TIDMANGM

RNS Number : 1511L

Angel Mining PLC

31 August 2012

ANGEL MINING PLC ("Angel Mining" or the "Company")

(AIM: ANGM)

2012 ANNUAL REPORT AND ACCOUNTS

Angel Mining announces the publication of its Annual Report and Accounts for the year ended 29 February 2012.

Highlights:

-- Commenced gold production at Nalunaq in May 2011 with commercial production expected during the third quarter of 2012, following recent receipt from the Bureau of Minerals and Petroleum of the new permit for partial mining of pillars.

-- Achieved first gold sale in August 2011 and by 31 July 2012 had sold 7,569 ounces of gold at an average price of $1,668 per ounce.

-- Continued development of the Black Angel zinc/lead mine and completed the construction of the cable car, subject to final commissioning.

Chairman's Report

OVERVIEW

There is no doubt that the last year has seen some major operational challenges for the Company, most of which, aside from the issues of funding, have now been overcome as discussed further in the CEO's report. Dealing with these issues has resulted in a weak share price and more equity dilution for shareholders than any of us would have liked. In the larger scheme of things, however, we must keep our eyes on the major prize, which is the Black Angel zinc and lead mine, and our target is to have this operational by 2014/15. Meanwhile, we expect the Nalunaq gold mine to produce enough gold, not only to make it a profitable exercise in its own right, but also to assist in the funding of the development of Black Angel. We will, of course, also need to tap both the equity and debt markets to fund the Black Angel project as is outlined below in the CEO's report. I think it fair to say that morale in the Company is generally high and we are looking forward to a period of steady gold production after all the problems encountered in the past year or so. Finally, I would like to add that both management and employees have done an extraordinary job of keeping the business afloat during this very difficult period and my heartfelt thanks go out to them all.

FOUNDATIONS

The Company is working to build a successful mining operation in Greenland where it is still the only company with active mining activities. It is learning how to deal with the challenge of working in a remote Arctic location and, during the year under review, it achieved some important milestones.

The main operation currently is the Nalunaq gold mine in southern Greenland. In May 2011, we commenced commissioning gold production using the world's first underground cyanide leaching plant. The Company is yet to reach and sustain commercial production and as such no sales revenue has been recognised during the year, as discussed further in the Financial Review section of the CEO's report. Commercial production is expected during the third quarter of 2012. The plant's cyanide leaching design aimed to achieve the highest level of environmental protection and it has proved to be a great success as the cyanide content of water leaving the mine is less than two parts per million, which is within the World Health's recommended standard for safe drinking water. The mine and process plant is capable of producing between 1,500 and 2,000 ounces of gold per month. Now that the major operational issues with the plant have been resolved, the remaining obstacle to achieving commercial production was permission to mine pillars which is needed to ensure that this target can be regularly achieved going forward. This vital permit has now been issued by the Bureau of Minerals and Petroleum (the "BMP") and the mining of pillars will commence immediately. The known resource base, including the pillars, should support this level of output for at least a further eighteen months and it is hoped that planned underground exploration will extend the operating life. Based on our experience to date, the cash cost of an ounce of gold should be approximately $800 at an average production rate of 1,750 ounces per month. It is also interesting to note that further exploratory work is planned to see if evidence can be found for any other veins of gold impregnated quartz in the same mountain.

The Company's main project is the Black Angel zinc/lead mine, which is located some 900 kilometers further north. It is a high grade, high quality deposit with a resource potential that exceeds seven million tonnes of ore, of which 4.425 million tonnes can be measured on a JORC compliant basis. The current feasibility study is based on an annual production of approximately 80,000 tonnes of concentrate a year. The resource base, as it is currently understood, can support this level of production for approximately 25 years. The adit access to the mine is 600 metres above sea level, entering a mountain made of white marble, which is separated from the base camp by a 1.7 kilometres wide fjord. A cable car has been constructed to facilitate access to the mine and this work was completed in October 2011, subject to final commissioning. Commissioning will take place once the Company is ready to commence construction of the mine infrastructure and the process plant which it also plans to build underground. The development of the mine and process plant is, of course, subject to the Group securing funding.

