an average
throughput of 4,875 tonnes per day with an availability of 92%. The
plant design includes a three-stage crushing circuit, ball mill,
gravity concentration, classification, standard leach and
Carbon-In-Leach (CIL) technology,
and detoxification before deposition into a Tailings Storage
Facility (TSF).
The process plant has been designed to realize an average
recovery of 95.7% of the gold sourced from Goliath, 91.9% sourced
from Goldlund, and 89.6% sourced from Miller over the life of the
project. Of this, the gravity circuit recovers 17%-44% of the gold
across the three different ore sources. Gold recovery has been
based on metallurgical test work completed on Goliath and Goldlund
material between 2011 and 2017 with the confidence in recoveries
reflecting the more extensive metallurgical work done at Goliath
compared to Goldlund and Miller. Metallurgical testing
planned for 2021 at Goldlund and Miller is expected to improve
recovery assumptions.
The Company will provide additional details related to Tailings
Management and Closure in the PEA report filed on SEDAR within 45
days.
Mining &
Processing Inputs
|
Mine life –
Total
|
years
|
13.5
|
Mining
Rate
|
|
|
Open Pit (Year 1-5
average)
|
tpd
|
45,000
|
Underground (Peak
production)
|
tpd
|
1,400
|
Open
Pit
|
|
|
Total Mill
feed
|
million
tonnes
|
21.0
|
Open Pit – gold
grade
|
g/t
|
1.17
|
Open Pit – silver
grade
|
g/t
|
0.80
|
Total
waste
|
million
tonnes
|
82.5
|
Total Material
Mined
|
million
tonnes
|
103.5
|
Open pit strip
ratio
|
waste:mill
feed
|
3.93
|
Underground
|
|
|
Total mill feed
(underground)
|
million
tonnes
|
3.0
|
Underground – stope
gold grade
|
g/t
|
3.67
|
Underground – silver
grade
|
g/t
|
9.05
|
Processing
|
|
|
Feed Rate
|
tpd
|
4,875
|
Total tonnes
processed
|
Million
tonnes
|
24.0
|
Mill head grade –
gold
|
g/t
|
1.47
|
Mill head grade –
silver
|
g/t
|
1.82
|
LOM gold
recovery
|
%
|
93.6%
|
LOM silver
recovery
|
%
|
60.0%
|
A mine plan summary is included in Appendix 1 at the end of this
news release.
Operating Costs
Mining costs for owner operated mining
were developed from first principles with local vendor quotations
and detailed haulage profiles. Process plant operating costs were
developed based on the labour requirements and calculated
consumption rates of reagents, consumable materials, and electrical
power associated with the plant equipment. Costing factors were
applied leveraging in-house data based on comparable gold milling
operations in Ontario. Processing
costs include plant maintenance and upkeep.
Operating Costs
(life of mine average)
|
Mining costs (open
pit)
|
$/t
mined
|
3.27
|
Mining costs (open
pit)
|
$/t
processed
|
16.95
|
Mining costs
(underground)
|
$/t
processed
|
70.31
|
Processing
costs
|
$/t
processed
|
11.37
|
G&A
costs
|
$/t
processed
|
2.28
|
Total site operating
costs
|
$/t
processed
|
40.70
|
Cash
Costs
|
Cash costs
(LOM)*
|
$/oz
Au
|
699
|
All-in sustaining
costs (LOM)**
|
$/oz
Au
|
911
|
*Cash costs consist
of mining costs, processing costs, mine-level general &
administrative expenses and refining charges and
royalties
|
**AISC includes cash
costs plus sustaining capital, closure cost and salvage
value
|
Initial and Sustaining Capital Costs
Initial capital
costs in the PEA are estimated to be $233
million including a contingency of 5% on mining equipment,
and 25% on all other direct costs, excluding pre-production
stripping. Life of mine sustaining capital is estimated at
$313 million, primarily for Goliath
underground development and TSF construction. A small sustaining
capital budget is allocated to the processing plant, with general
plant maintenance and upkeep accounted for in operating costs.
