We refer to our announcements dated 23 May 2014, 4 August 2014,
28 October 2014 and 28 November 2014
The Independent Tester, Faithful & Gould Limited
("F&G"), has yet to issue a completion certificate in respect
of phase 8 of the project. Separately Healthcare Support
(Newcastle) Limited ("HSN"), Laing O'Rourke Construction Limited
("LOR") and Newcastle Upon Tyne Hospitals NHS Foundation Trust (the
"Trust") have attempted to settle the dispute through a formal
mediation process as required under the Project Agreement. As the
formal mediation did not resolve the dispute HSN issued proceedings
on 17 November 2015 under Part 7 of the Civil Procedure Rules
against the Trust and LOR in accordance with the provisions of the
Project Agreement and the Construction Contract.
Given the longstop date under the Project Agreement is 28
October 2014 the Trust, HSN and LOR entered into an agreement with
effect from 1 February 2015 whereby the Trust has undertaken to
provide 7 days notice of an intention to terminate the Project
Agreement. The notice period will allow HSN adequate time to seek
an injunction from the Court to prevent a wrongful termination.
HSN continues to engage with the Majority Creditors.
Ends
This information is provided by RNS
The company news service from the London Stock Exchange
END
MSCGCBDBLUDBGUG
(END) Dow Jones Newswires
November 20, 2015 06:00 ET (11:00 GMT)
Hlthcare2.187% (LSE:73FU)
過去 株価チャート
から 11 2024 まで 12 2024
Hlthcare2.187% (LSE:73FU)
過去 株価チャート
から 12 2023 まで 12 2024
Real-Time news about Hlthcare2.187% (ロンドン証券取引所): 0 recent articles
その他のHlthcare2.187%ニュース記事