FINANCIAL RESULTS

The loss for the year was $5,534,000, compared to a loss of $7,773,000 for the same period last year. At 29 February 2012, the Group's cash and bank balances amounted to $667,000 compared to $441,000 at 28 February 2011. The financial results for the year, and the accounting treatment of sales during the period, are described in more detail in the financial review found in the CEO's Report.

MARKETS

Since Nalunaq commenced commissioning production in May 2011, the price of gold has fluctuated between a high of $1,898 and a low of $1,487. Between our first shipment in August 2011 and 31 July 2012, the Company sold 7,569 ounces of gold at an average price of $1,668 per ounce.

In line with my comments last November when we published our half year results, there is still a great deal of uncertainty affecting the world's financial markets and it remains likely that the USA and major European countries will resort to further quantitative easing to help stimulate stagnant economies. The consequence of these conditions provides potential for the gold price to increase and this would enhance the cash generation capability of Nalunaq.

Since last November the market prices of both zinc and lead have weakened, due to the general slowdown in manufacturing activity and the resultant over supply. Prices fell to $1,650 per tonne for zinc and $1,680 per tonne for lead but by 31 July 2012 they had recovered to $1,850 and $1,947 respectively. A recent report by Wood Macenzie predicts that the price of zinc may rise as high as $4,000 per tonne by 2015. That prediction may prove to be optimistic but I am of the opinion that Black Angel is likely to benefit from higher market prices if it can be brought into production by 2014/2015, as is now planned.

FINANCE

It is anticipated that the Black Angel mine will be funded by cash generated from gold sales, advance sales of zinc and lead, plus an element of debt and equity.

The Company will ultimately need to renegotiate its loans with Cyrus and to restructure the Group's balance sheet but these steps are unlikely to happen until a clear financing programme can be agreed and announced to shareholders.

THE FUTURE

The Group has laid some important foundations during the year under review. It has encountered some production setbacks since the year end, as reported by the Chief Executive in his report, but the fundamentals of the business remain positive, despite difficult market conditions. In the current year I expect the Company to generate trading profits and to secure funding for the Black Angel project.

THANKS TO THE TEAM

Finally, I would like to express my thanks to the team at Nalunaq in Greenland and those who are in support in the UK. I am delighted that the Nalunaq team are now in sight of achieving their target and that we now have a dedicated team working full time on the Black Angel project.

Frank Chapman

Chairman

30 August 2012

Enquiries:

 
Angel Mining plc 
 Nicholas Hall, Chief Executive Officer         07931 709 053 
 Kevin McNair, Chief Financial Officer           07900 690 908 
Fox-Davies Capital (Broker) 
 Daniel Fox-Davies/Simon Leathers                0203 463 5000 
 
 
  Bishopsgate Communications Limited 
  Nick Rome/ Anna Michniewicz/ Ivana Petkova     0207 562 3350 
 

Chief Executive Officer's Report

SUMMARY

During the year, we achieved the following milestones:

   --      Commenced commissioning gold production at Nalunaq in May 2011; 
   --      Achieved our first gold sales in August 2011; 
   --      Significantly strengthened the team in Greenland; and 

-- Completed the construction of the upper terminal of the cable car at Black Angel and hung the cables across the fjord.

Nalunaq

The mine at Nalunaq is targeting a vein of quartz hosted in Basalt which reposes at approximately 35 degrees parallel to the south face of the Mountain. The top part of the resource from the 600 meters level to 800 meters is known as the Mountain Block and it contains the highest grade ore. Typically this ore contains at least 50 grammes per tonne but it can be much higher. The central part of the deposit, which was most heavily mined by the previous owner of the mine, extends from the 270 meter level to the 600 meter level and is known as the Target Block. Grade varies but has averaged approximately 14.5 grammes per tonne. Below this part of the mine is the area known as South Block. Core drilling data indicated that the geological structure continued and it was assumed that there would be further gold resource to mine, going to greater depth, but it had been anticipated also that the grade would progressively reduce.

Production built slowly during 2011 following the initial pour in late May and this reflected the fact that there were many improvements needed to get the plant to operate with an acceptable level of efficiency in terms of gold recovery. By January 2012, the mine was close to achieving the lower end of its production target range and then the first of two setbacks hit the team. The first related to a critical pump for which parts had been ordered on time but the wrong parts were sent and it took two weeks for replacement parts to arrive from America costing the Company two valuable weeks of plant production.