Initial Capital
Costs ($ millions)
|
Mining equipment and
infrastructure
|
$20
|
Pre-production
mining
|
$25
|
Processing
plant
|
$65
|
Site
infrastructure
|
$51
|
Project delivery,
owner's costs and other indirects
|
$43
|
Contingency
|
$30
|
Total Initial
Capital
|
$233
|
Sustaining Capital
Costs ($ millions)
|
|
Mining
equipment
|
$26
|
Underground mine
development
|
$136
|
Mining
infrastructure
|
$55
|
TSF
|
$71
|
Process plant
sustaining capital
|
$1
|
Site closure and
reclamation
|
$24
|
Total Sustaining
Capital
|
$313
|
Site closure and reclamation include final closure costs for the
Goliath, Goldlund and Miller projects. Costs address demolition of
facilities, placement of covers on the tailing facility and waste
rock storage areas, and revegetation of disturbed areas.
Economic Sensitivity to Gold Price
Sensitivities of
post-tax NPV and post-tax IRR to gold price per ounce are as
follows:
Gold
Price
US$/oz
|
Post-Tax
NPV(5%)
Base
Case
|
Initial
CAPEX
|
Total
OPEX
|
FX
|
(-25%)
|
(+25%)
|
(-25%)
|
(+25%)
|
(-25%)
|
(+25%)
|
$1,200
|
$47
|
$101
|
($8)
|
$170
|
($93)
|
$331
|
($163)
|
$1,400
|
$189
|
$244
|
$134
|
$308
|
$66
|
$513
|
($15)
|
$1,600
|
$328
|
$383
|
$273
|
$445
|
$208
|
$694
|
$102
|
$1,850
|
$498
|
$553
|
$443
|
$615
|
$381
|
$921
|
$243
|
$2,000
|
$600
|
$655
|
$545
|
$717
|
$484
|
$1,057
|
$326
|
Gold
Price
US$/oz
|
Post-Tax
IRR
Base
Case
|
Initial
CAPEX
|
Total
OPEX
|
FX
|
(-25%)
|
(+25%)
|
(-25%)
|
(+25%)
|
(-25%)
|
(+25%)
|
$1,200
|
9.3%
|
16.9%
|
4.4%
|
19.0%
|
0.0%
|
30.4%
|
0.0%
|
$1,400
|
20.7%
|
31.0%
|
14.3%
|
28.5%
|
11.3%
|
41.5%
|
3.5%
|
$1,600
|
30.2%
|
42.7%
|
22.4%
|
37.1%
|
22.5%
|
51.4%
|
14.1%
|
$1,850
|
40.7%
|
55.6%
|
31.3%
|
46.8%
|
34.0%
|
62.7%
|
24.6%
|
$2,000
|
46.4%
|
62.6%
|
36.2%
|
52.2%
|
40.2%
|
69.2%
|
30.1%
|
All-In-Sustaining-Cost*
All-in-sustaining costs
("AISC")* are built up as follows:
AISC US$ per ounce
of Au*
|
Operating
Cost
|
$688
|
Royalties
|
$16
|
Refining
Cost
|
$11
|
Silver
Credit
|
($16)
|
Subtotal Cash
Cost
|
$699
|
Sustaining
Capital
|
$204
|
Salvage
Value
|
($8)
|
Closure
|
$17
|
Total AISC
|
$911
|
Mineral Resource Estimate
The mineral resource
estimate for Goliath used as the basis for the PEA with an
effective date of December 16, 2020
was completed using a total of 726 surface drill holes with an
aggregated length of 238,036 metres and a total of 96,912 assays.
The QP responsible for the resource estimate is Pierre Desautels P.Geo of AGP Mining
Consultants.
