FOR:  BEMA GOLD CORPORATION

TSX, AMEX SYMBOL:  BGO
AIM SYMBOL:  BAU

December 6, 2005

Bema Signs Loan Agreements for Up to US$425 Million for Kupol Mine Construction

VANCOUVER, BRITISH COLUMBIA--(CCNMatthews - Dec. 6, 2005) - Bema Gold Corporation (TSX:BGO)(AMEX:BGO)(AIM:BAU)
("Bema" or "the Company") is pleased to announce that Chukotka Mining and Geologic Corporation ("CMGC") (owned
75% by Bema and 25% by the Government of Chukotka) has signed loan agreements for up to US$425 million of
financing for the construction of the Kupol Mine. The loans consist of a Project Loan for up to US$400 million
and a Corporate Loan for CMGC of US$25 million.

The Project Loan consists of two tranches. The first tranche is for US$250 million and is fully underwritten by
the Mandated Lead Arrangers, Bayerische Hypo- und Vereinsbank AG ("HVB") and Societe Generale Corporate &
Investment Banking ("SG CIB"). The second tranche for US$150 million is from a group of multilateral and
industry finance institutions, of which the Mandated Lead Arrangers is comprised of Caterpillar Financial SARL
("Caterpillar"), Export Development Canada ("EDC"), International Finance Corporation ("IFC") and Mitsubishi
Corporation ("Mitsubishi"). Both tranches of the Project Loan will be administered by HVB, as Documentation and
Facility Agent, and SG CIB, as Technical and Insurance Agent.

The US$250 million tranche will have a six and a half year term from drawdown, and the US$150 million tranche
will have a seven and a half year term. The Project Loan is secured against the Kupol Mine and will be
guaranteed by Bema until economic completion is achieved.

As part of the project equity contribution, CMGC has signed a subordinated loan for Kupol with the IFC for
US$25 million. This facility, which will be non-recourse to Bema, will have an eight and a half year term from
drawdown. As part of the loan agreement, Bema will issue 8.5 million share purchase warrants to the IFC, each
warrant entitling the IFC to purchase one common share of Bema at a price of US$2.94 per share. Proceeds from
the exercise of the warrants will be used to repay the loan.

The cost for the construction of the Kupol Mine (not including certain prior equity expenditures) is estimated
at US$470 million and includes pre-production capital costs, working capital, financing fees and costs,
interest and taxes. The breakdown of funding is as follows: of the US$400 million Project Loan, US$380 million
is available to fund construction and US$20 million is set aside for contingencies; of the IFC Corporate Loan,
US$19.5 million will be contributed towards construction costs and US$5.5 million will be set aside for
interest payments. Bema's remaining equity contribution to the project will be approximately US$53 million and
the Government of Chukotka will be responsible for contributing approximately US$18 million of equity. Bema's
equity will be funded from a portion of the US$120 million equity financing completed on October 5, 2005.

Drawdown of the Project Loan and IFC Corporate Loan is expected in the first quarter of 2006. The material
conditions precedent for drawdown are final construction permits for Kupol (expected in early 2006) and equity
contributions from Bema and the Government of Chukotka.

HVB has also agreed to provide, at Bema's option, a US$17.5 million cost overrun facility in addition to the
Kupol Project Loan. In the event that Bema wishes to drawdown under this facility, the Company will issue to
HVB convertible unsecured notes with a seven year term from drawdown. The conversion price of the notes will be
a 35% premium to Bema's average share price in the 20 trading days following the initial drawdown of the
Project Loan.

Bema has completed a feasibility study for the Kupol project, demonstrating that it is technically feasible and
can be developed as a high grade, low cost gold and silver mine with robust project economics. The main
construction years at Kupol will be 2006 and 2007. Bema is currently on budget and on schedule to commence
production in mid 2008.

Endeavour Financial International Corporation acted as the financial advisor to Bema, and will receive a fee
for providing assistance in structuring, sourcing, negotiation and closing of the Project Financing.

On Behalf of Bema Gold Corporation

Clive Johnson, Chairman, CEO, President

For information on Bema Gold Corporation please visit our website at www.bema.com or contact Investor
Relations:

Some of the statements contained in this release are forward-looking statements, such as estimates and
statements that describe the Company's future plans, objectives or goals, including words to the effect that
the Company or management expects a stated condition or result to occur. Since forward-looking statements
address future events and conditions, by their very nature, they involve inherent risks and uncertainties.
Actual results in each case could differ materially from those currently anticipated in such statements.

-30-

FOR FURTHER INFORMATION PLEASE CONTACT:

Bema Gold Corporation
Ian MacLean
Manager, Investor Relations
(604) 681-8371
investor@bemagold.com

OR

Bema Gold Corporation
Derek Iwanaka
Investor Relations
(604) 681-8371
investor@bemagold.com
www.bemagold.com

The Toronto and American Stock Exchanges neither approve nor disapprove the information contained in this News
Release.

-0-

                                                                
Bema Gold Corporation



                                                                

Bema Npv (LSE:BAU)
過去 株価チャート
から 12 2024 まで 1 2025 Bema Npvのチャートをもっと見るにはこちらをクリック
Bema Npv (LSE:BAU)
過去 株価チャート
から 1 2024 まで 1 2025 Bema Npvのチャートをもっと見るにはこちらをクリック