The plant was back in production for a few days when, on 5(th) March 2012, the second setback occurred and the main generator on site failed. The stand-by generator was immediately brought into service but it is a smaller unit and could not produce enough power to run the crushing circuit. It took approximately six weeks to repair the generator and this stopped all crushing of ore during this period.

While the generator was being repaired, the process plant was unable to process ore mined during the period of enforced shutdown and the mining team were deployed on the construction of a bulkhead to create a new disposal area for tailings. This work has now created a very substantial area in the old workings which will outlive the needs of the mine. The mining crew then returned to the task of mining new ore and one of the main headings was the development in South Block.

The table below sets out the history of doré production and gold and silver sales since commissioning production commenced in May 2011:

 
              Doré Produced     Gold Sales   Silver 
                                                   Sales 
-----------  ---------------------  -----------  ------- 
              Kg        Ounces       Ounces       Ounces 
-----------  --------  -----------  -----------  ------- 
 2011 
-----------  --------  -----------  -----------  ------- 
 May          0.9       30           -            - 
-----------  --------  -----------  -----------  ------- 
 June         1.3       41           -            - 
-----------  --------  -----------  -----------  ------- 
 July         6.0       192          -            - 
-----------  --------  -----------  -----------  ------- 
 August       12.3      394          322          - 
-----------  --------  -----------  -----------  ------- 
 September    21.8      701          799          - 
-----------  --------  -----------  -----------  ------- 
 October      10.4      335          391          - 
-----------  --------  -----------  -----------  ------- 
 November     21.6      693          614          163 
-----------  --------  -----------  -----------  ------- 
 December     29.2      940          842          - 
-----------  --------  -----------  -----------  ------- 
 2012 
-----------  --------  -----------  -----------  ------- 
 January      32.4      1,042        432          - 
-----------  --------  -----------  -----------  ------- 
 February     17.0      545          1,043        143 
-----------  --------  -----------  -----------  ------- 
 March        15.0      481          430          - 
-----------  --------  -----------  -----------  ------- 
 April        -         -            -            82 
-----------  --------  -----------  -----------  ------- 
 May          40.7      1,309        1,125        - 
-----------  --------  -----------  -----------  ------- 
 June         27.5      883          765          - 
-----------  --------  -----------  -----------  ------- 
 July         29.3      941          806          183 
-----------  --------  -----------  -----------  ------- 
 

During the year, the Group did not reach the commercial production level defined for the Nalunaq gold mine, as set out in the Financial Review section of this report. As such, none of the gold and silver sales listed above have been recognised as revenue during the year. All sales have been offset against capital expenditure in the year. The Group is expected to reach commercial production in Q3 of 2012 if all ramp-up activities are successful.

In June 2012, the grade of the ore in the South Block started to deteriorate and the geologists realised that we were entering into an area of unexpected faulting. The nature of the faults was that they run with the quartz which is why it took a few days before the full extent of the problem was understood. It meant, however, that the ore which was processed in June was a lower grade than had been anticipated and the gold production was therefore less than planned. Consequently, mining has been terminated in this part of the mine so that men and machines can concentrate their efforts mining the remaining panels in other parts of the mine, preparing for the mining of pillars in the Target Block, and developing new exploratory headings and rises in the Mountain Block. It is still possible that mining could be re-established in South Block if additional geological work indicates the probability of there being economic resource.

A year ago, our team of geologists estimated that it had 102,800 tonnes of economic ore to mine. The current estimate is that there is 96,690 tonnes of high grade ore, which should yield approximately 35,000 ounces of gold. This figure is believed to be conservative as it is hoped that the Mountain Block will prove to contain much more ore than can currently be measured or inferred.

The current mine plan indicates that mining will continue until at least August 2014 and the process plant will continue to operate until all available ore has been processed. At a gold price of $1,600 per ounce and cost base of $800 per ounce, the mine would generate approximately $28 million of free cash. Hopefully this will be increased by further development within the Mountain Block.

When production ends, it is envisaged that all of the mining assets, buildings and mobile equipment will be transferred to Black Angel. The process plant will be mothballed as it is possible that it may be practical for the plant to process ore from other gold mines which are expected to be opened in the area. Several promising sites are currently being explored by Nuna Minerals and just one of them could lead to a second life for Nalunaq.