For Goldlund, the mineral resource estimate with an effective
date of October 23, 2020 was
completed using a total of 176,498 metres of drill core and channel
samples entered as pseudo holes distributed in 856 surface drill
holes, 189 surface trench channel samples, 480 underground drill
holes, and 246 underground channel samples for a total of 114,102
gold assays. The QP responsible for the estimate is Chris Keech P. Geo. of CGK Consulting Services
Inc.
For Miller, the mineral resource estimate with an effective date
of October 26, 2020 was completed
using a total of 96 surface drill holes totalling 7,386 metres. Of
those, 26 intersected the mineralized domains and were used in the
resource estimate. The QP responsible for the estimate is
Paul Daigle P. Geo of AGP Mining
Consultants.
The table summarizes the resource estimate for all three
deposits. The material amenable to open pit extraction was reported
within Lerchs-Grossman optimized resource constraining shell, while
the material amenable to underground extraction was reported within
a 3-dimensional wireframe representing a likelihood of
being coherent mining shapes with reasonable prospect of being
accessed. Open pit resource constraining shell and underground
resource shapes were provided by AGP's Engineering team.
For the Goliath Deposit, a gold price of US$1,700 /ounce and a silver price of
US$23 /ounce was used for the cut-off
determination. For open pit resources, a cut-off of 0.25 g/t gold
was used. Resources below the open pit shell used a cut-off of 1.60
g/t gold to define possible underground resources. For the
Goldlund and Miller Deposits, a gold price of US$1,700 /ounce was used for the cut-off
determination. For open pit resources, a cut-off of 0.26 g/t gold
was used. Resources below the open pit shell at Goldlund used a
cut-off of 1.60 g/t gold to define possible underground
resources.
Deposit
|
Cut-off
Grade (g/t)
|
Quantity ('000 tonnes)
|
Grade Gold
(g/t)
|
Contained Gold
('000 oz)
|
Measured
Resources
|
Goliath Open
Pit
|
0.25
|
1,471
|
1.90
|
90
|
Goliath
Underground
|
1.6
|
98
|
4.84
|
16
|
Total
Measured
|
|
1,569
|
2.09
|
105
|
Indicated
Resources
|
Goliath Open
Pit
|
0.25
|
26,956
|
0.87
|
757
|
Goliath
Underground
|
1.6
|
2,592
|
3.16
|
263
|
Goldlund Open
Pit
|
0.26
|
24,300
|
1.07
|
840
|
Total
Indicated
|
|
53,848
|
1.07
|
1,860
|
Total Measured and
Indicated
|
|
55,417
|
1.10
|
1,965
|
Inferred
Resources
|
Goliath Open
Pit
|
0.25
|
5,644
|
0.65
|
76
|
Goliath
Underground
|
1.6
|
704
|
2.75
|
62
|
Goldlund Open
Pit
|
0.26
|
14,400
|
0.56
|
260
|
Goldlund
Underground
|
1.6
|
233
|
6.8
|
51
|
Miller Open
Pit
|
0.26
|
1,981
|
1.24
|
79
|
Total
Inferred
|
|
22,962
|
0.77
|
528
|
Note on Mineral
Resources:
|
(1) Mineral resources
are estimated in conformance with the CIM Mineral Resource
definitions referred to in NI 43-101 Standards of Disclosure for
Mineral Projects. This mineral resource estimate covers the Goliath
Deposit, the Goldlund Deposit and the Miller deposit.
|
(2) Mineral Resources
that are not Mineral Reserves do not have demonstrated economic
viability. The quantity and grade of the reported Inferred Mineral
Resources in this estimation are conceptual in nature and are
estimated based on limited geological evidence and sampling.
Geological evidence is sufficient to imply but not verify
geological and grade or quality continuity. For these reasons, an
Inferred Mineral Resources has a lower level of confidence than an
Indicated Mineral Resources and it is reasonably expected that the
majority of Inferred Mineral Resources could be upgraded to
Indicated Mineral Resources with continued exploration.
|
(3) Goliath: Mineral
resources are reported within an optimized constraining shell using
a gold price of US$1700/Oz and a Silver price of US$23/Oz and
recoveries of 95.5% for gold and 62.6% for silver and a base
mining, processing + G&A costs of $CDN18.68/tonne open pit,
$CDN93.54/tonne for underground.
Grades were estimated using 1.5-meter capped composites via
Ordinary kriging for the Main and C zones and inverse distance
cubed for all other zones.
|
(4) Goldlund: Mineral
resources are reported within an optimized constraining shell using
a gold price of US$1700/Oz and gold recovery of 89% and a mining
and processing + G&A costs of $CDN18.51/tonne open pit,
$CDN93.53/tonne for underground and $CDN2.71/tonne for base mill
feed cost.
Gold grades were estimated using 2.0 m capped composites within 9
mineralized zones using ordinary kriging.
|
(5) Miller: Mineral
resources are reported within an optimized constraining shell using
a gold price of US$1700/Oz and gold recovery of 89% and a mining,
base mill feed and G&A cost of US$21.22/tonnes.
Grades were estimated using 2.0 m capped composites within the
granodiorite domain using Inverse Distance Cubed
interpolation.
|
(6) Summation errors
may occur due to rounding.
|
Overall, a more conservative approach was taken to the mineral
resource estimation methodologies on all sites in anticipation of a
potential future mining and construction decision. For both Goliath
and Goldlund a probabilistic estimation approach was used to model
the gold and silver mineralization.
For Goliath, this differs from the previous mineral resource
estimate approach that used discrete wireframes created from both
geological contacts and drill assay results for the underground
model and wider wireframes for the open pit model. With the new
methodology, the entire mineralized corridor for the Main Zone and
C-Zone were wireframed conventionally and then, internally
sub-divided in a low grade, medium grade and high grade components
using a probabilistic approach. The resulting single model
respects the known geological information while ensuring that the
grade distribution is more representative of the field condition.
This has resulted in having a more conservative approach to
continuity of the mineralization in both the low grade (Open Pit)
and high grade (Underground) zones.
For Goldlund, the mineral resource estimation approach has
considered a more conservative treatment of unsampled historic
intervals to limit the influence of high-grade samples within the
mineralized zones. The Goldlund probability mineral resource
estimation approach has also revised the search strategy and
geological domains to ensure that the modelling better reflects the
controls on gold mineralization. This has resulted in a more
conservative mineral resource estimate with more tonnes at a lower
average grade above cut-off. Drilling is currently underway
that specifically targets areas that have insufficient drill hole
density with the goal of increasing the confidence in the
continuity and adding inferred mineral resources in those
areas.
The results of these updated resource estimates allow for a much
larger proportion of Measured and Indicated resources to be
included in the proposed mining plan. The following graph
shows the high proportion of Measured and Indicated resources
within the proposed mine plan. Additional exploration drilling is
currently ongoing that is anticipated to enhance resource
continuity based on this approach to previously assumed levels.
Further details on the mineral resource estimate will be
available in the technical report on www.sedar.com and on the
Company's website at www.treasurymetals.com.
Permitting and Approvals
The approach to environmental
permitting and approvals for the Goliath Gold Complex will be to
treat the Goliath, Goldlund and Miller deposits as three distinct
projects for provincial permitting, all being processed at the mill
facility within the existing federal EA approval for Goliath.
The schedule for permitting and approvals for the Goliath Gold
Project is more advanced than the schedule for Goldlund and Miller,
given that a Federal Environmental Assessment (EA) has already been
completed for this Project. Specifically, on August 19, 2019, Treasury Metals received Federal
Government approval under the Canadian Environmental Assessment
Act, 2012 for the Goliath Gold Project, with the Minister of
Environment and Climate Change Canada concluding that with
implementation of appropriate mitigation measures, the Project is
not likely to cause significant adverse environmental effects.