The geologist who discovered the Nalunaq deposit believes that there is a good chance that there will be other gold bearing veins in the same mountain and it is now planned to undertake some surface exploration to see if we can find evidence to support this theory. If the evidence is found, we will be keen to undertake more serious exploration during the summer of 2013.

Black Angel

The cable car needed to provide access to the mine across some 1.7 kilometres across the fjord and up to the adit entrance 600 metres above sea level, is now largely constructed. Both upper and lower terminals are fully constructed, the winding mechanism and controls are all in place and the main cables have been installed and tensioned. No more work will be done on site until funding for the project is in place. At that point, we will arrange for the gondolas to be fixed in place, the connecting cable to be drawn across the fjord and final commissioning to be undertaken. Work will then commence immediately on the construction of the mine and process plant.

A week was spent on site with our principle technical advisors and suppliers, GBM, Golders Associates, Qualter Hall, EMJ-Atcom, the senior Nalunaq team and Dr. Bob Dowdell, a consultant to the Group, last September to focus on some key issues which included:

   --      agreeing the ideal location for the process plant; 

-- assessing the Deep Ice Zone bulkhead and how to safely drain the 2 kilometre tunnel behind it;

   --      review source of clean water to feed the process plant; 

-- plan the layout of ground facilities at Maarmorilik and ensure that the materials handling plan can be fully automated; and

   --      treatment and disposal of tailings 

The trip was a great success. The perfect location was quickly found for the process plant within the old Angel Zone workings. There is sufficient physical space and the floor is on a slight slope which will help the plant to rely more on gravity than on pumping. The area can be kept separate from the rest of the mine with its own ventilation arrangements. It is also close to the main drive on the 600 meter level so material will be fed into the plant using the existing rail, a Granby tippler and conveyor. The Deep Ice Zone bulkhead will require work as water has weakened the rock wall to which the bulkhead is fixed. However, a number of possible solutions were put forward, so a study will be done nearer the time to determine exactly how it should be dealt with as the area needs to be secured before mining commences. The Deep Ice Zone can produce 90 litres of water per second which is more than enough for the needs of the process plant. The plant has been designed to recycle all of the water that will be extracted from both concentrate and tailings using a filter press. EMJ and Qualter Hall worked together to design the ground facilities to take maximum advantage of the topography and Golders Associates were able to expand on their proposal for the disposal of tailings. A large proportion of the tailings in phase 1 will be used in the pillar backfill and will become part of the mine support. The remainder will be taken by conveyor to walled-in sections for safe, long term disposal.

The revised financial model indicates a cash cost of $1,120 per tonne of zinc or lead and the net smelter return at $1,800 per sales tonne is $1,260 per tonne.

Recent discussions with potential funding sources suggested that we had to achieve two things to raise the funding:

   --      Produce a resource statement for the Deep Ice Zone; and 
   --      Demonstrate that the project is viable at current market prices for zinc and lead. 

Dr. Bob Dowdell has prepared an estimate of the potential resource in the Deep Ice Zone based on mineralisation intersections from the Cominco exploration programme. Unfortunately, the drill holes were not close enough for us to get a JORC compliant resource statement. Dr. Dowdell's estimate of the potential resource in the Deep Ice Zone totalled 2.6 million tonnes at an average grade of 5.5% Lead and 14.9% Zinc. The grade has been assumed to be the same as the workings in the Deep Ice Zone that were undertaken by Cominco before the mine closed.

The resource statement produced by Wardell Armstrong International Ltd. in 2007 confirmed a JORC compliant resource of 4.425 million tonnes at an average grade of 3.0% Lead and 8.6% Zinc. The Deep Ice Zone, which is not included in the 4.425 million tonnes, is therefore a very significant addition to the mine's potential.

The original bankable feasibility study from January 2008 was based on an average metal price of $2,500 per tonne but the project, at that time, did not provide for a processing plant to be built on site because it was considered to be too environmentally controversial. The current price is low and it reduces to $1,260 per tonne as a net smelter return when we adjust for shipping costs and the smelter's treatment costs.