Therefore, following the release of the PEA, the Goliath Gold
Project may proceed directly into provincial permitting and other
environmental approvals using the updated proposed mining plan,
while additional baseline data collection will be completed for
Goldlund and Miller to support anticipated future provincial
approval processes. A full year of baseline data collection has
been completed for the Goldlund site and will continue throughout
the remainder of 2021 to support the anticipated future provincial
approval processes.
Opportunities
The PEA has outlined a number of
initiatives that may enhance the project which include:
- For Goldlund, 6,400 metres of additional infill drilling in
Zone 1 to confirm the continuity of high-grade mineralization and
convert indicated to measured mineralization; 29,000 metres of
additional infill drilling in Zones 2, 3, 4, 6, 8, and 9 to convert
inferred mineralization to indicated mineralization; and 7,200
metres of exploration drilling to confirm the northeast extensions
of Zones 1 and 4.
- For Goliath, the focus will be on converting the remaining
Inferred resources to the Indicated category in preparation for a
Pre-Feasibility Study. The proposed resource conversion program
consists of approximately 31,000 metres of additional drilling
across the full strike of proposed underground mine plan. A small,
limited drill program is also proposed for resource expansion
between covering a strike length of 200 metres on the eastern
portion of the deposit which could result in sufficient material
amenable to open pit extraction. This small program consists of
approximately 3,000 metres of additional drilling.
- Further metallurgical test work to increase gold recovery at
Goldlund and Miller.
- The use of mined out open pit areas provide an opportunity for
the storage of tailings and waste material. There is a
significant volume that could be utilized for storage on a long
term basis that would both reduce cost, and importantly provide an
opportunity to limit the footprint and volume of tailings stored
above surface.
- The transport of Goldlund mineralized materials represents a
significant cost that could be reduced by the use of ore sorting
technology. Goldlund material has been shown to be amenable
to such technology and prioritized for study.
- The optimization of transporting material from the Goldlund and
Miller sites to the Goliath Mill facility represents an opportunity
for reduced cost. Additional studies will be completed in the next
phase to better define the capital and operating costs of various
options including different trucking options and the use of
technologies such as Railveyor that provide efficient transport
options.
- Additional testing of the correlation of gold to silver at the
Goldlund and Miller deposits has the opportunity to add silver to
the resource if completed. The limited test data at the
Goldlund resource is not sufficient to be included as part of the
resource, but it should be noted that in this limited testing there
does appear to be silver associated with some samples. A more
fulsome assay program should be instituted to re-assay available
samples and include assaying for future drill programs to
investigate whether or not sufficient correlation is possible to
create a silver by product from mining.
Next Steps
The Company intends to immediately initiate
trade-off and optimization studies as part of a formal
Pre-Feasibility Study, baseline environmental work, and other
critical studies with a view to completing all required engineering
work to facilitate the provincial permitting process later this
year. Engagement with local communities and Indigenous Nations will
also continue throughout the year.
In addition, the Company will continue exploration drilling at
the Goldlund deposit totalling approximately 42,000 metres, which
will include both infill and definition drilling, as well as
additional drilling at the Miller deposit. The Company intends to
mobilize a second drill at the Goliath deposit in the spring to
conduct infill and definition drilling totalling approximately
27,000 metres in order to explore targets at depth and along strike
which are outside the existing resource. Contingent on the success
of the drill program and market conditions, the Company may
consider mobilizing a third exploration drill.
Qualified Persons
The PEA for the Treasury
Metal Goliath Gold Complex summarized in this news release was
completed by Ausenco together with other technical consultants and
will be incorporated in a NI 43-101 technical report which will be
available under Treasury's SEDAR profile at www.sedar.com, and on
the Treasury website at www.treasurymetals.com within 45 days of
this news release. The affiliation and areas of
responsibility for each of the Qualified Persons involved in
preparing the PEA, upon which the technical report will be based,
are as follows: Mr. Tommaso Roberto
Raponi, P.Eng – Qualified Person for Processing and
Metallurgy; Mr. Pierre Desautels,
P.Geo. – Qualified Person for Goliath Mineral Resource Evaluation;
Mr. Christopher Keech, P.Geo –
Qualified Person for Goldlund Mineral Resource Evaluation;
Mr. Paul Daigle, P.Geo – Qualified
Person for Miller Resource Evaluation; Mr. Gordon Zurowski, P.Eng – Qualified Person for
Mine Engineering and Costing; Reagan
McIsaac, Ph.D., P.Eng. – Qualified Person for Tailings
Management; Sheila Daniel, P.Geo. –
Qualified Person for Closure and Closure Costing,
By virtue of their education, membership to a recognized
professional association and relevant work experience, Mr.
Tommaso Roberto Raponi, Mr.
Pierre Desautels, Mr. Christopher Keech, Mr. Paul Daigle, and Mr. Gordon Zurowski, are independent Qualified
Persons as defined under NI 43-101.
Data Verification
The Qualified Persons responsible
for the preparation of the PEA and the technical report in respect
thereof have verified the data disclosed in this news release,
including sampling, analytical, and test data underlying the
information contained in this news release. Geological, mine
engineering and metallurgical reviews included, among other things,
reviewing mapping, core logs, and re-logging existing drill holes,
review of geotechnical and hydrological studies, environmental and
community factors, the development of the life of mine plan,
capital and operating costs, transportation, taxation and
royalties, and review of existing metallurgical test work. In the
opinion of the Qualified Persons, the data, assumptions, and
parameters used to estimate Mineral Resources, the metallurgical
model, the economic analysis, and the PEA are sufficiently reliable
for those purposes. The technical report in respect of the PEA,
when filed, will contain more detailed information concerning
individual responsibilities, associated quality assurance and
quality control, and other data verification matters, and the key
assumptions, parameters and methods used by the Company.
Mark Wheeler, P.Eng., Director,
Projects, and Adam Larsen,
Exploration Manager, are both considered as a "Qualified Person"
for the purposes of National Instrument 43-101 Standards of
Disclosure for Mineral Project ("NI 43-101"), and have
reviewed and approved the scientific and technical disclosure
contained in this news release on behalf of Treasury.
Twitter @TreasuryMetals
About Treasury Metals Inc.
Treasury Metals Inc. is a
gold focused company with assets in Canada. Treasury's Goliath Gold Complex, which
includes the Goliath, Goldlund and Miller deposits along a
65-kilometre trend, is located in Northwestern Ontario. The deposits benefit
substantially from excellent access to the Trans-Canada Highway,
related power and rail infrastructure, and close proximity to
several communities including Dryden and Sioux
Lookout, Ontario. The Company also owns several other
projects throughout Canada,
including the Lara Polymetallic Project, Weebigee-Sandy Lake Gold
Project JV, and grassroots gold exploration property Gold Rock.
To view further details about Treasury, please visit the
Company's website at www.treasurymetals.com.
About Ausenco
Ausenco is a global company based
across 26 offices in 14 countries, with projects in over 80
locations worldwide. Combining deep technical expertise with a
30-year track record, Ausenco delivers innovative, value-add
consulting studies, project delivery, asset operations and
maintenance solutions to the mining & metals, oil & gas and
industrial sectors.
Forward-Looking Statements
This news release
contains information and projections that constitute
"forward-looking statements" under applicable securities
laws. All statements in this release, other than statements of
historical facts, that address events or developments that
management of the Company expect, are forward-looking statements.