To improve the project economics, we are investigating the possibility of building a hydro-electric power plant. A study undertaken in 1979 concluded that there is sufficient water in the South Lake to give us the potential of generating 9 megawatts and the process plant as currently designed, requires 4.4 megawatts and this power requirement may be reduced by using more efficient crushing machines. Golders Associates have suggested that the cost of a hydro-electric generation plant is in the region of $2 million to $4 million per megawatt which would indicate a cost range of $18 million to $36 million but this could potentially reduce the annual cost of fuel from $10.4 million to $3.5 million. The saving of $6.9 million each year would give pay back in three to five years. We now need to get proper cost and performance quotations to fully explore this opportunity.

People

The Group employed an average of 107 people during the year under review. Headcount peaked at 114 earlier this year but since then we have reduced the team to 104 as at 31 July 2012. This change reflects the team's efforts to reduce the cost base by working smarter and the fact some activities, like mine development, now require less men and machines.

Mike Buckland left in April 2012 to spend more time with his family in Angola having recruited Alex Hamilton as Head of Mineral Processing and Steve Ainsworth as Head of Mining in 2011. Alex and his deputy, John Simpson, have made significant improvements to the Nalunaq processing plant. Steve has transformed the mining operation by recruiting experienced hard rock miners and promoting the partial mining of pillars. Steve has also introduced new standards of health and safety, job risk assessments and weekly safety training sessions.

Steve left the Company in July 2012 to take up an opportunity near his home in Armenia. He will continue to work with us in an advisory capacity. Alex Hamilton has been appointed General Manager and Haraldur Haraldsson has been appointed Health & Safety and Environmental Superintendent. Nigel Handley joined the Company in late July 2012 as Joint General Manager of Nalunaq, General Manager of Angel Mining and Group Head of Mining.

The Black Angel Project team is currently led by myself and it comprises Joan Plant as project manager, Shaun Bentley as data control manager, Chris Hill as procurement officer and Nigel Handley as General Manager. The team is support by Bob Dowdell as technical consultant and continues to work closely with GBM for the plant design, Golders Associates for mine planning and water management and Qualter Hall for materials handling.

FINANCIAL REVIEW

The Group has a stated production target of 2,000 ounces of gold per month. Capitalisation of costs and associated sales from start-up operations continues until the mine is capable of operating as intended, which includes achieving and sustaining commercial production. The Group has determined that it will achieve commercial production when it is capable of producing 70% of its stated target production. The Group did not reach commercial production during the year. As a result, no revenue was recognised in the Consolidated Statement of Comprehensive Income. The Group sold $7,525,000 of gold during the period and these sales were offset against expenditure during the period which was capitalised. The operating loss of $2,804,000 does not, therefore, include any sales revenue achieved during the year or any associated mine operating costs. The operating loss of $2,804,000 is made up principally of Group overheads and foreign exchange losses.

During the period, the Group incurred finance charges of $3,074,000 which were primarily related to the Company's borrowings. The Group's borrowings at 29 February 2012 totalled $37,052,000 (2011: 29,038,000).

Capital expenditure during the year totalled $16,523,000 after credits for gold sales. This investment included commissioning and start-up activities at the Nalunaq gold mine and completion of the upper terminal for the cable car at the Black Angel mine.

Cyrus/FBC

In December 2011, Cyrus agreed to capitalise any accrued interest to 31 December 2011 on the loan and for the repayment terms of the loan to be amended so that the repayment date of the loan was extended to 31 December 2012. The Company is currently in technical default on this facility. This is discussed further in note 21 to the financial statements.

On 24 July 2012, Cyrus and FBC agreed to advance the Company an additional $1.75 million via the secured short term funding facility already in place. The advance is interest free and must be repaid by 30 November 2012. The Company also agreed to increase its management fee to Cyrus from 5% of deemed cash margin on sales to 6%. This change is in recognition of additional strategic advisory services which are being provided by Cyrus in relation to the Black Angel project.

Standby Equity Distribution Agreement ("SEDA")

On 24 April 2009, the Company entered into a GBP5.0 million ($7.3 million) SEDA with Yorkville, of which $812,509 was drawn down during the year to 29 February 2012 (2011: $6,417,608) through the issue of 12,229,423 shares at a price of 4.09p per share. The facility expired on 26 June 2011 having been largely utilised.

On 27 July 2011, the Company entered into a new GBP10.0 million ($16.0 million) SEDA with Yorkville. On the same date, the Company entered into a promissory note facility of up to $3,654,000 with the agreement of Yorkville. The Company had fully drawn down the funds available under the promissory note by 1 February 2012. The promissory note can, at the Company's election, be repaid either out of cash resources or through the issue of advance notices under the SEDA. The promissory note bears interest at 4% per annum and is repayable in instalments with the final instalment due on 30 September 2012. Amounts of principal outstanding under the promissory note are convertible at the option of Yorkville into ordinary shares at 3.0p per share. Due to the negative impact of the failure of the main generator at Nalunaq in March 2012, the Company was unable to meet all its repayments under the promissory note with Yorkville. The Company has chosen not to use the SEDA to meet these repayments to avoid excessive dilution of the shareholders. The promissory note is currently in technical default and the Company is in discussions with Yorkville to resolve this situation.

Subsequent to the year end, the Company has drawn down $1,229,309 through the issue of 60,007,071 shares at an average price of 1.30 pence per share.

Socius

On 31 August 2010, the Company signed an agreement for a $25.0 million financing facility with Socius which would enable the Company to issue 10 year 10% Eurobonds as it draws down on the facility. The financing facility contains certain conditions which must be met before an issue can be completed. On draw down of a portion of the facility, the Company would issue an option to Socius to subscribe for ordinary shares in the Company at the closing Angel Mining share price on the day before the draw down request ("the investment share price") for such number of ordinary shares in the Company that would have a value equal to 110% of the draw down amount. The Company would also issue warrants to Socius which could be exercised at any time for twelve months from the date of issue at the investment share price, for a value equal to 25% of the draw down amount. Socius could pay for the exercise of the options and warrants either in cash or in four year 2% loan notes, which may be offset against the Eurobond notes. The Eurobonds provide for an early redemption premium such that the loan notes, the Eurobond and interest commitments will cancel each other out at anniversary dates plus one day.

On 1 October 2010, the Company requested a drawn down of $3.0 million when the share price was 3.21p. In accordance with the terms of the facility, Angel Mining issued $3.0 million 10% loan notes and issued to Socius warrants over 10,885,714 ordinary shares in the Company and an option to subscribe for 47,897,142 ordinary shares in the Company. Socius subsequently exercised both the warrants and the option to subscribe for the full amount. These shares were paid for through the issue of a promissory note.

On 3 April 2011, the Company made an $8.0 million draw down request when the share price was 4.38p. The draw was to have been in two parts, a first tranche of $5.0 million and a second tranche of $3.0 million. The Company issued options and warrants over 153,996,951 shares in relation to the $8.0 million draw as per the terms of the programme agreement which Socius exercised immediately. On 19 May 2011, Socius advised the Company that it needed to change the terms of the second draw to reflect the recent fall in the share price. The Company exercised its right to abandon the draw down. As a result, Socius is in possession of 50,025,312 ordinary shares which relate to the $3.0 million tranche which was never completed. The Company and Socius are working together to arrange the return of these shares to the Company although this may take some time due to technical legal reasons. These shares are recognised as having been issued in the Company's financial statements.

GOING CONCERN

The Directors have prepared the financial statements on the going concern basis. The Directors consider that the greatest risks facing the Group are the ability to raise future funding, the continued support of Cyrus and the Group's ability to generate cash at Nalunaq gold mine. The ability to draw down against the Socius and Yorkville facilities is an important element impacting availability of cash.

As a result of the above, the Directors have concluded that a material uncertainty exists. This is discussed further in note 1a to the financial statements.

JOINT OWNERSHIP SHARE PLAN ("JSOP")

There were no awards of shares via the JSOP during the period. The accounts of the Employee Benefit Trust associated with the JSOP are consolidated within the Group financial statements. The scheme enables participants to benefit as though the scheme was an HMRC approved share option scheme.

UPAPPROVED SHARE OPTION SCHEME

During the period, the Company started a new Unapproved Share Option Scheme and awarded options over 15,000,000 shares to various employees. Some of those employees left the business during the year and their options lapsed. At 29 February 2012, there were options outstanding over 2,500,000 shares in the Company.