Forward-looking statements are frequently, but not always,
identified by words such as "expects", "anticipates", "believes",
"plans", "projects", "intends", "estimates", "envisages",
"potential", "possible", "strategy", "goals", "objectives", or
variations thereof or stating that certain actions, events or
results "may", "could", "would", "might" or "will" be taken, occur
or be achieved, or the negative of any of these terms and similar
expressions. Forward-looking information in this news
release includes, but is not limited to statements regarding: the
Company's expectations relating to the development of the Goliath
Gold Complex, including, without limitation, the anticipated mine
life and annual gold production of any mine to be developed, the
ability of the Company to implement a "hub and spoke" regional
production strategy, the anticipated operating costs, initial and
sustaining capital costs, all-in sustaining costs, closure costs
and post-tax NPV and IRR of any such development, the processing
methodologies expected to be used in connection with any such
development and the gold recovery of such processing methodologies;
the economics and benefit to the Company, Indigenous Nations and
local stakeholders that would result from any such development; the
mineralization of the Goliath Gold Complex; the exploration
potential across the Company's 330 square-kilometre land package
and the results of future exploration activities thereon;
expectations regarding the Company's ability to expand its resource
in parallel with development; the approach to permitting that will
be taken by the Company with respect to the Goliath Gold Complex
and the timing of receiving all necessary permits; expectations
regarding future work anticipated to be completed on the Goliath
Gold Complex, including, without limitation, trade-off and
optimization studies, baseline environmental work, exploration
drilling and other critical studies and the anticipated timing
thereof; expectations regarding the timing of the Company
progressing to the feasibility stage with respect to its evaluation
of the Goliath Gold Complex; expectations regarding the initiatives
suggested by the PEA that might enhance the Goliath Gold Complex
project, including, without limitation, additional infill drilling,
further metallurgical testing work, the use of mined out open pit
areas for the storage of tailings material, the use of ore sorting
technology, the optimization of transporting material from the
Goldlund and Miller sites to the Goliath Mill facility, additional
testing of the correlation of gold to silver at the Goldlund and
Miller deposits and the review of locating the process plant and
tailings storage facility on the Goldlund property. Actual results
or developments may differ materially from those described in or
implied by the forward-looking statements contained herein.
Treasury disclaims any intention or obligation to update or revise
any forward-looking statements, whether as a result of new
information, future events or otherwise, save and except as may be
required by applicable securities laws.
Forward-looking statements in this news release reflect the
Company's views with respect to future events and are necessarily
based upon a number of assumptions and estimates that, while
considered reasonable by management, are inherently subject to
significant business, economic, competitive, political and social
uncertainties and contingencies. Many factors, both known and
unknown, could cause actual results, performance or achievements to
be materially different from the results, performance or
achievements that are or may be expressed or implied by the
forward-looking statements contained in this presentation and the
Company has made assumptions and estimates based on or related to
many of these factors. Such factors include, but are not limited
to: the risk of that the assumptions underlying the PEA and the
Company's financial projections, including, without limitation,
assumptions relating to the price of gold and the exchange rate
from USD to CAD, are inaccurate; the risk that that the results of
the Company's exploration of the Goliath Gold Complex to date does
not an accurately reflect of the mineralization of the Goliath Gold
Complex; the risk that the Company with not be able to undertake
all planned development and permitting activities in a manner
consistent with its expectations and without material delay; the
risk that the Company will not be able to maintain all necessary
existing permits; the fact that mineral reserve and mineral
resource figures relating to the Goliath Gold Complex are only
estimates and are subject to revision based on developing
information; health, safety and environmental risks; the risk that
the Company will not have to resources to finance the development
of the Goliath Gold Complex as contemplated or at all;
uncertainties related to negotiations with contractors and other
material parties in connection with the development of the Goliath
Gold Complex; risks associated with the mining industry, including
operational risks in exploration and development as a result of the
COVID-19 pandemic; and such additional risks listed under the
heading "Risk Factors" in the Company's Annual Information Form
dated March 27, 2020 and in other
filings of the Company with securities and regulatory authorities
which are available on SEDAR at www.sedar.com.