OUTLOOK

Once commercial production is achieved, Nalunaq should be cash generative for at least twelve months and we look forward to any resource that may be found by extending the working drives in Mountain Block. The Directors believe that the outlook for the price of gold during the life of the mine is positive. The assets from Nalunaq will then be used in the development and construction of Black Angel and the experienced team that we now have will transfer to the new mine.

Forecast and Historic Zinc Prices (2010-2025)

The challenge of raising finance for the Black Angel project is on hold while we investigate hydro-electric power generation. Hopefully, hydro-electric powered project can be prepared for financing in mid 2013. This is later than originally planned and production of zinc and lead concentrates may not therefore commence until H1 2015. Wood Macenzie, has a base case prediction for the price of zinc as being circa $3,000 per tonne in 2015 and therefore the profit opportunity for this project could be considerably enhanced as a result of this delay.

Nicholas Hall

Chief Executive Officer

30 August 2012

Consolidated Statement of Comprehensive Income

Year ended 29 February 2012

 
                                                         2012        2011 
                                                         $000        $000 
--------------------------------------------  ---  ----------  ---------- 
 Continuing operations 
 Operating costs                                      (2,804)     (3,384) 
-------------------------------------------------  ----------  ---------- 
 Operating loss                                       (2,804)     (3,384) 
 
 Finance costs                                        (3,074)     (4,444) 
 Finance revenue                                          344          42 
 Change in fair value of assets held for 
  trading                                                   -          13 
 Loss before tax                                      (5,534)     (7,773) 
 Taxation                                                   -           - 
--------------------------------------------  ---  ----------  ---------- 
 Retained loss for the financial year                 (5,534)     (7,773) 
-------------------------------------------------  ----------  ---------- 
 Loss per share 
 Basic and diluted loss per share (cents)              (0.75)      (2.11) 
-------------------------------------------------  ----------  ---------- 
 
 Other comprehensive gain for the year 
 Exchange translation difference on foreign 
  operations                                              188         339 
 Total comprehensive loss for the year 
  attributable 
  to ordinary equity holders of the company           (5,346)     (7,434) 
 
 

Consolidated and Company Statement of Financial Position

29 February 2012

 
                                                               Group                          Company 
                                                     ------------------------         ---------------------- 
                                                            2012         2011                2012       2011 
                                                            $000                             $000 
                                                                         $000                           $000 
----------------------------------  ----  ---------  -----------  -----------  -----  -----------  --------- 
 Non-current assets 
 Property, plant 
  and equipment                                           64,802       48,297                   4          6 
 Investments in subsidiaries                                   -            -               9,670      9,670 
 Note receivable                                           2,803            -               2,803          - 
 Rehabilitation deposit                                    4,326        4,414                   -          - 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
                                                          71,931       52,711              12,477      9,676 
  -------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 Current assets 
 Inventories                                               1,355          862                   -          - 
 Trade and other 
  receivables                                                 44          137              60,703     48,054 
 Other financial 
  asset                                                    1,257        1,260               1,257      1,260 
 Cash and cash equivalents                                   667          441                 642        395 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
                                                           3,323        2,700              62,602     49,709 
  -------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 Current liabilities 
 Trade and other 
  payables                                              (10,163)      (7,769)             (2,114)    (3,289) 
 Current borrowings                                     (29,206)     (21,848)            (29,206)   (21,848) 
 Current provisions                                        (722)      (1,333)               (722)    (1,333) 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
                                                        (40,091)     (30,950)            (32,042)   (26,470) 
  -------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 
 Net current (liabilities)/assets                       (36,768)     (28,250)              30,560     23,239 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 Total assets less 
  current liabilities                                     35,163       24,461              43,037     32,915 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 
 Non-current liabilities 
 Non-current borrowings                                  (7,846)      (7,190)             (7,846)    (7,190) 
 Non-current provisions                                  (4,831)      (4,398)                   -          - 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
                                                        (12,677)     (11,588)             (7,846)      7,191 
  -------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 Net assets                                               22,486       12,873              35,191     25,725 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 
 Capital and reserves 
 Share capital                                            14,915        8,052              14,915      8,052 
 Share premium                                            47,904       39,455              47,904     39,455 
 Own shares held 
  by EBT                                                 (2,568)      (2,568)             (2,568)    (2,568) 
 Convertible borrowings 
  - equity component                                       7,371        7,371               7,371      7,371 
 Share option reserve                                         23            -                  23          - 
 Translation reserve                                     (1,029)        (841)                   -          - 
 Retained deficit                                       (44,130)     (38,596)            (32,454)   (26,585) 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 Total equity                                             22,486       12,873              35,191     25,725 
---------------------------------------------------  -----------  -----------  -----  -----------  --------- 
 