Should one or more of these risks or uncertainties
materialize, or should assumptions underlying the forward-looking
statements prove incorrect, actual results, performance or
achievements could vary materially from that expressed or implied
by the forward-looking statements contained herein. Readers are
cautioned not to place undue reliance on the forward-looking
information.
Appendix 1
Mine Plan Summary
|
Total
|
Total
|
Year
-1
|
Year
1
|
Year
2
|
Year
3
|
Year
4
|
Year
5
|
Year
6
|
Year
7
|
Year
8
|
Year
9
|
Year
10
|
Year
11
|
Year
12
|
Year
13
|
Year
14
|
Mill
Feed
|
Mill Feed
(Kt)
|
23,966
|
-
|
1,530
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
1,800
|
836
|
Au (g/t)
|
1.47
|
-
|
2.37
|
1.93
|
1.76
|
1.98
|
2.16
|
2.09
|
1.78
|
1.61
|
1.60
|
1.13
|
0.52
|
0.45
|
0.41
|
0.41
|
Ag (g/t)
|
1.82
|
-
|
1.5
|
1.6
|
-
|
1.3
|
4.0
|
3.0
|
2.7
|
2.7
|
2.1
|
2.5
|
0.1
|
0.6
|
1.7
|
1.7
|
Goliath Mill
Feed
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Open
Pit
|
Mill Feed
(Kt)
|
6,099
|
|
301
|
353
|
-
|
26
|
602
|
197
|
-
|
-
|
-
|
1,314
|
-
|
670
|
1,800
|
836
|
|
Au (g/t)
|
0.97
|
|
3.22
|
2.98
|
-
|
2.74
|
2.21
|
1.33
|
-
|
-
|
-
|
0.66
|
-
|
0.41
|
0.41
|
0.41
|
|
Ag (g/t)
|
2.77
|
|
7.80
|
7.98
|
-
|
10.50
|
4.36
|
2.97
|
-
|
-
|
-
|
2.05
|
-
|
1.68
|
1.68
|
1.68
|
Underground
|
Mill Feed
(Kt)
|
2,965
|
|
-
|
-
|
-
|
181
|
450
|
511
|
511
|
511
|
501
|
283
|
18
|
-
|
-
|
-
|
|
Au (g/t)
|
3.67
|
|
-
|
-
|
-
|
3.31
|
3.62
|
4.22
|
4.04
|
3.32
|
3.27
|
3.56
|
4.92
|
-
|
-
|
-
|
|
Ag (g/t)
|
9.05
|
|
-
|
-
|
-
|
11.14
|
10.27
|
9.32
|
9.34
|
9.45
|
7.60
|
6.61
|
8.37
|
-
|
-
|
-
|
Goldlund
Mill Feed
|
Mill Feed
(Kt)
|
13,590
|
|
1,229
|
1,447
|
1,800
|
1,593
|
749
|
925
|
1,171
|
1,111
|
1,085
|
36
|
1,782
|
662
|
-
|
-
|
|
Au (g/t)
|
1.25
|
|
2.16
|
1.68
|
1.76
|
1.82
|
1.24
|
1.22
|
0.78
|
0.78
|
0.78
|
0.77
|
0.48
|
0.48
|
-
|
-
|
|
Ag (g/t)
|
-
|
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
Miller Mill
Feed
|
Mill Feed
(Kt)
|
1,312
|
|
-
|
-
|
-
|
-
|
-
|
167
|
118
|
178
|
214
|
168
|
-
|
468
|
-
|
-
|
|
Au (g/t)
|
1.16
|
|
-
|
-
|
-
|
-
|
-
|
1.32
|
1.91
|
1.92
|
1.85
|
0.76
|
-
|
0.46
|
-
|
-
|
|
Ag (g/t)
|
-
|
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
-
|
View original content to download
multimedia:http://www.prnewswire.com/news-releases/treasury-metals-announces-positive-preliminary-economic-assessment-for-goliath-gold-complex-301220051.html
SOURCE Treasury Metals Inc.