 
 

Consolidated and Company Statement of Cashflows

Year ended 29 February 2012

 
                                                  Group                Company 
                                          --------------------  -------------------- 
                                               2012       2011       2012       2011 
                                               $000       $000       $000       $000 
----------------------------------------  ---------  ---------  ---------  --------- 
 Loss before tax                            (5,534)    (7,773)    (5,869)    (4,707) 
 Adjusted for: 
 Depreciation of property, plant 
  and equipment                                   5          4          5          4 
 Change in fair value of assets                   -       (13)          -          - 
  held for trading 
 Loss/(gain) on disposal of property,             -         26          -          - 
  plant and equipment 
 Finance income                               (344)       (42)      (292)          - 
 Finance costs                                3,074      4,444      4,223      4,402 
 Share-based payments                         (678)        298      (678)        298 
 Reversal of/(provision) against 
  investments in assets held for 
  trading/associate                               -          -          -       (13) 
 Increase in inventories                      (493)       (12)          -          - 
 Increase/(decrease) in trade and 
  other receivables                             128        725         48         46 
 Increase/(decrease) in trade and 
  other payables                              3,077        321      1,043        176 
 Net cash (outflow)/ inflow from 
  operating activities                        (765)    (1,632)    (1,520)        206 
----------------------------------------  ---------  ---------  ---------  --------- 
 Investing activities 
 Loans to subsidiary companies                    -          -   (13,358)   (18,156) 
 Purchase of property, plant and 
  equipment                                (14,063)   (16,119)        (3)          - 
 Increase in other financial assets               -      (135)          -      (135) 
 Interest received                               17         42          -          - 
 Proceeds from disposal of assets 
  held for trading                                -        197          -        197 
 Cash outflow from investing activities    (14,046)   (16,015)   (13,361)   (18,094) 
----------------------------------------  ---------  ---------  ---------  --------- 
 Financing activities 
 Equity share capital subscription, 
  net                                         7,519      6,418      7,519      6,418 
 Draw down from Socius facility               5,000      3,000      5,000      3,000 
 New borrowings, net of costs                 2,972      6,400      2,972      6,400 
 Repayment of borrowings                      (358)          -      (358)          - 
 Cash flows from financing activities        15,133     15,818     15,133     15,818 
----------------------------------------  ---------  ---------  ---------  --------- 
 
 Net (decrease)/increase in cash 
  and cash equivalents                          322    (1,829)        252    (2,054) 
 Cash and cash equivalents at start 
  of year                                       441      1,823        395      1,808 
 Exchange movements                            (96)        447        (5)        657 
----------------------------------------  ---------  ---------  ---------  --------- 
 Cash and cash equivalents at end 
  of year                                       667        441        642        395 
----------------------------------------  ---------  ---------  ---------  --------- 
 

The above information has been extracted from the financial statements of Angel Mining plc, registered number 3319691, which were approved by the Board of Directors, authorised for issue on 31 August 2012 and signed on its behalf by: Nicholas Hall, Chief Executive Officer.

Copies of the Report and Accounts will be posted to shareholders shortly and are available for download from the Company's website: www.angelmining.com. The Company has also today given notice that the 2012 Annual General Meeting of the Company (AGM) is to be held at 12.00 p.m. on 24 September 2012 at the offices of Davenport Lyons, 30 Old Burlington Street, London, W1S 3NL. The notice convening the AGM is set out in a letter accompanying the Report and Accounts.

This information is provided by RNS

The company news service from the London Stock Exchange

END

FR EAKPEDLSAEFF

Angel Mining (LSE:ANGM)
過去 株価チャート
から 5 2024 まで 6 2024 Angel Miningのチャートをもっと見るにはこちらをクリック
Angel Mining (LSE:ANGM)
過去 株価チャート
から 6 2023 まで 6 2024 Angel Miningのチャートをもっと見るにはこちらをクリック